1.
This is the 39th monthly Environmental Monitoring
and Audit (EM&A) Report for the First Phase Development of Kwu Tung North (KTN) and Fanling North
(FLN) New Development Areas (NDAs), comprising the Advance Works and First
Stage Works (hereinafter called the
¡§the
Project¡¨). This report is prepared
by Wellab Limited under ¡§Service Contract No. NDO
04/2019 Environmental Team for Environmental Monitoring and Audit Works in
Construction Phase for the First Phase Development of KTN and FLN NDAs¡¨ (hereinafter called
the ¡§Service Contract¡¨). This report documents the findings of EM&A works conducted in January 2023.
2.
During the reporting month, the following
Works Contracts under relevant Environmental Permit(s) were undertaken for the
Project:
Table I Works
Contracts under relevant Environmental Permit(s) in the Reporting Month
Works Contracts |
Environmental Permit No. |
Designated Project (DP) |
Commencement date of construction |
Contract No. ND/2019/01 ¡V Kwu Tung North New Development Area,
Phase 1: Site Formation and Infrastructure Works |
EP-466/2013/A |
Castle Peak Road Diversion |
12 August 2020 |
EP-467/2013/A |
Kwu Tung North New Development Area Road P1
and P2 and Associated New Kwu Tung Interchange and
Pak Shek Au Interchange Improvement |
12 August 2020 |
|
Kwu Tung North New Development Area Road D1
to D5 |
1 June 2020 |
||
Utilization of Treated Sewage Effluent
(TSE) from Shek Wu Hui Sewage Treatment Works |
23
March 2020 |
||
Contract No. ND/2019/02 ¡V Kwu Tung North New Development Area,
Phase 1: Roads and Drains between Kwu Tung North
New Development Area and Shek Wu Hui |
EP-469/2013 |
Sewage Pumping Stations in Kwu Tung North New Development Area |
28
October 2020 |
Contract No. ND/2019/03 ¡V Kwu Tung North and Fanling North New Development Areas, Phase 1: Development
of Long Valley Nature Park |
Kwu Tung North New Development Area Road D1
to D5 |
3 July
2020 |
|
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
6
October 2020 |
|
Contract No. ND/2019/04 ¡V
Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shek
Wu San Tsuen North to Lung Yeuk Tau) |
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
23
February 2021 |
EP-546/2017 |
Fanling North Temporary Sewage Pumping Station |
16
February 2021 |
|
Contract
No. ND/2019/05 ¡V
Fanling North New Development Area, Phase 1: Fanling
Bypass Eastern Section (Shung Him Tong to Kau Lung
Hang) |
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
1
August 2020 |
Contract No. ND/2019/06 ¡V
Fanling North
New Development Area, Phase 1: Re-provisioning of North District Temporary
Wholesale Market for Agricultural Products |
Reprovision of temporary Wholesale
Market in Fanling North New Development Area |
29
October 2019 |
|
Contract No. ND/2019/07 ¡V
Fanling North New
Development Area, Phase 1: Site Formation and Infrastructure Works |
Works area
not under relevant Environmental Permit for Phase 1 of the Project. |
1 March 2021 |
3.
