Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (December 2023) |
ND/2019/01 |
(a)
Drainage
works, watermain works and sheet piles in Portion 1a (b)
Site
formation and erection of hoarding in Portion 1c (c)
Sheet
piling, site clearance, site formation, construction of subway, drainage
works and road works in Portion 2 (d)
Sheet
piling, drainage works and watermain works in Portion 3 (e)
Watermain
works in Portion 5 (f)
Backfilling,
drainage and watermain works in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Excavation
and drainage works in Portion 7 (i)
Construction
of retaining wall, RC construction of fresh water reservoir, construction of
WSD’s maintenance access, drainage works, backfilling works and soil nail in
Portion 8a (j)
Pipe
jacking at LWSC’s carpark, trenchless work and watermain construction in
Portion 8b (k)
Sheet
piling, excavation, drainage and watermain works in Portion 9b (l)
Removal of existing structure in Portion 11b (m)
Site clearance, removal of existing structure,
site formation and erection of hoarding in Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road
& Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b) Portion 2 to Portion 20C -
Wetland creation & restoration, Dry agricultural
land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer’s Forum |
ND/2019/04 |
(a)
Tree Pruning (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork and Scaffolding Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
ND/2019/05 |
(a)
South Team -
E3-05M – Pier head construction in progress. -
E3-04a – Column construction in progress. -
E3-04b – ELS in progress. Unforeseen obstruction
encountered. -
E4-01 – ELS in progress. -
E4-02 – ELS pipe pile wall in progress.
Unforeseen obstruction encountered. -
D2-04M – Bored Piling completed on 22 Nov 2023. -
FS04 – Raking drain completed. Middle berm and
U-channel construction in progress. -
Works in TWSRE A. BBI
cover walkway (Steelwork) – 1st stage was completed. B. HKY
Footbridge/Staircase – Installation of subframe and roof in progress. C. BBI
Toilet – Base slab was casted. Wall construction is in progress. D. Connecting
Road L201 to D300 – Backfilling is in progress. -
Works in TWSRW A. TWRSW
Stage 2 TTA completed on 22 Nov 2023. B. 11kv
cable laying (near HKY entrance) in progress. C. Drainage
work – Laying 2x1200Dia Pipes to Manhole (FL9110) in progress. D. Sewerage
work – Laying 600Dia pipes at FW06 is in progress. E. Gas
Pipe laying (IPA400/HP600 – near HKY entrance) in progress. F. Fresh
watermain diversion in progress. Connection works to be carried out by WSD in
Early Feb 2024. G. Lift
LT02 – Mini piles in progress. 13 out of 19 piles were completed. -
NB109 A. Bay 11
– 1st Wall was completed. B. Bay 12
Footing was completed. 1st Wall is in progress. C. Bay 13
Site Clearance is in progress. -
NB69 A.
Bay 5, Bay 6 – 1st Wall was completed. B.
Bay 2, Bay 3 – ELS is in progress. Unforeseen
obstruction encountered. C.
Bay 6, Bay 7, Bay 8 – ELS is in progress -
NB110 A.
Bay 3 to 5 was completed. Backfilling to
formation is in progress B.
Bay 8 was completed on 10 Nov 2023. C.
Bay 9 – ELS is in progress. -
NB 29 A.
3 Trial Pits were carried out along NB29 U-trough
area. (b)
North Team -
Slope
works of FS 30 completed. -
1st pour
concreting at C2-01 crosshead completed. -
Dismantling
of steel beam for B1-02 Portal Beam construction completed. -
Soffit
erection for C1-02 portal beam construction completed. -
Truss
erection for C1-01 MJ portal construction in progress. -
Falsework
erection for B2-02 & B2-03 cross head construction in progress -
D2-01
pier & pier head construction completed. -
Sheet
pile extraction of B1- Abutment wall- phase 1 completed. -
Backfilling
& extraction of sheet pile at C2-02 were in progress. -
Backfilling
at C4-02, C4-01a & C4-01b were in progress -
Removal
of debris (additional request from DSD) due to black rainstorm were
completed. -
JCR:
Permeant bitumen pavement works in northbound completed. Traffic diversion completed. -
JCR:
Construction of pipe support for DN 150 exposed pipe & trench excavation
for WSD were in progress. -
JCR Tong
Hang Village J/O improvement works: Blinding of box-culvert casted.
Construction of box-culvert & head wall for footpath were in progress. -
Construction of manhole & associated DN 900
drain pipe were in progress (c)
Bridges and Structures -
Total 746 segments were casted in Huizhou
casting yard. -
Total 489 segments were delivered to site, and
total 489 segments erected. -
C2-04 to C3-01 end span segment erection by LG
completed. -
Fabrication of steel support for Bridge B1
completed at Zhengzhou. -
Bridge B1 construction in progress. -
Preparation of casting yard for Bridge B2
segments commenced at Dongguang. -
Fabrication of parapet-skin commenced at
ShenZheng casting yard, total 20 pieces parapet-skin fabricated. (d)
Form Traveler -
Form traveler rebar fixing for 04th pair segment
at E3-01 in progress. -
Form traveler rebar fixing for 07th pair segment
at D2-02 in progress. -
Form traveler rebar fixing for 07th pair segment
at D2-03 in progress. -
Form traveler rebar fixing for 01st pair segment
at E2-02 in progress. -
FT05 erection at E2-01 completed. -
Completed concreting E2-E2-02-E2-03-S013,
E2-E2-02-E2-01-S13. E2-E2-02-E2-03-S014, -
Completed concreting D2-D2-02-D2-03-S05,
D2-D2-02-D2-01-S05, D2-D2-02-D2-03-S06, D2-02-D2-01-S06. -
Completed concreting D2-D2-03-D2-04-S02,
D2-D2-03-D2-02-S02, -
Completed concreting E3-E3-01-E2-03-S03 &
E2-E2-01-E2-02-S01 |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |