10.1
Site
audits were carried out by ET on a weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures on the Contract site. Summary
of the site
audits are presented in Table 10.1 and Appendix P.
Table 10.1 Summary
of Site Audits
Environmental Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly site audit with representative of the Supervisor’s Representative and the
Contractor |
5, 12, 19
and 28 Dec 23 |
6, 14, 20
and 29 Dec 23 |
8, 15, 19
and 27 Dec 23 |
7, 12, 21
and 28 Dec 23 |
4, 14, 18 and 27 Dec 23 |
N/A |
1, 8, 15, 22 and 29 Dec 23 |
Joint Site Audit with representative of the Supervisor’s Representative, the
Contractor and IEC |
12 Dec 23 |
29 Dec 23 |
19 Dec 23 |
12 Dec 23 |
14 Dec 23 |
N/A |
15 Dec 23 |
Remarks: The weekly site
inspection for ND/2019/06 has been terminated starting from 19/10/2023 since
the termination proposal was approved by EPD on the same day.
10.2
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarised in Table 10.2.
Any outstanding and recurrence deficiencies are presented in Table 10.3.
10.3
All
construction activities with significant environmental impact undertaken by
Contract No. ND/2019/06 was substantially completed in March 2022 and the majority
of outstanding works were also completed
in April 2022 with defect rectification works remained. The outstanding installation works
were
the short-duration works which would be completed within 2 months during
the 1-year defect correction period, originally estimated.
10.4
Due to problems
in material deliveries from Mainland China in 2022, the completion date of the
outstanding works would be extended to June 2023 tentatively. However, in June
2023, more defects were found during the handover inspection so the
rectification works were undertaken until July 2023 when all works were completed.
10.5
The
weekly site inspection and EM&A Reporting for ND/2019/06 were maintained
until the termination proposal for ND/2019/06 has been endorsed by the IEC (17
Aug 23), the Engineer (26 Aug 23) and the Project Proponent (19 Sep 23)
followed by approval from EPD (19 Oct 23) in accordance. The procedure for
termination proposal for ND/2019/06 is in accordance with section 15.4.2 of
updated EM&A Manual.
Table 10.2 Observations and Recommendations during
Site Audits
Date |
Observations and
Recommendations |
Follow-up |
|
Contract No.: ND/2019/01 |
|||
Water Quality |
19/12/2023 |
The litter in RC2 at
Portion 1B should be cleared. RC2 should be maintained properly. |
Improvement/Rectification
was observed during follow-up audit session on 28 Dec 2023. |
Air Quality |
05/12/2023 |
Provide impervious
sheeting for the dusty stockpile at portion 2. |
Improvement/Rectification
was observed during follow-up audit session on 12 Dec 2023. |
05/12/2023 |
Provide valid NRMM
label for the generator at portion 5. |
Improvement/Rectification
was observed during follow-up audit session on 12 Dec 2023. |
|
12/12/2023 |
Review and enhance the
condition of hydroseeding at Pak Shek Au. |
Item remarked as 231219-R02. Follow-up action is
needed to be review. |
|
19/12/2023 |
Improvement/Rectification
was observed during follow-up audit session on 28 Dec 2023. |
||
19/12/2023 |
Review and enhance the
condition of hydroseeding at Portion 1C. |
Improvement/Rectification
was observed during follow-up audit session on 28 Dec 2023. |
|
Waste / Chemical Management |
05/12/2023 |
Keep clean and tidy for
the portion 9b. |
Improvement/Rectification
was observed during follow-up audit session on 12 Dec 2023. |
12/12/2023 |
Fell trees and yard
waste should be cleared at Pak Shek Au. |
Improvement/Rectification
was observed during follow-up audit session on 19 Dec 2023. |
|
Landscape and Visual |
12/12/2023 |
Tree protection zone
should be provided for the retained trees at Portion 11b. |
Improvement/Rectification
was observed during follow-up audit session on 19 Dec 2023. |
Noise |
28/12/2023 |
The NEL of the air
compressor at Portion 8a should be displayed. |
Follow-up action is needed to be reported in the following
month. |
Contract No.: ND/2019/02 |