A summary of the EM&A activities in
this reporting month is listed in Table
II below:
Table II Summary
Table for EM&A Activities in the Reporting Month
EM&A
Activities |
Monitoring
Station (s) |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
||
1-hr Total Suspended Particulates (TSP) Monitoring |
FLN-DMS1 |
N/A |
N/A |
4, 10, 16, 20 and 26 Jan 23 |
4, 10, 16, 20 and 26 Jan 23 |
N/A |
N/A |
N/A |
FLN-DMS3 |
N/A |
N/A |
4, 10, 16, 20 and 26 Jan 23 |
|||||
FLN-DMS5 |
3, 9, 13, 19, 26 and 31 Jan 23 |
3, 9, 13, 19, 26 and 31 Jan 23 |
N/A |
|||||
KTN-DMS4(B) |
3, 9, 13, 19, 26 and 31 Jan 23 |
3, 9, 13, 19, 26 and 31 Jan 23 |
N/A |
|||||
24-hr TSP Monitoring |
FLN-DMS1 |
N/A |
N/A |
3, 9, 13, 19, 26 and 31 Jan 23 |
3, 9, 13, 19, 26 and 31 Jan 23 |
N/A |
N/A |
N/A |
FLN-DMS3 |
N/A |
N/A |
3, 9, 13, 19, 26 and 31 Jan 23 |
|||||
FLN-DMS5A |
3, 9, 13, 19, 26 and 31 Jan 23 |
3, 9, 13, 19, 26 and 31 Jan 23 |
N/A |
|||||
KTN-DMS4(B) |
3, 9, 13, 19, 26 and 31 Jan 23 |
3, 9, 13, 19, 26 and 31 Jan 23 |
N/A |
|||||
Noise Monitoring |
CP-FLN-NMS1 |
N/A |
4, 10, 16 and 27
Jan 23 |
N/A |
||||
CP-FLN-NMS2 |
N/A |
4, 10, 16 and 27 Jan 23 |
N/A |
|||||
CP-KTN-NMS2 |
3, 9, 19, 26 and 31 Jan 23 |
N/A |
N/A |
|||||
CP-KTN-NMS3 |
||||||||
CP-KTN-NMS5 |
||||||||
CP-KTN-NMS6 |
N/A |
3, 9, 19, 26 and 31 Jan 23 |
||||||
Ecological Survey |
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley |
N/A* |
N/A* |
5, 6, 11, 12, 19, 20, 26 and 27 January 23 |
5, 12, 19 and 26 January 23 |
N/A* |
N/A* |
N/A* |
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San
Tsuen Stream |
N/A* |
N/A* |
N/A* |
N/A* |
N/A* |
N/A* |
N/A* |
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from
Disturbance and Pollution |
13 and 18 January 23 |
13 and 18 January 23 |
18 January 23 |
18 January 23 |
18 January 23 |
N/A* |
N/A* |
|
24-hr RSP (Ambient Arsenic)
Monitoring for Land Contamination |
4, 10, 16, 21 and 27 Jan 23 |
N/A |
4, 10, 16, 21 and 27 Jan 23 |
N/A |
N/A |
N/A |
N/A |
|
Water Quality Monitoring |
N/A |
3, 5, 7, 9, 11, 13, 16, 18, 20, 26, 28 and 30 Jan 23 |
N/A |
3, 5, 7, 9, 11, 13, 16, 18, 20, 26, 28 and 30 Jan 23 |
N/A |
N/A |
N/A |
|
Landfill Gas Monitoring |
30 Jan
23 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Built Heritage Monitoring |
N/A |
N/A |
N/A |
Daily assessment subject to construction
works conducted within assessment area |
Daily assessment subject to construction
works conducted within assessment area |
N/A |
N/A |
|
3, 10, 17, 27 and 31 Jan 23 |
4, 13, 18 and 26 Jan 23 |
6, 13, 17 and 27 Jan 23 |
5, 12, 16 and 26 Jan 23 |
3, 9, 19, 26 and 30 Jan 23 |
5, 12, 16 and 26 Jan 23 |
6, 12, 20 and 27 Jan 23 |
Remarks:
N/A ¡V No relevant monitoring is required
according to the updated EM&A Manual
N/A* ¡V No relevant monitoring is required
according to the Baseline Ecological Monitoring Plan (Table 3.1)
[1]
Since the distance between monitoring station CP-KTN-NMS2 and site boundary of
ND/2019/03 under EP-468/2013/A exceeds 300m, the monitoring station is not
applicable to ND/2019/03
[2]
Since the distance between monitoring station CP-KTN-NMS3 and site boundary of
ND/2019/03 under EP-468/2013/A exceeds 300m, the monitoring station is not
applicable to ND/2019/03
[3]
Since the distance between monitoring station CP-KTN-NMS1 and site boundary of
ND/2019/02 under EP-469/2013 exceeds 300m, the monitoring station is not
applicable to ND/2019/02
[4]
Since the distance between monitoring station FLN-DMS1 and site boundary of
ND/2019/05 under EP-473/2013/A exceeds500m, the monitoring station is not
applicable to ND/2019/05
[5]
Since the distance between monitoring station FLN-DMS3 and site boundary of
ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 500m, the monitoring
station is not applicable to ND/2019/03 and ND/2019/04
[6]
Since the distance between monitoring station FLN-DMS5 and site boundary of
ND/2019/05 under EP-473/2013/A exceeds 500m, the monitoring station is not
applicable to ND/2019/05
[7]
Since the distance between monitoring station CP-FLN-NMS2 and site boundary of
ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 300m, the monitoring
station is not applicable to ND/2019/03 and ND/2019/04
[8]
Since the distance between monitoring station CP-FLN-NMS1 and site boundary of
ND/2019/03 under EP-473/2013/A exceeds 300m, the monitoring station is not applicable to ND/2019/03
4.
