1.
This is the 50th monthly Environmental Monitoring
and Audit (EM&A) Report for the First Phase Development of Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs), comprising the Advance Works and
First Stage Works (hereinafter
called the “the
Project”). This report is prepared
by Wellab Limited under “Service Contract No. NDO
04/2019 Environmental Team for Environmental Monitoring and Audit Works in
Construction Phase for the First Phase Development of KTN and FLN NDAs” (hereinafter called the “Service
Contract”). This report documents the findings of EM&A works conducted in December
2023.
2.
During the reporting month, the following Works
Contracts under relevant Environmental Permit(s) were undertaken for the
Project:
Table I Works
Contracts under relevant Environmental Permit(s) in the Reporting Month
Works Contracts |
Environmental Permit No. |
Designated Project (DP) |
Commencement date of construction |
Contract No. ND/2019/01 – Kwu Tung North New Development Area,
Phase 1: Site Formation and Infrastructure Works |
EP-466/2013/A |
Castle Peak Road Diversion |
12 August 2020 |
EP-467/2013/A |
Kwu Tung North New Development Area Road P1 and
P2 and Associated New Kwu Tung Interchange and Pak
Shek Au Interchange Improvement |
12 August 2020 |
|
Kwu Tung North New Development Area Road D1 to
D5 |
1 June 2020 |
||
Utilization of Treated Sewage Effluent (TSE)
from Shek Wu Hui Sewage Treatment Works |
23
March 2020 |
||
Contract No. ND/2019/02 – Kwu Tung North New Development Area,
Phase 1: Roads and Drains between Kwu Tung North
New Development Area and Shek Wu Hui |
EP-469/2013 |
Sewage Pumping Stations in Kwu Tung North New Development Area |
28 October
2020 |
Contract No. ND/2019/03 – Kwu Tung North and Fanling North New Development Areas, Phase 1: Development
of Long Valley Nature Park |
Kwu Tung North New Development Area Road D1 to
D5 |
3 July
2020 |
|
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
6 October
2020 |
|
Contract No. ND/2019/04 – Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shek Wu San Tsuen North
to Lung Yeuk Tau) |
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
23
February 2021 |
EP-546/2017 |
Fanling North Temporary Sewage Pumping Station |
16
February 2021 |
|
Contract
No. ND/2019/05 – Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shung Him Tong to Kau
Lung Hang) |
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
1
August 2020 |
Contract No. ND/2019/06 – Fanling North New Development Area,
Phase 1: Re-provisioning of North District Temporary Wholesale Market for
Agricultural Products |
Reprovision of temporary Wholesale Market in
Fanling North New Development Area |
29
October 2019 |
|
Contract No. ND/2019/07 – Fanling North New
Development Area, Phase 1: Site Formation and Infrastructure Works |
Works
area not under relevant Environmental Permit for Phase 1 of the Project. |
1 March
2021 |
3.