|||
Water Quality |
29/11/2023 |
Provide maintenance for the water mitigation measure to prevent
surface runoff. |
Improvement/Rectification
was observed during follow-up audit session on 6 Dec 2023. |
29/11/2023 |
Provide maintenance for the sandbags to prevent muddy water/ debris
discharge onto cycling track. |
Improvement/Rectification
was observed during follow-up audit session on 6 Dec 2023. |
|
29/11/2023 |
Provide maintenance to the concrete bund to prevent wheel-washing
wastewater discharge. |
Item remarked as 231206-R02. Follow-up action is
needed to be review. |
|
06/12/2023 |
Item remarked as 231214-R02. Follow-up action is
needed to be review. |
||
14/12/2023 |
Improvement/Rectification
was observed during follow-up audit session on 20 Dec 2023. |
||
29/11/2023 |
Exposed slope at Portion 5 should be properly covered by tarpaulin
sheets. |
Improvement/Rectification
was observed during follow-up audit session on 6 Dec 2023. |
|
29/11/2023 |
Silt accumulating in the nullah near the water outlet at the material
storage should be cleared continuously. Contractor was also reminded to
enhance water mitigation measures to prevent further accumulation of silt. |
Item remarked as 231206-R03. Follow-up action is
needed to be review. |
|
06/12/2023 |
Item remarked as 231214-R03. Follow-up action is
needed to be review. |
||
14/12/2023 |
Item remarked as 231220-R02. Follow-up action is
needed to be review. |
||
20/12/2023 |
Item remarked as 231229-R02. Follow-up action is
needed to be review. |
||
29/12/2023 |
Follow-up action is needed to be reported in the
following month. |
||
29/11/2023 |
Muddy water in Portion 11 should be cleared immediately to avoid
overflow. |
Improvement/Rectification
was observed during follow-up audit session on 6 Dec 2023. |
|
29/11/2023 |
Leakage of muddy water was observed at Portion 4. Contractor was
reminded to repair the drainage system. |
Improvement/Rectification
was observed during follow-up audit session on 6 Dec 2023. |
|
29/11/2023 |
Leakage of untreated water was observed. Contractor was reminded to
review the water treatment system of Portion 5. |
Improvement/Rectification
was observed during follow-up audit session on 6 Dec 2023. |
|
06/12/2023 |
The channel should be properly blocked to prevent contamination. |
Improvement/Rectification
was observed during follow-up audit session on 14 Dec 2023. |
|
06/12/2023 |
Provide maintenance to sandbags to prevent muddy water/ debris
discharge in river. |
Improvement/Rectification
was observed during follow-up audit session on 14 Dec 2023. |
|
06/12/2023 |
Regular cleaning of the garbage in Portion 11 should be conducted. |
Improvement/Rectification
was observed during follow-up audit session on 14 Dec 2023. |
|
14/12/2023 |
Enhance the mitigation measures to prevent waste or surface runoff
for the discharge point of Portion 1. |
Item remarked as 231220-R04. Follow-up action is
needed to be review. |
|
20/12/2023 |
Item remarked as 231229-R03. Follow-up action is needed
to be review. |
||
29/12/2023 |
Follow-up action is needed to be reported in the
following month. |
||
20/12/2023 |
Provide maintenance to impervious sheeting on the exposed slope at
Portion 5. |
Item remarked as 231229-R04. Follow-up action is
needed to be review. |
|
29/12/2023 |
Follow-up action is needed to be reported in the
following month. |
||
20/12/2023 |
Accumulated ground water should be pumped out to wastewater treatment
facilities prior to discharge. |
Improvement/Rectification
was observed during follow-up audit session on 29 Dec 2023. |
|
20/12/2023 |
Provide impervious sheeting for the exposed slope at Portion 4. |
Improvement/Rectification
was observed during follow-up audit session on 29 Dec 2023. |
|
29/12/2023 |
Contractor was reminded to ensure the vehicles are properly cleaned
of dirt and dust before leaving the site. |
Follow-up action is needed to be reported in the
following month. |
|
Air Quality |
14/12/2023 |
Provide impervious sheeting for the exposed slope at Portion 4. |
Item remarked as 231220-R03 (Water Quality).
