Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (August 2023)

ND/2019/01

(a)          Drainage works at Portion 1a

(b)         Watermain works at Portion 1b

(c)          Site formation and socket-H piling at Portion 1c

(d)         Temporary storage of material at Portion 1e

(e)          Site clearance, site formation and construction of subway, drainage works and road works at Portion 2

(f)          Sheet piling, drainage works and construction of haul road and watermain works at Portion 3

(g)         Watermains works at Portion 5

(h)         Drainage works and backfilling at Portion 6a

(i)           No activities carried out at Portion 6b

(j)           Sheet pile, excavation and drainage works at Portion 7

(k)         Construction of retaining wall, RC construction of fresh water service reservoir, construction of WSD¡¦s maintenance access, drainage works and backfilling works at Portion 8a

(l)           Pipe jacking at LWSC¡¦s car park, trenchless work and watermain construction at Portion 8b

(m)       Sheet piling, excavation, drainage and watermain works

(n)         Site clearance and removal of existing structures at Portion 13

ND/2019/02

(a)            Pipe Jacking

(b)           Backfilling

(c)            Concreting

(d)           Bedding and pipe laying

(e)            ELS

(f)            Sheet Pile Installation

(g)           Cut and Fill of Slope

ND/2019/03

(a)       Portion 1 & Portion 1A

-             Road & Drainage works and watermains works at Yin Kong Road

-             Construction of Pavilion at Yin Kong Road

(b)      Portion 2 to Portion 20C

-             Wetland creation & restoration, Dry agricultural land creation

-             Construction of compacted earth path

-             Construction of Water Treatment Wetland

-             Tree felling and tree pruning work

-             Construction of Lodging Facility

-             Construction of Dry Weather Flow Interception (DWFI)

-             Construction of Car Park and Farmer¡¦s Forum

ND/2019/04

(a)           Tree Felling

(b)           Pile Cap

(c)           Back Filling

(d)           Excavation

(e)           Grouting

(f)            Sheet Piling

(g)           Road works

(h)           Formwork Erection

(i)            Rebar Fixing

(j)            Pre-drill

(k)           Bore pile

(l)            ELS

ND/2019/05

(a)          The segment erection using launching gantry is critical to completion of section 4.

(b)         The pier D2-01 with bridge rotation system is critical to completion of section 5.

(c)          The erection of 3rd form traveler at D2-02 is in progress.

(d)         5th set of form traveler is under fabrication off-site to be used at E2-01.

ND/2019/06

The construction phase was completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)            Road works at Portion 1, 4 and 5

(b)           C&D waste disposal at Portion 1, 2, 4 and 5

(c)            Drainage works, Sewerage works at Portion 2, 3, 4 and 5

(d)           Construction of box culvert at Portion 2

(e)            Filling works at Portion 2 and 4

(f)            Construction of site haul road at Portion 4

(g)           Waterworks at Portion 1, 2 and 4