11.1 One (1) Limit Level for DO of impact water
quality monitoring was recorded. After investigation, the exceedance was
considered due to the other external factors rather than the contract works.
11.2 One (1) Action Level for construction noise was
recorded as one complaint about construction noise was received during the
reporting month. No Action/Limit Level exceedance for air quality,
ambient arsenic, landfill gas monitoring and build heritage monitoring was
recorded in the reporting month. The summary of exceedance recorded in the reporting month is shown in
Appendix O.
11.3 Ecological monitoring was carried out in the reporting
month. The results will be compared with Action and Limit Levels after issuance
of the Final Baseline Ecological Report.
11.4 Should the monitoring results of the environmental
monitoring parameters at any designated monitoring stations indicate that
Action / Limit Levels are exceeded, the actions in accordance with the Event/Action
Plan in Appendix N would be carried
out.
11.5 No environmental non-compliance was recorded in the
reporting month.
11.6 One environmental
complaint was received in the reporting month. The complaint is for ND/2019/01.
The investigation of the environmental complaint regarding polluting effluent
discharge for ND/2019/05 in the last report was completed. The Cumulative Complaint Log since the commencement
of the Project is presented in Appendix S.
11.7
There was no
successful environmental prosecution or notification of summons received since
the Project commencement. The Cumulative Log for environmental summon and
successful prosecution since the commencement of the Project is presented in Appendix T.