2.1
The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of
land and housing supply in the medium and long term. The development of the KTN
and FLN NDAs will be implemented in phase for full completion by 2031. The
Phase 1 of the NDAs development, comprising the Advance Works and First Stage
Works, is targeted to be implemented from the second half of 2019
progressively. The Advance and First Stage Works would include site formation,
engineering infrastructure works (including roads, drainage, sewerage,
waterworks, landscaping works, pumping stations, and fresh water and flushing
water service reservoirs), soil remediation, reprovisioning of North District
Temporary Wholesale Market, development of a nature park at Long Valley and
implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling
Bypass (FLBP(E)) connecting the FLN NDA to Fanling
Highway and other roads with footpaths and cycle tracks, and associated
junction/ road improvements;
iii)
engineering
infrastructure works including drainage. Sewerage (including two sewage pumping stations), waterworks (including a fresh
water service reservoir and a flushing water service reservoir in the KTN NDA),
landscape works and slopeworks;
iv)
part
expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);
v)
reprovisioning
works; and
vi)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River
for connection between these two facilities;
ii)
reprovisioning
of two egretry sites in the FLN NDA and enhancement
works to an existing egretry site in the KTN NDA;
iii)
site
formation of land for a village resite
area and a district police station in the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds, and
landscape works; and
v)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule
3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October
2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director
of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs
under the Project and the respective Work Contracts are summarised in Tables
2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
|
|||||||
Kwu Tung North New
Development Area Road P1 and P2 and Associated New Kwu
Tung Interchange and Pak Shek Au Interchange Improvement |
ü |
|
|||||||
Kwu Tung North New
Development Area Road D1 to D5 |
ü |
ü |
|
||||||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
ü |
|
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
|
|||||||
Fanling Bypass Eastern
Section |
ü |
ü |
ü |
|
|||||
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
ü |
|
|||||||
EP-546/2017 |
Fanling North Temporary
Sewage Pumping Station |
ü |
|
Notes:
C1: ND/2019/01 C2: ND/2019/02 C3: ND/2019/03 C5A:
ND/2019/04
C5B:
ND/2019/05 C6: ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental
Permit (EP) No. |
Work
Contract(s) |
Scope
of Works under concerned EP(s) |
Site
Layout Plan under concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak Road and join with the Pak
Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road (P1)
within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor roads (D1,
D3, D4 and part of D5) within Kwu Tung North New
Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley and
ecological mitigation and enhancement works for the nature park (Condition
2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station in Kwu Tung North with installed capacity of more than 2,000
m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and watermain
for the reuse of treated sewage effluent for reuse in Kwu
Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment of alternative egretry sites and enhance
the existing egretry site at Ho Sheung Heung and/or
its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor inside
FLN NDA, which provides a linkage between the Man Kam To
Road and the proposed Fanling Bypass Eastern
Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will have
approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage pumping
station in Fanling North with installed capacity
(average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark:
The EP(s) not related to the Project of the First
Phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) Development
Areas are not included in the Table.
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
The
required submissions and submission status under Environmental Permits are
shown in Appendix U.
2.6
The
site
layout
plans
under concerned Environmental Permits are shown in Figures
12 - 22.
2.7
Different
parties with different levels of involvement in the Project organisation include:
Project Proponent – Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative – AECOM Asia Co. Ltd.