A summary of the EM&A activities in
this reporting month is listed in Table
II below:
Table II Summary
Table for EM&A Activities in the Reporting Month
EM&A Activities |
Monitoring Station
(s) |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
||
1-hr Total Suspended Particulates (TSP) Monitoring |
FLN-DMS1 |
N/A |
N/A |
6, 12, 18, 22 and 28 Dec 23 |
6, 12, 18, 22 and 28 Dec 23 |
N/A |
N/A |
N/A |
FLN-DMS3 |
N/A |
N/A |
6, 12, 18, 22 and 28 Dec 23 |
|||||
FLN-DMS5 |
5, 11, 15, 21 and 27 Dec 23 |
5, 11, 15, 21 and 27 Dec 23 |
N/A |
|||||
KTN-DMS4(B) |
5, 11, 15, 21 and 27 Dec 23 |
5, 11, 15, 21 and 27 Dec 23 |
N/A |
|||||
24-hr TSP Monitoring |
FLN-DMS1 |
N/A |
N/A |
5, 11, 15, 21 and 27 Dec 23 |
5, 11, 15, 21 and 27 Dec 23 |
N/A |
N/A |
N/A |
FLN-DMS3 |
N/A |
N/A |
5, 11, 15, 21 and 27 Dec 23 |
|||||
FLN-DMS5A |
5, 11, 15, 21 and 27 Dec 23 |
5, 11, 15, 21 and 27 Dec 23 |
N/A |
|||||
KTN-DMS4(B) |
5, 11, 15, 21 and 27 Dec 23 |
5, 11, 15, 21 and 27 Dec 23 |
N/A |
|||||
Noise Monitoring |
CP-FLN-NMS1 |
N/A |
6, 12, 18 and 28 Dec
23 |
N/A |
||||
CP-FLN-NMS2 |
N/A |
6, 12, 18 and 28 Dec 23 |
N/A |
|||||
CP-KTN-NMS2 |
5, 11, 21 and 27 Dec 23 |
N/A |
N/A |
|||||
CP-KTN-NMS3 |
||||||||
CP-KTN-NMS5 |
||||||||
CP-KTN-NMS6 |
N/A |
5, 11, 21 and 27 Dec 23 |
||||||
Ecological Survey |
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley |
N/A |
N/A |
4, 7, 11, 15, 18, 21, 27 and 28 Dec 2023 |
7, 15, 21, and 28 Dec 23 |
N/A |
N/A |
N/A |
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen
Stream |
N/A* |
N/A* |
N/A* |
N/A* |
N/A* |
N/A* |
N/A* |
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from
Disturbance and Pollution |
5 and 12 Dec 23 |
5 and 12 Dec 23 |
12 Dec 23 |
12 Dec 23 |
12 Dec 23 |
N/A* |
N/A* |
|
Egretry Monitoring |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
24-hr RSP (Ambient Arsenic)
Monitoring for Land Contamination |
5, 11, 15, 21 and 27 Dec 23 |
N/A |
5, 11, 15, 21 and 27 Dec 23 |
N/A |
N/A |
N/A |
N/A |
|
Water Quality Monitoring |
N/A |
1, 4, 6, 8, 11, 13, 15, 18, 20, 22, 27 and 29 Dec 23 |
N/A |
1, 4, 6, 8, 11, 13, 15, 18, 20, 22, 27 and 29 Dec 23 |
N/A |
N/A |
N/A |
|
Landfill Gas Monitoring |
21 Dec 23 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Built Heritage Monitoring |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
5, 12, 19
and 28 Dec 23 |
6, 14, 20
and 29 Dec 23 |
8, 15, 19
and 27 Dec 23 |
7, 12, 21
and 28 Dec 23 |
4, 14, 18 and 27 Dec 23 |
NIL |
1, 8, 15, 22 and 29 Dec 23 |
Remarks:
N/A – No relevant monitoring is required according
to the updated EM&A Manual
N/A* – No relevant monitoring is required according to
the Baseline Ecological Monitoring Plan (Table 3.1)
[1] Since the distance between monitoring station
CP-KTN-NMS2 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m, the
monitoring station is not applicable to ND/2019/03
[2] Since the distance between monitoring station
CP-KTN-NMS3 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m, the
monitoring station is not applicable to ND/2019/03
[3] Since the distance between monitoring station
CP-KTN-NMS1 and site boundary of ND/2019/02 under EP-469/2013 exceeds 300m, the
monitoring station is not applicable to ND/2019/02
[4] Since the distance between monitoring station
FLN-DMS1 and site boundary of ND/2019/05 under EP-473/2013/A exceeds500m, the
monitoring station is not applicable to ND/2019/05
[5] Since the distance between monitoring station
FLN-DMS3 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A
exceeds 500m, the monitoring station is not applicable to ND/2019/03 and
ND/2019/04
[6] Since the distance between monitoring station
FLN-DMS5 and site boundary of ND/2019/05 under EP-473/2013/A exceeds 500m, the
monitoring station is not applicable to ND/2019/05
[7] Since the distance between monitoring station
CP-FLN-NMS2 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A
exceeds 300m, the monitoring station is not applicable to ND/2019/03 and
ND/2019/04
[8] Since the distance between monitoring station
CP-FLN-NMS1 and site boundary of ND/2019/03 under EP-473/2013/A exceeds 300m, the
monitoring station is not applicable to ND/2019/03
4.