Follow-up action is needed to be review. |
20/12/2023 |
Exposed works sites and haul roads should be sprayed with water as
dust suppression. |
Improvement/Rectification
was observed during follow-up audit session on 29 Dec 2023. |
|
29/12/2023 |
Dusty stockpile and exposed slopes should be covered with tarpaulin
sheets. |
Follow-up action is needed to be reported in the
following month. |
|
Landscape and Visual |
29/11/2023 |
The removed green hoarding along Sheung Yue River due to the
construction works should be replaced and maintained properly as soon as
possible. |
Item remarked as 231206-R01. Follow-up action is
needed to be review. |
06/12/2023 |
Item remarked as 231214-R01. Follow-up action is
needed to be review. |
||
14/12/2023 |
Item remarked as 231220-R01. Follow-up action is
needed to be review. |
||
20/12/2023 |
Item remarked as 231229-R01. Follow-up action is
needed to be review. |
||
29/12/2023 |
Follow-up action is needed to be reported in the following
month. |
||
Waste / Chemical Management |
29/11/2023 |
Provide drip tray for chemical/fuel container at visiting center. |
Improvement/Rectification
was observed during follow-up audit session on 6 Dec 2023. |
29/11/2023 |
Accumulation of general refuse should be avoided at the riverbank of
Portion 11. |
Item remarked as 231206-R04. Follow-up action is
needed to be review. |
|
06/12/2023 |
Improvement/Rectification
was observed during follow-up audit session on 14 Dec 2023. |
||
14/12/2023 |
Keep site clean and tidy at Portion 1. |
Improvement/Rectification
was observed during follow-up audit session on 20 Dec 2023. |
|
Permit / Licences |
20/12/2023 |
Construction Noise Permit should be available for inspection at site
entrance. |
Improvement/Rectification
was observed during follow-up audit session on 29 Dec 2023. |
Contract No.: ND/2019/03 |
|||
Water Quality |
08/12/2023 |
Contractor was reminded to ensure vehicles are
properly washed before leaving the site. |
Improvement/Rectification
was observed during follow-up audit session on 15 Dec 2023. |
Waste/Chemical Management |
15/12/2023 |
Provide drip tray for chemical/fuel containers. |
Improvement/Rectification
was observed during follow-up audit session on 19 Dec 2023. |
Contract No.: ND/2019/04 |
|||
Water Quality |
12/12/2023 |
Blue hoses should be kept away from the riverside
near A3-03. |
Item remarked as 231221-R02. Follow-up action is
needed to be review. |
21/12/2023 |
Improvement/Rectification
was observed during follow-up audit session on 28 Dec 2023. |
||
Ecology |
30/11/2023 |
The dull green barrier of the 10m buffer zone
near Siu Hang San Tsuen should be maintained properly and regularly. |
Item remarked as 231207-R02. Follow-up action is
needed to be review. |
07/12/2023 |
Improvement/Rectification
was observed during follow-up audit session on 12 Dec 2023. |
||
30/11/2023 |
The silt curtain next to A3-01 should be
maintained properly |
Item remarked as 231207-R03. Follow-up action is
needed to be review. |
|
07/12/2023 |
Improvement/Rectification
was observed during follow-up audit session on 12 Dec 2023. |
||
28/12/2023 |
The silt curtain at Bridge F should be maintained
regularly and properly. |
Follow-up action is needed to be reported in the
following month. |
|
Air Quality |
30/11/2023 |
Stockpile of dusty material at A1-03 and Portion
K should be covered by impervious sheets properly. |
Improvement/Rectification
was observed during follow-up audit session on 7 Dec 2023. |
07/12/2023 |
Exposed site area should be watered regularly as
dust suppression at A1-03 and A3-03. |
Improvement/Rectification
was observed during follow-up audit session on 12 Dec 2023. |
|
12/12/2023 |
Dusty stockpile should be covered by impervious
sheets properly at Portion K. |
Item remarked as 231221-R01. Follow-up action is
needed to be review. |
|
21/12/2023 |
Dusty stockpile at Portion K should be covered
properly or watered regularly as dust suppression. |
Improvement/Rectification
was observed during follow-up audit session on 28 Dec 2023. |
|
Waste / Chemical Management |
07/12/2023 |
Accumulation of general refuse should be avoided
at A1-05. |
Improvement/Rectification
was observed during follow-up audit session on 12 Dec 2023. |
Contract No.: ND/2019/05 |
|||
Waste / Chemical Management |
04/12/2023 |