Summary of the environmental exceedances
of the reporting month is tabulated in Table
III.
Table III Summary Table for Events Recorded
in the Reporting Month
Environmental
Monitoring |
Parameter |
No. of
non-project related Exceedances |
Total No. of
non-project related Exceedances |
No.
of Exceedance related to the Construction Works of the Contract |
Total No. of Exceedance related to the Construction
Works of the Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||||
Air
Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hr RSP (Ambient Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
0 |
0 |
Water
Quality [1] |
DO |
0 |
0 |
0 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
|
SS |
0 |
0 |
0 |
0 |
0 |
0 |
|
Arsenic |
0 |
0 |
0 |
0 |
0 |
0 |
|
Landfill Gas |
O2 |
0 |
0 |
0 |
0 |
0 |
0 |
CH4 |
|||||||
CO2 |
|||||||
Cultural heritage |
Built Heritage Monitoring |
0 |
0 |
0 |
0 |
0 |
0 |
Air Quality
5. All construction air quality monitoring was conducted as scheduled in the
reporting month. No Action/Limit Level exceedance was recorded.
Construction Noise
6.
All construction noise monitoring was
conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
Water Quality
7. All additional
water quality monitoring was conducted as scheduled in the reporting month. No
Action /Limit Level Exceedance was recorded. No construction of channel for
alternation of natural streams was carried out in the reporting month. Therefore, no water quality monitoring was
conducted according to the Updated
EM&A Manual and Baseline Water Quality Monitoring Report (KTN & FLN
NDA). Relevant details are given in Section
5.
Land Contamination
8. All
ambient arsenic monitoring was conducted as scheduled in the reporting month.
No Action/Limit Level exceedance was recorded.
Landfill Gas Monitoring
9. Monitoring
of landfill gas in the reporting month was carried out by the Contractor under
ND/2019/01 at excavation location Portion 6b. No Limit Level exceedance was recorded.
Built Heritage Monitoring
10. Built
heritage monitoring was carried out in the reporting month by the Contractor
under ND/2019/05 for surveyed cultural heritage. No Limit Level exceedance was
recorded.
Ecological Monitoring
11. All ecological monitoring was conducted as scheduled in the reporting
month. The monitoring result is shown in Appendix
L and will be compared with the Action/Limit level after the issuance of
Final Baseline Ecological Report.
Complaint Log
12. Two
environmental complaints were received in the reporting month. The complaint
regarding muddy water discharged at Sheung Yue River is for ND/2019/01 and
ND/2019/02, which was referred by EPD on 12 Jan 2023 for the complaint case
received by EPD on 11 Nov 2022.
13. The
other complaint regarding polluting effluent discharged near On Lok Garden is
for ND/2019/05. This complaint case was received by EPD on 29 January 2023 and
referred to ET and IEC on 3 February 2023. The investigation is in progress and
the detail will be reported in the next monthly EM&A report (February
2023).
Notification of Summons and
Successful Prosecutions
14. No
notification of summons or successful prosecutions was received in the
reporting month.
15. This
report has been prepared in compliance with the reporting requirements for the
subsequent monthly EM&A Report as required by the ¡§Updated Environmental
Monitoring and Audit Manual for Advance and First Stage Works of Kwu Tung North and Fanling North
New Development Areas¡¨ (Updated EM&A Manual).
