Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities (March to May 2023) |
ND/2019/01 |
(a)
Site
Clearance, tree felling, removal of existing structures, site formation and
G.I works in Portion 1a (b)
Excavation,
backfilling, drainage works, construction of hoarding/fencing, road works and
noise barrier in Portion 1b (c)
Site
clearance, site formation and socket H piling in Portion 1c (d)
Temporary
storage of material and site formation in Portion 1e (e)
Site
clearance, tree felling, site formation work and
construction of subway in Portion 2 (f)
Excavation,
backfilling and drainage works in Portion 3 (g)
Drainage
works, watermain, excavation, backfilling, road works, sheet piling and pipe
jacking in Portion 5 (h)
Drainage
works, backfilling, road works and watermains work in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
formation, sheet piling, excavation and drainage works in Portion 7 (k)
Construction
of retaining wall, RC construction of flushing water service reservoir and
fresh water reservoir, pipe pile wall of WSD¡¦s maintenance access and
backfilling works in Portion 8a (l)
ELS for
jacking pit at LWSC¡¦s car park and trenchless work, excavation and watermain
construction and trial pit in Portion 8b (m)
Sheet
piling, excavation, drainage works and constructure of retaining wall, soil
nail and watermain construction in Portion 9b (n)
Stockpile
of soil in Portion 9c (o)
Utilities
works in Portion 10a (p)
Sheet
piling, excavation and drainage works in Portion 10b (q)
Site clearance, tree felling, remove of existing
structure in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road work
at Yin Kong Road -
Construction
of Dwarf Wall (b)
Portion 2
to Portion 20C -
Erection of Permanent Boundary Structure -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Wetland Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree Felling (b)
Pile Cap (c)
Bored Piling (d)
Excavation (e)
Sheet Piling (f)
Drainage Works (g)
Grouting (h)
Road works (i)
ELS (j)
Pre-drill |
ND/2019/05 |
(a)
North Team Works -
ELS works and Pile cap construction at B2-01,
B2-02, B2-03, C1-01a, C2-03b, C2-04b, C3-01b & D2-01 -
Pier construction at C1-01a, C3-01b, C2-03b,
C2-04b, D2-01 & E2-01. -
Pier head construction at C3-01b, C1-01a &
E2-01 -
Cross head construction at C2-02, C3-02. -
Slope works, road works and drainage work at
Jockey Club Road (3SW-C/F63), Tong Hang Junction and Portion VI (FS28 &
29) (b)
Viaduct Works -
Segment fabrication for bridge C2 & D1 &
E1. -
Segments erection for bridges C3, D1 and E1. -
3rd set FT design and fabrication. To be used in
Feb-2023. -
4th set FT design and fabrication. To be used in
May-2023. -
Complete construction of pile cap D2-01 and
installation of cast-in rotation bridge components. -
Complete erection of tower crane at E2-02. -
Complete segment erection for C4-02 T-Span. -
Complete segment casting for E2-02 and E3-03. (b) South
Team Works -
TWSRW ¡V Road work (section ch
250 to 450). -
TWSR (West) ¡V Slope work for FS06. Soil nail for
FS04. 132KV ducts laying at FS04. Outage of 132 kv. -
TWSR (East) ¡V Form D300 new road, BBI footing -
HKY FB (East) ¡V Erection of stair case -
HKY FB (West) ¡V Construction of LT2 -
E2-03 ¡V Pier construction. -
E3-05M and E4-01 ¡V cap construction. -
NB109 ¡V bay 5~8, base slab construction. |
ND/2019/06 |
The construction phase has
been completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1,
2, 4 and 5 (c)
Construction of box culvert at Portion
2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at
Portion 4 (f)
Drainage works, Sewerage works at
Portion 1, 3, 4 and 5 (g)
Mini piling works at Portion 4 (h)
Construction of noise barrier at
Portion 4 and 5 (i)
Waterworks at Portion 1 |