The construction site at On Lok Garden should be
kept clean and tidy generally. The contractor was reminded to clear the waste
regularly. |
Improvement/Rectification
was observed during follow-up audit session on 14 Dec 2023. |
Water Quality |
18/12/2023 |
Litter in the temporary drainage at B1-02a should
be cleared and maintained properly. |
Improvement/Rectification
was observed during follow-up audit session on 27 Dec 2023. |
Contract No.: ND/2019/06 |
|||
-- |
-- |
-- |
-- |
Contract No.: ND/2019/07 |
|||
Waste/Chemical Management |
22/12/2023 |
Ensure that the drip tray remains clear to
maintain adequate capacity. |
Improvement/Rectification
was observed during follow-up audit session on 29 Dec 2023. |
Table 10.3 Summary Table for the Outstanding item(s) in the reporting month
Contract No. |
Outstanding deficiencies since last
reporting month (Nov 2023) |
Deficiencies recorded in the reporting month (Dec 2023) |
Total deficiencies (including repeated
deficiencies) in the reporting month |
Deficiencies rectified in the reporting
month |
Outstanding deficiencies need to be Follow-up in the next month (Jan 2024) |
Total outstanding deficiencies |
||||||||||||||
A |
N |
W |
W/C |
CH |
L&V |
E |
P/L |
A |
N |
W |
W/C |
CH |
L&V |
E |
P/L |
|||||
ND/2019/01 |
/ |
5 |
1 |
1 |
2 |
/ |
1 |
/ |
/ |
10 |
8 |
/ |
1 |
/ |
/ |
/ |
/ |
/ |
/ |
1 |
ND/2019/02 |
11 |
3 |
/ |
17 |
2 |
/ |
4 |
/ |
1 |
27 |
17 |
1 |
/ |
4 |
/ |
/ |
1 |
/ |
/ |
6 |
ND/2019/03 |
/ |
/ |
/ |
1 |
1 |
/ |
/ |
/ |
/ |
2 |
2 |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
ND/2019/04 |
3 |
3 |
/ |
2 |
1 |
/ |
/ |
3 |
/ |
9 |
7 |
/ |
/ |
/ |
/ |
/ |
/ |
1 |
/ |
1 |
ND/2019/05 |
/ |
/ |
/ |
1 |
1 |
/ |
/ |
/ |
/ |
2 |
2 |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
ND/2019/06* |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
ND/2019/07 |
/ |
/ |
/ |
/ |
1 |
/ |
/ |
/ |
/ |
1 |
1 |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
Legends:
A = Air Quality
N = Construction Noise Impact
W = Water Quality
W/C = Waste / Chemical Management
CH = Cultural Heritage
L&V = Landscape & Visual
E = Ecology
P/L = Permit / Licences
* The weekly site inspection for ND/2019/06 has been terminated starting
from 19/10/2023 since the termination proposal was approved by EPD on the same
day.
10.6
According
to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
Q. The photographic records of measures as stipulated in EPs
to mitigate environmental impacts in the reporting month are presented in Table 10.4.
Table 10.4 Photographic Records and Implementation
Status of Measures
EP No. |
Condition |
Photographic Record |
Implementation Status |
EP-466/2013/A |
2.9 |
To
minimise adverse impacts on habitats of ecological
importance
in the vicinity of the Project, 2m high solid dull green site barrier fences
shall be erected around all active works areas. |
^[1] |
EP-467/2013/A |
2.9 |
To
minimise adverse impacts on habitats of ecological
importance
in the vicinity of the Project, 2m high solid dull green site barrier fences
shall be erected around all active works areas. |
^[1] |
EP-468/2013/A |
2.11 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-469/2013 |
2.7 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-473/2013/A |
2.13 |
To
minimise adverse impacts on habitats of ecological importance
in the vicinity of the Project, 2m high solid dull green site barrier fences
shall be erected around all active works areas. |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance of mitigation measure · Non-compliance
but rectified by the contractor N/A Not
Applicable at this stage as no such site activities were conducted in the
reporting period |
Remark:
[1]: Barrier
fences might be subjected to change according to the phasing plan designed at
detailed design stage
10.7
The water quality mitigation measures
detailed in the EIA Report and the Updated EM&A Manual are recommended to
be implemented during the construction phase. Water quality mitigation measures
implemented by the contractors were closely monitored to prevent water
pollution, especially during rainy season. An updated summary of the
Environmental Mitigation Implementation Schedule is provided in Appendix Q.
Specific water quality mitigation measures for major construction works in the
reporting month are presented in Table 10.4.