Environmental Team (ET) – Wellab Limited
Independent Environmental Checker
(IEC) – Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
names and contact numbers of key personnel are summarised in Table
2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax
No. |
Civil Engineering and
Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Ryan Chau |
3797 5387 |
3547
1658 |
Supervisor / Supervisor's Representative (AECOM Asia Co. Ltd.) |
Chief Resident Engineer |
Mr. Alan Lee |
6398
5982 |
2680
9515 |
Senior Resident
Engineer |
Mr. King-man
Chan |
9651
2635 |
2680
9515 |
|
Environmental Team (Wellab
Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898
7388 |
2898 7076 |
Independent
Environmental Checker (MottMac) |
Independent Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract No. ND/2019/01 Contractor
(Build King – Richwell Engineering Joint Venture) |
Site Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr. Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor
(Chun Wo – Kwan Lee Joint Venture.) |
Site Agent |
Mr. Andy Chan |
3485 9780 |
-- |
Environmental Officer |
TBC |
-- |
||
Contract No. ND/2019/03 Contractor
(Sang Hing Kuly Joint Venture) |
Site Agent |
Mr. Tang Wing Kai |
9300 7037 |
-- |
Environmental Officer |
Mr. Ken Cheung |
9803 5297 |
||
Contract No. ND/2019/04 Contractor
(Daewoo – Chun Wo – Kwan Lee Joint Venture) |
Site Agent |
Mr. Eric Wu |
9786 8630 |
-- |
Environmental Officer |
Mr. Sam Lam |
6178 3179 |
||
Contract No. ND/2019/05 Contractor
(CRCC – Paul Y. Joint Venture) |
Site Agent |
Mr. Darvin Lo |
9467 5891 |
-- |
Environmental Manager |
Mr. Pan Fong |
9436 9435 |
||
Environmental Officer |
Ms. Iris Ho |
5611 8325 |
||
Contract No. ND/2019/06 Contractor
(New Concepts Engineering Development Ltd.) |
Project Manager |
Mr. Joe
Cheng |
9861 0060 |
-- |
Environmental Officer |
Mr. Alex Choy |
6360 3236 |
||
Contract No. ND/2019/07 Contractor
(China Road and Bridge Corporation) |
Site Agent |
Mr. Mac Chow |
9169 9567 |
-- |
Environmental Officer |
Mr. K. M. Lui |
5113 8223 |
||
Environmental Supervisor |
Mr. Attlee Chau |
6386 9018 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (December 2023) |
ND/2019/01 |
(a)
Drainage
works, watermain works and sheet piles in Portion 1a (b)
Site
formation and erection of hoarding in Portion 1c (c)
Sheet
piling, site clearance, site formation, construction of subway, drainage
works and road works in Portion 2 (d)
Sheet
piling, drainage works and watermain works in Portion 3 (e)
Watermain
works in Portion 5 (f)
Backfilling,
drainage and watermain works in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Excavation
and drainage works in Portion 7 (i)
Construction
of retaining wall, RC construction of fresh water reservoir, construction of
WSD’s maintenance access, drainage works, backfilling works and soil nail in
Portion 8a (j)
Pipe
jacking at LWSC’s carpark, trenchless work and watermain construction in
Portion 8b (k)
Sheet
piling, excavation, drainage and watermain works in Portion 9b (l)
Removal of existing structure in Portion 11b (m)
Site clearance, removal of existing structure,
site formation and erection of hoarding in Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road
& Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b) Portion 2 to Portion 20C -
Wetland creation & restoration, Dry agricultural
land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer’s Forum |
ND/2019/04 |
(a)
Tree Pruning (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork and Scaffolding Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
ND/2019/05 |
(a)
South Team -
E3-05M – Pier head construction in progress. -
E3-04a – Column construction in progress. -
E3-04b – ELS in progress. Unforeseen obstruction
encountered. -
E4-01 – ELS in progress. -
E4-02 – ELS pipe pile wall in progress.
Unforeseen obstruction encountered. -
D2-04M – Bored Piling completed on 22 Nov 2023. -
FS04 – Raking drain completed. Middle berm and
U-channel construction in progress. -
Works in TWSRE A. BBI
cover walkway (Steelwork) – 1st stage was completed. B. HKY
Footbridge/Staircase – Installation of subframe and roof in progress. C. BBI
Toilet – Base slab was casted. Wall construction is in progress. D. Connecting
Road L201 to D300 – Backfilling is in progress. -
Works in TWSRW A. TWRSW
Stage 2 TTA completed on 22 Nov 2023. B. 11kv
cable laying (near HKY entrance) in progress. C. Drainage
work – Laying 2x1200Dia Pipes to Manhole (FL9110) in progress. D. Sewerage
work – Laying 600Dia pipes at FW06 is in progress. E. Gas
Pipe laying (IPA400/HP600 – near HKY entrance) in progress. F. Fresh
watermain diversion in progress. Connection works to be carried out by WSD in
Early Feb 2024. G. Lift
LT02 – Mini piles in progress. 13 out of 19 piles were completed. -
NB109 A. Bay 11
– 1st Wall was completed. B. Bay 12
Footing was completed. 1st Wall is in progress. C. Bay 13
Site Clearance is in progress. -
NB69 A.
