Table 10.2       Observations and Recommendations during Site Audits

Parameters

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

 

Waste/Chemical Management

27/04/2023

General refuse should be disposed of properly and regularly.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/02

Water Quality

12/04/2023

To enhance water mitigation measures surrounding exposed sloped works area on river bank at 河口 (Portion3, near Castle Peak Road).

Improvement/Rectification was observed during follow-up audit session on 21 April 2023.

Waste/Chemical Management

03/04/2023

Provide drip tray for chemical/fuel containers.

Item remarked as 230412-R01. Follow-up action is needed to be review.

12/04/2023

Item remarked as 230421-R01. Follow-up action is needed to be review.

21/04/2023

Improvement/Rectification was observed during follow-up audit session on 26 April 2023.

Contract No.: ND/2019/03

Air Quality

31/03/2023

Dusty debris was observed at Yin Kong Road. Contractor was reminded to clear the dusty debris immediately.

Item remarked as 230406-O01. Follow-up action is needed to be review.

06/04/2023

Item remarked as 230413-O01. Follow-up action is needed to be review.

13/04/2023

Improvement/Rectification was observed during follow-up audit session on 18 April 2023.

28/04/2023

Follow-up action is needed to be reported in the following month.

Water Quality

31/03/2023

Clear the wheel-washing bay regularly.

Item remarked as 230406-O02. Follow-up action is needed to be review.

06/04/2023

Provide adequate wheel-washing facilities for each vehicle exits, suitable for the current temporary traffic arrangement, and ensure that vehicles are properly washed before leaving the site.

Item remarked as 230413-O02. Follow-up action is needed to be review.

13/04/2023

Item remarked as 230418-O01. Follow-up action is needed to be review.

18/04/2023

Item remarked as 230428-O01. Follow-up action is needed to be review.

28/04/2023

Follow-up action is needed to be reported in the following month.

Waste / Chemical Management

31/03/2023

Provide drip tray for chemical/fuel containers.

Item remarked as 230406-R01. Follow-up action is needed to be review.

06/04/2023

Item remarked as 230413-R02. Follow-up action is needed to be review.

13/04/2023

Item remarked as 230418-R01. Follow-up action is needed to be review.

18/04/2023

Item remarked as 230428-R01. Follow-up action is needed to be review.

28/04/2023

Follow-up action is needed to be reported in the following month.

Landscape & Visual

06/04/2023

Remove any construction material from tree protection zone.

Item remarked as 230413-R02. Follow-up action is needed to be review.

13/04/2023

Item remarked as 230418-R02. Follow-up action is needed to be review.

18/04/2023

Item remarked as 230428-R02. Follow-up action is needed to be review.

28/04/2023

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/04

Water Quality

30/03/2023

Covering of stockpile is required to minimize the muddy runoff during rainstorm.

Item remarked as 230404-R01. Follow-up action is needed to be review.

04/04/2023

Item remarked as 230413-R01. Follow-up action is needed to be review.

13/04/2023

Item remarked as 230420-R01. Follow-up action is needed to be review.

20/04/2023

Improvement/Rectification was observed during follow-up audit session on 26 April 2023.

Contract No.: ND/2019/05

Waste/Chemical Management

03/04/2023

Provide drip tray for chemical/fuel containers.

Improvement/Rectification was observed during follow-up audit session on 11 April 2023.

Water Quality

27/03/2023

Should provide adequate capacity of water treatment to prevent muddy runoff going through site surface in Kwu Tung site.

Improvement/Rectification was observed during follow-up audit session on 3 April 2023.

03/04/2023

Discharge of muddy water was observed. Enhance the water mitigation measure in Tai Wo Service Road West.

Item remarked as 230411-R01. Follow-up action is needed to be review.

11/04/2023

Improvement/Rectification was observed during follow-up audit session on 20 April 2023.

 

20/04/2023

The drainage channel at FS04 should be properly protected to clear the soil nearby.

Improvement/Rectification was observed during follow-up audit session on 24 April 2023.

Contract No.: ND/2019/06

--

--

--

--

Contract No.: ND/2019/07

--

--

--

--