Table 10.5 Specific Water Quality Mitigation Measures for Major
Construction Works in the Reporting Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Hydroseeding for
slope area |
ND/2019/02 |
Hard paved exposed
haul road |
Hard paved exposed slope surface |
ND/2019/03 |
Hard paved exposed
haul road |
Watering the main haul road regularly. |
ND/2019/04 |
Hard paved exposed slope surface |
Deployment of silt curtain around works area in Ng Tung River |
ND/2019/05 |
Covering dusty
stockpile |
Provision of sand bags around works area |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
De-silting waste water before discharge |
Water quality mitigation measures for site(s) in operation
phase, remaining defect works |
||
ND/2019/06 |
Hard paved exposed
haul road |
Hard paved exposed haul road |
10.8
Waste generated
from Contract Nos.
ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05 and ND/2019/07
included
inert construction and demolition (C&D) materials and non-inert C&D wastes
in the reporting
month.
The site of ND/2019/06 was handed over to AFCD for operation since 4 April
2022.
10.9
The amount of wastes generated by the construction works of the Contract
Nos.
ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05 and ND/2019/07 during the reporting month are shown in Appendix R. The site of
ND/2019/06 was handed over to AFCD for operation since 4 April 2022.
10.10 The Contractors are advised to minimise the wastes generated
through recycling or reusing. All mitigation measures stipulated in the Updated
EM&A Manual and waste management plans shall be fully implemented. The
status of implementation of waste management and reduction measures are
summited in Appendix Q.
10.11
Based on the findings of the EIA
Report, the area of Long Valley has been assessed as of high to very high
ecological value and is the largest contiguous area of freshwater wetland
habitats in Hong Kong. To safeguard the ecological value of Long Valley, about
37 hectares of land in Long Valley has been proposed to develop into Long
Valley Nature Park (LVNP) for conserving and enhancing the ecologically
important environment as well as for compensation of the wetland loss due to
the NDA development.
10.12
LVNP is developed according to the approved
Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. HCMP
provides a framework and specifications for development and management of LVNP
and guides the development to maintain and enhance the 37 hectares of low-lying
wetland habitats.
10.13
Regarding
the design, the zoning of land use in LVNP is intended to maintain the existing
mosaic pattern of wet and dry agriculture, while controlling the activities
that could potentially disturb target habitats and species. LVNP will be divided
into three broad zones of land use as below:
•
Biodiversity
Zone of about 21 hectares largely designated for biodiversity conservation
through cultivation of specified crops and habitat management.
•
Agricultural
Zone of about 11 hectares designated for commercially focuses crop production
and eco-friendly agricultural practice for farming.
•
Visitor
Zone of about 5 hectares designed to accommodate visitors as well as storage
and other facilities and for educational purposes.
10.14
The
construction of LVNP started in late 2019 and was expected to be completed in 2023.
During the construction
period, the progress of construction and wetland enhancement works has been
under observation by different stakeholders including AFCD and green groups.
Close communication between AFCD and CEDD were conducted to exchange views on
conservation, restoration and management of habitats
as well as on the planning and design of the park. In addition, advices
from green groups, Hong Kong Bird Watching Society (HKBWS) and The Conservancy
Association (CA), have been taken on habitat management of Long
Valley and potential effects on habitat and wildlife of each individual work
conducted in Long Valley. The last meeting was held on 18 November 2022 to share
the progress of LVNP with different stakeholders, including CEDD, AFCD, CA,
HKBWS, Contractor, ET, IEC and farmers.
10.15 Proposals on wetland creation and
restoration, dry agricultural land creation, pond creation, water treatment
wetland and design of irrigation channel were submitted by the Contractor to
achieve the objectives stated in HCMP and accepted by the Engineer with consent
from AFCD before implementation. The Contractor would consult the stakeholders for
recommendations and suggestions on mitigation measures to minimise
the environmental impacts arising from construction works. The progress of
works would
be arranged to minimise impacts to avifauna and
maintain the habitat for avifauna. The photographic records of site activities
in LVNP are presented in Table 10.5.
Table 10.6 Photographic
Records of Site Activities in LVNP
Continuing agricultural practice in existing
farmland to maintain habitats in Long Valley |
|
Open
water Habitat |
Open
water Habitat |
Creation of wetland with designated
habitat for biodiversity conservation |
|
Planting of paddy rice to provide
foraging ground for Yellow-breasted Bunting |
|
Enhancement of irrigation channel
to provide reliable water source for farmland in Long Valley |
|
Provision of bird island (hidden area) |
Restoring of water flea pond to provide
food source to water birds |
Construction of storage sheds for farmers |
A Himantopus
himantopus was recorded |
Wet agricultural land |