Summary of the environmental exceedances
of the reporting month is tabulated in Table
III.
Table III Summary Table for Events Recorded in the
Reporting Month
Environmental Monitoring |
Parameter |
No. of non-project related
Exceedances |
Total
No. of non-project related
Exceedances |
No. of Exceedance
related to the Construction Works of the Contract |
Total
No. of Exceedance related to the Construction Works of the Contract |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||||
Air Quality |
1-hr
TSP |
0 |
0 |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hr RSP (Ambient Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
0 |
0 |
Water Quality |
DO |
0 |
0 |
0 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
|
SS |
0 |
0 |
0 |
0 |
0 |
0 |
|
Arsenic |
0 |
0 |
0 |
0 |
0 |
0 |
|
Landfill
Gas |
O2 |
0 |
0 |
0 |
0 |
0 |
0 |
CH4 |
|||||||
CO2 |
|||||||
Cultural
heritage |
Built Heritage Monitoring |
0 |
0 |
0 |
0 |
0 |
0 |
Ecological
Monitoring |
Avifauna |
0 |
0 |
0 |
0 |
0 |
0 |
Non-aquatic fauna |
2 |
2 |
0 |
0 |
0 |
0 |
Air Quality
5. All
construction air quality monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level exceedance was recorded.
Construction Noise
6.
All construction noise monitoring was
conducted as scheduled in the reporting month. No Action/Limit
Level exceedances were recorded.
Water
Quality
7. All
additional water quality monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level Exceedance was recorded. No construction of
channel for alternation of natural streams was carried out in the reporting
month. Therefore, no water quality monitoring was
conducted according to the Updated
EM&A Manual and Baseline Water Quality Monitoring Report (KTN & FLN
NDA). Relevant details are given in Section
5.
Land Contamination
8. All ambient
arsenic monitoring was conducted as scheduled in the reporting month. No
Action/Limit Level exceedance was recorded.
Landfill Gas Monitoring
9. Monitoring
of landfill gas in the reporting month was carried out by the Contractor under ND/2019/01
at excavation location Portion 6b. No Limit Level exceedance was recorded.
Built Heritage Monitoring
10. No Built
heritage monitoring was carried out in the reporting month due to no works causing for surveyed cultural
heritage at all. No Limit Level exceedance was recorded.
Ecological Monitoring
11. All
ecological monitoring was conducted as scheduled in the reporting month.
12. Two
(2) action level exceedance and two (2) limit level
exceedance for non-aquatic fauna were recorded at T3 & T6. The exceedance were
considered non-project related, as large proportion of vegetative habitat along
T3 were observed either removed and tarmacked as haul road by construction
works outside of project, first reported in the Monthly Monitoring Report in
December 2021. Dry weather throughout the month might also have influenced
number of species of odonates recorded. In addition,
necessary Ecological mitigation measure were provided by all nearby project-related sites.
No evidence to suggest that the exceedance was related to project activities.
13. The
ecological monitoring result in the Reporting Month is shown in Appendix L.
Complaint Log
14. No
environmental complaint was received in the reporting month.
Notification of Summons and Successful
Prosecutions
15. No
notification of summons or successful prosecutions was received in the
reporting month.
16. This
report has been prepared in compliance with the reporting requirements for the
subsequent monthly EM&A Report as required by the “Updated Environmental
Monitoring and Audit Manual for Advance and First Stage Works of Kwu Tung North and Fanling North
New Development Areas” (Updated EM&A Manual).
