Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities (May to July 2023) |
ND/2019/01 |
(a)
Site
Clearance, tree felling, removal of existing structures, slope work and
drainage works in Portion 1a (b)
Excavation,
backfilling, construction of hoarding/fencing and road works and tree felling
in Portion 1b (c)
Site clearance,
site formation and socket H piling in Portion 1c (d)
Temporary
storage of material and site formation in Portion 1e (e)
Tree
felling, site formation work and construction of subway in Portion 2 (f)
Excavation,
backfilling and drainage works in Portion 3 (g)
Watermain,
excavation, backfilling, road works, sheet piling and pipe jacking in Portion
5 (h)
Drainage
works, backfilling, road works, watermains work in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
formation, sheet piling, excavation and drainage works in Portion 7 (k)
Construction
of retaining wall, RC construction of fresh water reservoir, construction of WSD¡¦s
maintenance access and backfilling works and drainage works in Portion 8a (l)
Construction
of jacking pit at LWSC¡¦s car park and trenchless work, excavation, watermain
construction and trial pit in Portion 8b (m)
Sheet
piling, excavation, drainage works and watermain construction in Portion 9b (n)
Stockpile
of soil in Portion 9c (o)
Road
works and site clearance in Portion 10a (p)
Road works
and site clearance in Portion 10b (q)
Site clearance, tree felling, remove of existing
structure in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road &
Drainage works and watermains works at Yin Kong Road -
Construction of Pai Lau -
Installation of Street Lighting -
Construction of Pavilion at Yin Kong Road (b)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural
land creation -
Construction of Tea House Pavilion -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception (DWFI) |
ND/2019/04 |
(a)
Tree Felling and transplant (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Pre-drill (i)
Bore pile (j)
ELS |
ND/2019/05 |
(a)
North Team Works -
ELS works and Pile cap construction at B2-01,
B2-02, B2-03, C2-04b & D2-01 -
Pier construction at C2-03b, C2-04b, D2-01 &
E2-01. -
Pier head construction at C2-03b, C2-04b, C1-01a
& E2-01 -
Cross head construction at C2-01, C2-02, C3-02. -
Slope works, road works and drainage work at
Jockey Club Road (3SW-C/F63), Tong Hang -
Junction and Portion VI (FS28 & 29) Viaduct Works -
Segment fabrication for bridge C2 & D1 &
E1. -
Segments erection by LG at bridges C4, C3. -
Segments erection by crane at bridge D1 and E1. -
T-span construction by form traveler at Pier
E2-02, E3-03, D2-02, E3-01 -
SOP construction at E3-02, D2-03, E2-01 -
Construction of pile cap and installation of
bridge rotation components at pier D2-01. -
Design and fabrication of 3rd and 4th set of form
traveler. -
Design and fabrication of truss formwork for
Bridge B1. -
Erection of tower crane at E2-01. (b)
South Team Works -
TWSRW ¡V Road work (section ch
250 to 450). UU diversion. -
TWSRW ¡V Soil nail and ranking drain for FS04.
Outage of CLP 132 kv. -
TWSRE ¡V Form D300 new road, BBI footing,
relocation of existing BBI and road diversion -
HKY FB (East) ¡V construction of extension roof -
HKY FB (West) ¡V Construction of LT2 -
E2-03 ¡V Pier head construction. -
E3-04a, E3-05M, E4-01 and E4-02 ¡V cap
construction. -
NB109 ¡V bay 5~8, base slab construction. -
NB69 ¡V ELS excavation |
ND/2019/06 |
The construction phase has
been completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1,
2, 4 and 5 (c)
Construction of box culvert at Portion
2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at
Portion 4 (f)
Drainage works, Sewerage works at
Portion 1, 3, 4 and 5 (g)
Mini piling works at Portion 4 (h)
Construction of noise barrier at
Portion 4 and 5 (i)
Waterworks at Portion 1 and 4 |