16. The major site activities for the coming three
months are shown in Table IV.
Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities
(February to April 2023) |
ND/2019/01 |
(a)
Site
Clearance, tree felling, removal of existing structures, site formation and
G.I works in Portion 1a (b)
Excavation,
backfilling, drainage works, construction of hoarding/fencing, road works and
noise barrier in Portion 1b (c)
Site
clearance, site formation in Portion 1c (d)
Temporary
storage of material and site formation in Portion 1e (e)
Site
clearance, tree felling, site formation work and construction of subway in
Portion 2 (f)
Excavation,
backfilling and drainage works in Portion 3 (g)
Drainage
works, watermain, excavation, backfilling, road works, sheet piling and pipe
jacking in Portion 5 (h)
Drainage
works, backfilling, road works and watermains work and socket H piling in
Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
formation, sheet piling, excavation and drainage works in Portion 7 (k)
Construction
of retaining wall, RC construction of flushing water service reservoir and fresh
water reservoir, pipe pile wall of WSD¡¦s maintenance access and backfilling
works in Portion 8a (l)
ELS for
jacking pit at LWSC¡¦s car park and trenchless work, excavation and watermain
construction and trial pit in Portion 8b (m)
Sheet
piling, excavation, drainage works and constructure of retaining wall, soil
nail and watermain construction in Portion 9b (n)
Stockpile
of soil in Portion 9c (o)
Excavation,
drainage works, road construction and utilities works
in Portion 10a (p)
Sheet
piling, excavation and drainage works in Portion 10b (q)
Site clearance, tree felling, remove of existing
structure in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road work
at Yin Kong Road -
Construction
of Pai Lau (b)
Portion 2
to Portion 20C -
Erection of Permanent Boundary Structure -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Wetland Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree Felling (b)
Pile Cap (c)
Bored Piling (d)
Excavation (e)
Sheet Piling (f)
Drainage Works (g)
Grouting (h)
Road works (i)
ELS |
ND/2019/05 |
(a)
North Team Works -
ELS works and Pile cap construction at B1-01M,
B2-02, B2-03, C1-01a, C2-03b, C2-04b, C3-01b, D2-01 -
Pier construction at C1-01a C3-01b, C2-03b,
C2-04b, D2-01 & E2-01. -
Pier head construction at C3-01b, C1-01a &
E2-01 -
Cross head construction at C2-02, C3-02. -
Slope works, road works and drainage works at Jockey Club Road (3SW-C/F63), Tong Hang Junction
and Portion VI (FS28 & 29) (b)
Viaduct Works -
Segment fabrication for bridge C2 & D1 &
E1. -
Segments erection for bridges C3, D1 and E1. -
3rd set FT design and fabrication. To be used in
Feb-2023. -
4th set FT design and fabrication. To be used in
May-2023. -
Complete construction of pile cap D2-01 and
installation of cast-in rotation bridge components. -
Complete erection of tower crane at D2-02, and
E2-02. -
Complete segment erection for C4-02 T-Span. -
Complete segment casting for E2-02 and E3-03. (b) South
Team Works -
TWSRW ¡V Road work (section ch
250 to 450). -
TWSR (West) ¡V Slope work for FS06. Soil nail for
FS04. 132KV ducts laying at FS04. Outage of 132 kv. -
TWSR (East) ¡V Form D300 new road, BBI footing -
HKY FB (East) ¡V Erection of steel bridge -
HKY FB (West) ¡V Construction of LT2 -
E2-03 ¡V Pier construction. -
D2-03 ¡V Pier construction. -
E3-05M and E4-01 ¡V cap construction. -
NB109 ¡V base slab construction. |
ND/2019/06 |
The construction phase has been completed and
handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1,
2, 4 and 5 (c)
Construction of box culvert at Portion
2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at
Portion 4 (f)
Drainage works, Sewerage works at
Portion 1, 3, 4 and 5 (g)
Mini piling works at Portion 4 (h)
Construction of noise barrier at
Portion 4 and 5 (i)
Waterworks at Portion 1 |