Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site Activities
(February 2023) |
ND/2019/01 |
(a)
Site clearance, removal of existing structures at Portion 1a (b)
Excavation, backfilling and drainage works at Portion 1b (c)
Site clearance and site formation at Portion 1c (d)
Temporary storage of material at Portion 1e (e)
Site clearance, site formation and construction of subway at
Portion 2 (f)
Site clearance, excavation, sheet piling and drainage works at
Portion 3 (g)
Drainage works, excavation, backfilling and sheet piling at
Portion 5 (h)
Drainage works and backfilling at Portion 6a (i)
Operation of HAC soil treatment facility at Portion 6b (j)
Drainage works, excavation and backfilling at Portion 7 (k)
Construction of retaining wall, RC construction of flushing & fresh water service reservoir and
backfilling works at Portion 8a (l)
ELS for jacking pit at LWSC¡¦s car park, excavation for jacking
pit, trenchless work, watermain
construction and trial pit at Portion 8b (m)
Sheet piling, excavation, drainage works, construction of
retaining wall, watermain construction and soil nail at Portion 9b (n)
Stockpile of soil at Portion 9c (o)
Excavation and road works at Portion 10b |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road work
at Yin Kong Road -
Construction
of Pai Lau (b)
Portion 2
to Portion 20C -
Erection of Permanent Boundary Structure -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Wetland Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree Felling and transplant (b)
Pile Cap (c)
Excavation (d)
Sheet Piling (e)
Road works (f)
Pre-drill (g)
Grouting (h)
ELS |
ND/2019/05 |
(a)
The segment erection using launching gantry is
critical to completion of section 4. (b)
The pier D2-01 and E2-01 construction with bridge
rotation system is critical to completion of section 5. (c)
The in-situ T-span construction by form traveler
at E2-02 and E3-03 is also critical to section 5 completion. |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 1, 3 and 4 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Waterworks at Portion 1 |