Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities (September to November 2023) |
ND/2019/01 |
(a)
Drainage works
in Portion 1a (b)
No
construction activities in Portion 1b (c)
Site
formation, socket H piling and construction of noise barrier in Portion 1c (d)
Temporary
storage of material in Portion 1e (e)
Site
formation work, construction of subway and road works in Portion 2 (f)
Excavation,
backfilling, drainage and watermain works in Portion 3 (g)
Watermain
works, excavation, backfilling, road works, sheet piling and pipe jacking in
Portion 5 (h)
Drainage
works, backfilling, road works, watermains works in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
formation, sheet piling, excavation and drainage works in Portion 7 (k)
Construction
of retaining wall, RC construction of fresh water reservoir, excavation at WSD¡¦s
maintenance access, backfilling works and drainage works in Portion 8a (l)
Trenchless
work, excavation and watermain works in Portion 8b (m)
Sheet piling,
excavation, drainage works and watermain works in Portion 9b (n)
Site clearance, tree felling and removal of
existing structure in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and Fill
of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road &
Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a)
Tree Felling (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
ND/2019/05 |
(a)
North Team Works -
ELS works and Pile cap construction at B2-01 -
Backfilling and drainage work at C4-02 & C4-01. -
Backfilling at C3-04b & C2-02. -
Slope works at On Lok Garden FS29 & 30. -
Construction of B1 abutment wall and backfill. -
Exposed water main of Jockey Club Rd - F63. -
Road works of northbound of Jockey Club Rd. -
Laying ducting for traffic signal, traffic light
& street light & construction of permanent footpath -
for subsequent pedestrian diversion at J/O of JCR
and Tong Hang Tsuen -
Construction of new box culvert & retaining
wall at Tong Hang Tsuen -
Drainage works - DN 900 at On Kui Street near B1. -
Pier construction at D2-01 & B2-03 -
Pier head construction at D2-01 -
Cross head construction at C2-01, B2-02 -
Portal beam construction at C1-02 & C1-01 (b)
Viaduct Works -
Segment fabrication for bridge C2, D1, D2& E1 -
Segments erection by LG at bridges C3, C2 -
Segments erection by crane at bridge D1 and E1 -
SOP construction at E2-01, E2-03, D2-01 -
Construction of pile cap and installation of
bridge rotation components at pier D2-01 -
Design and fabrication of falsework for Bridge B1 (c)
South Team Works -
TWSRW ¡V
Road work and UUs laying (Section P800 CH 235 to 450). -
TWSRW ¡V Construction work of middle berm at
FS04. -
TWSRW - CLP 11 kv
cable diversion work (1ST) -
TWSRW ¡V Gas (IPA400 and HP600) diversion work -
TWSRW ¡V Foundation work of D2-04M -
TWSRE ¡V Form D300 new road, BBI footing,
relocation of existing BBI and road diversion -
TWSRE ¡V Drainage Diversion, Road Drain, UUs
laying (HKT, CLP, TCSS, Irrigation) -
HKY FB (East) ¡V Construction of extension roof,
install subframe, cladding, E&M -
HKY FB (West) ¡V Construction of LT2
(Foundation) -
E3-04a, E3-05M, E4-01 and E4-02 ¡V cap
construction. -
NB109 ¡V Bay 9~12 base slab construction. Bay 5
to 12 wall construction. -
NB69 ¡V Bay 6~8 ELS excavation and base slab
construction. -
NB110 ¡V Bay 3~5 Base slab and wall
construction. (d)
Form Traveler -
E3-03 ¡V Relocate to E3-01 -
E2-02 ¡V construction 10th to 14th pair -
D2-02 ¡V construction 1st to 2nd pair -
D2-03 ¡V erection of form traveller
no. 4 -
E2-01 - Fabrication & erection of 5th set
of form traveler. |
ND/2019/06 |
The construction phase has been completed
and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1,
2, 4 and 5 (c)
Construction of box culvert at Portion
2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at
Portion 4 (f)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (g)
Mini piling works at Portion 4 (h)
Construction of noise barrier at
Portion 4 and 5 (i)
Waterworks at Portion 1, 2 and 4 |