17.
The major site
activities for the coming three months are shown in Table IV.
Table IV Summary
Table for Site Activities in the coming Three Months
Contract
No. |
Site Activities (January to March 2024) |
ND/2019/01 |
(a)
Drainage works
and sheet piles in Portion 1a (b)
Site
formation, stockpile of soil, erection of hoarding and construction of noise
barrier in Portion 1c (c)
Sheet
Piling, Site formation work, construction of subway, road works and drainage
works in Portion 2 (d)
Excavation,
backfilling, drainage and watermain works in Portion 3 (e)
Watermain
works, excavation, backfilling, road works, sheet piling and pipe jacking in
Portion 5 (f)
Drainage
works, backfilling, road works and watermains works in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Sheet
piling, excavation, stockpile of soil, drainage works and watermain work in
Portion 7 (i)
Construction
of retaining wall, RC construction of fresh water reservoir, excavation at WSD’s
maintenance access, backfilling works, drainage works and pipe pile wall
installation in Portion 8a (j)
Trenchless
work, excavation, watermain works and ground treatment in Portion 8b (k)
Sheet
piling, excavation, road works, drainage works and watermain works in Portion
9b (l)
Removal of existing structure in Portion 11b (m)
Site clearance, tree felling, removal of existing
structure, site formation and stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer’s Forum |
ND/2019/04 |
(a)
Tree Pruning (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork and Scaffolding Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
ND/2019/05 |
(a)
North Team Works -
Backfilling and drainage work at C4-02 &
C4-01. -
Backfilling at C2-02, C3-03 & portion II. -
Haul Road to bridge deck In On
Lok Garden. -
Construction of remaining abutment wall near
portal B2-01. -
Construction of FW 53. -
Water works at Jockey Club Rd. -
Road works of northbound of Jockey Club Rd &
ducting works at central median. -
Sampling of existing pavement in southbound of
Jockey Club Rd. -
Construction of new box culvert & retaining
wall at Tong Hang Tsuen -
Drainage works –DN 900 at On Kui Street near B1. -
Cross head construction at B2-01, B2-02 & B2-03. (b)
Viaduct Works -
Segment fabrication for bridge C2, C1, D2, E4 -
Segments erection by LG at bridges C3, C2 -
SOP construction at D2-01 -
Construction of Bridge B1 -
Parapet skin fabrication and parapet
construction. -
Segment fabrication for bridge B2. (c)
South Team Works -
TWSRW –
Road work and UUs laying (Section P800 CH 450 to 600). -
TWSRW –
Construction of lower berm and Hydroseeding at FS04. -
TWSRW -
CLP 11 kv cable diversion work (1ST) -
TWSRW –
Gas (IPA400 and HP600) diversion work -
TWSRW –
Foundation work of D2-04M -
HKY FB
(East) – Installation of cladding and E&M works. -
HKY FB
(West) – Construction of LT2 (Mini-piles) -
E3-04a,
E304b, E4-01 and E4-02 – cap construction -
E305M
Pier Head construction -
NB109 –
Bay 11~12 base slab construction. Bay 5 to 12 wall construction. -
NB69 –
Bay 2~8 ELS works -
NB110 –
Bay 6~7 ELS works -
Demolish
Existing NB74 and BBI -
Removal
Sign Gantry DS64 (d)
Form Traveler -
E3-01 – construction 4rd to 6th pair -
E2-02 – dismantling of FT1 -
D2-02 – construction 08th to 11th pair -
D2-03 – construction 3rd pair to 5th pair -
E2-01 - construction 02nd pair to 05th pair |
ND/2019/06 |
The construction phase has been completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1,
2, 4 and 5 (c)
Construction of box culvert at Portion
2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at
Portion 4 (f)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (g)
Construction of noise barrier at
Portion 4 and 5 (h)
Waterworks at Portion 1, 2 and 4 |