Bay 5, Bay 6 – 1st Wall was completed. B.
Bay 2, Bay 3 – ELS is in progress. Unforeseen
obstruction encountered. C.
Bay 6, Bay 7, Bay 8 – ELS is in progress -
NB110 A.
Bay 3 to 5 was completed. Backfilling to
formation is in progress B.
Bay 8 was completed on 10 Nov 2023. C.
Bay 9 – ELS is in progress. -
NB 29 A.
3 Trial Pits were carried out along NB29 U-trough
area. (b)
North Team -
Slope
works of FS 30 completed. -
1st pour
concreting at C2-01 crosshead completed. -
Dismantling
of steel beam for B1-02 Portal Beam construction completed. -
Soffit
erection for C1-02 portal beam construction completed. -
Truss
erection for C1-01 MJ portal construction in progress. -
Falsework
erection for B2-02 & B2-03 cross head construction in progress -
D2-01
pier & pier head construction completed. -
Sheet
pile extraction of B1- Abutment wall- phase 1 completed. -
Backfilling
& extraction of sheet pile at C2-02 were in progress. -
Backfilling
at C4-02, C4-01a & C4-01b were in progress -
Removal
of debris (additional request from DSD) due to black rainstorm were
completed. -
JCR:
Permeant bitumen pavement works in northbound completed. Traffic diversion completed. -
JCR:
Construction of pipe support for DN 150 exposed pipe & trench excavation
for WSD were in progress. -
JCR Tong
Hang Village J/O improvement works: Blinding of box-culvert casted.
Construction of box-culvert & head wall for footpath were in progress. -
Construction of manhole & associated DN 900
drain pipe were in progress (c)
Bridges and Structures -
Total 746 segments were casted in Huizhou
casting yard. -
Total 489 segments were delivered to site, and
total 489 segments erected. -
C2-04 to C3-01 end span segment erection by LG
completed. -
Fabrication of steel support for Bridge B1
completed at Zhengzhou. -
Bridge B1 construction in progress. -
Preparation of casting yard for Bridge B2
segments commenced at Dongguang. -
Fabrication of parapet-skin commenced at ShenZheng casting yard, total 20 pieces parapet-skin fabricated. (d)
Form Traveler -
Form traveler rebar fixing for 04th pair segment
at E3-01 in progress. -
Form traveler rebar fixing for 07th pair segment
at D2-02 in progress. -
Form traveler rebar fixing for 07th pair segment
at D2-03 in progress. -
Form traveler rebar fixing for 01st pair segment
at E2-02 in progress. -
FT05 erection at E2-01 completed. -
Completed concreting E2-E2-02-E2-03-S013,
E2-E2-02-E2-01-S13. E2-E2-02-E2-03-S014, -
Completed concreting D2-D2-02-D2-03-S05,
D2-D2-02-D2-01-S05, D2-D2-02-D2-03-S06, D2-02-D2-01-S06. -
Completed concreting D2-D2-03-D2-04-S02,
D2-D2-03-D2-02-S02, -
Completed concreting E3-E3-01-E2-03-S03 &
E2-E2-01-E2-02-S01 |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |
2.10
Copies of Contractors’ construction programmes are
provided in Appendix A.
2.11
A
summary of the relevant permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.4.
Table 2.4 Status of Environmental Licences,
Notifications and Permits
Contract No. |
Permit / Licence No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental
Permit (EP) |
||||
ND/2019/01 |
EP-466/2013/A |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013/A |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
|
ND/2019/04 |
EP/473/2013/A |
27/01/2017 |
N/A |
Valid |
EP/546/2017 |
16/11/2017 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction Noise
Permit (CNP) |
||||
ND/2019/01 |
GW-RN0966-23 |
25/09/2023 |
24/12/2023 |
Expired
in reporting month |
GW-RN0840-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0877-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0997-23 |
01/10/2023 |
31/03/2024 |
Valid |
|
GW-RN1057-23 |
13/10/2023 |
12/01/2024 |
Valid |
|
GW-RN1224-23 |
21/11/2023 |
20/02/2024 |
Valid |
|
GW-RN1146-23 |
19/11/2023 |
18/05/2024 |
Valid |
|
GW-RN1329-23 |
20/12/2023 |
28/02/2024 |
Valid |
|
GW-RN1330-23 |
20/12/2023 |
19/03/2024 |
Valid |
|
GW-RN1235-23 |
01/12/2023 |
29/02/2024 |
Valid |
|
GW-RN1328-23 |
25/12/2023 |
24/03/2024 |
Valid |
|
ND/2019/02 |
GW-RN0873-23 |
01/09/2023 |
31/12/2023 |
Expired
in reporting month |
GW-RN1178-23 |
10/11/2023 |
09/02/2024 |
Valid |
|
GW-RN1163-23 |
08/11/2023 |
07/04/2024 |
Valid |
|
ND/2019/03 |
GW-RN0733-23 |
01/09/2023 |
29/02/2024 |
Valid |
ND/2019/04 |
GW-RN0878-23 |
17/08/2023 |
07/12/2023 |
Expired
in reporting month |
GW-RN0984-23 |
23/09/2023 |
22/12/2023 |
Expired
in reporting month |
|
GW-RN1110-23 |
19/10/2023 |
31/12/2023 |
Expired
in reporting month |
|
GW-RN1039-23 |
08/10/2023 |
07/01/2024 |
Valid |
|
GW-RN1048-23 |
29/12/2023 |
28/03/2024 |
Valid |
|
ND/2019/05 |
GW-RN0977-23 |
01/10/2023 |
31/12/2023 |
Expired
in reporting month |
GW-RN1138-23 |
09/11/2023 |
31/01/2024 |
Valid |
|
GW-RN0897-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN1248-23 |
01/12/2023 |
29/02/2024 |
Valid |
|
GW-RN1334-23 |
13/12/2023 |
29/02/2024 |
Valid |
|
GW-RN1368-23 |
27/12/2023 |
31/01/2024 |
Valid |
|
GW-RN1367-23 |
29/12/2023 |
28/02/2024 |
Valid |
|
GW-RN1369-23 |
27/12/2023 |
26/03/2024 |
Valid |
|
Notification pursuant
to Air Pollution Control (Construction Dust)
Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
477388 |
02/03/2022 |
N/A |
Valid |
|
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/04 |
461184 |
23/10/2020 |
N/A |
Valid |
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
ND/2019/07 |
459393 |
28/08/2020 |
N/A |
Valid |
Billing Account for
Disposal of Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/04 |
7038391 |
22/09/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
ND/2019/07 |
7038309 |
14/09/2020 |
N/A |
Valid |
Registration
of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/04 |
5211-624-D2709-01 |
26/11/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
ND/2019/07 |
5213-625-C4498-01 |
21/09/2020 |
N/A |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00037191-2020 |
21/04/2022 |
28/02/2026 |
Valid |
|
WT00037204-2020 |
16/11/2022 |
28/02/2026 |
Valid |
|
WT00037412-2021 |
16/11/2022 |
30/04/2026 |
Valid |
|
WT00037564-2021 |
19/04/2021 |
30/04/2026 |
Valid |
|
WT00037886-2021 |
28/06/2021 |
30/06/2026 |
Valid |
|
WT00041311-2022 |
21/06/2022 |
30/06/2027 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
WT00036952-2020 |
17/12/2020 |
31/12/2025 |
Valid |
|
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
WT00036414-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
WT00037771-2021 |
08/07/2021 |
31/07/2026 |
Valid |
|
WT00035984-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
ND/2019/04 |
WT00037539-2021 |
02/06/2022 |
30/04/2026 |
Valid |
ND/2019/05 |
WT00036996-2020 |
22/12/2020 |
31/12/2025 |
Valid |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |
ND/2019/07 |
WT00037526-2021 |
21/04/2022 |
31/05/2026 |
Valid |