Table IV Summary Table for Site Activities in the coming Three
Months
Contract No. |
Site Activities (October 2022 to December 2022) |
ND/2019/01 |
(a)
Site
Clearance, tree felling, removal of existing structures, site formation and
G.I works in Portion 1a (b)
Sheet
piling, excavation, backfilling, drainage works, construction of hoarding,
road works and noise barrier in Portion 1b (c)
Site
clearance, removal of existing structures and site formation in Portion 1c (d)
Temporary
storage of material and site formation in Portion 1e (e)
Site
clearance, tree felling, site formation work and construction of subway in
Portion 2 (f)
Excavation,
backfilling and drainage works in Portion 3 (g)
Drainage
works, watermain, excavation, backfilling, road works and sheet piling in
Portion 5 (h)
Drainage
works, backfilling and road works in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
formation, sheet piling, excavation and drainage works in Portion 7 (k)
Construction
of retaining wall, slope drainage and maintenance access construction, RC
construction of flushing water service reservoir and excavation of fresh
water reservoir, pipe pile wall of WSD¡¦s maintenance access and backfilling
works in Portion 8a (l)
ELS for
jacking pit at LWSC¡¦s car park and trenchless work in Portion 8b (m)
Sheet
piling, excavation, drainage works and constructure of retaining wall and
soil nail in Portion 9b (n)
Stockpile
of soil in Portion 9c (o)
Excavation,
sheet piling for ELS, drainage works, road construction and utilities works
in Portion 10a (p)
Sheet
piling, excavation and drainage works in Portion 10b |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Water
Pipe Laying at Yin Kong Road -
Construction
of Pai Lau (b)
Long
Valley -
Construction
of Compacted Earth Bund / Walkway -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Storage Sheds -
Construction
of DWFI -
Wetland Creation & Restoration works |
ND/2019/04 |
(a)
Bored
piling (b)
Predrill (c)
ELS (d)
Excavation
(e)
Tree
felling (f)
Pile
cap construction (g)
Drainage
works |
ND/2019/05 |
(a)
North Team Works -
Pre-drilling for bored piles at B2-03-P3, P5, P6 -
Bored piling at B1, B2 & C1(Portion II) and
D2-01. -
ELS works and Pile cap construction at B1-01m,
B1-02ab, C1-01b, C1-02b, C1-03ab, C2-01, C2-02, C2-03a, C2-04a, C3-01a,
C3-02, D1-02 and E2-01. -
Pier construction at B1-02ab, C1-01ab, C1-02ab,
C1-03ab, C1-04ab, C2-01, C2-02, D1-02, E1-04 & E2-01. (b)
Viaduct Works -
Segment fabrication for bridge C2 & C3 &
D1 & E1. -
Remaining components of Launching Girder (LG)
delivery to site and assembly works. -
Segments erection for bridges D1 and E1. -
2nd set FT delivery. To be used in
September-2022. -
3rd set FT design and fabrication. To be used in
Feb-2023. -
4th set FT design and fabrication. To be used in
May-2023. -
Complete construction of pile caps E2-01 and
D2-01 and installation of cast-in rotation bridge components. -
Bridge rotation system fabrication completion and
delivery to site (c)
South Team Works -
Venton Area ¡V Construct new road (section from
Venton to Kei Kee). -
Portion 13 ¡V Fw52 bay 1 to 4a, backfilling to
formation level and Gas main laying. -
Portion 17 and 18 ¡V Backfilling for new TWSRW. -
Portion 18 ¡V 11kv ducts laying. -
TWSR (West) ¡V Backfilling and form new road
behind FW06 and FS04 slope works. -
TWSR (East) ¡V Form D300 new road, BBI footing -
HKY FB (East) ¡V Erection of steel bridge -
E2-03 ¡V Pile cap and Pier construction. -
E3-02 ¡V Pier construction -
D2-02 ¡V Pier head and piling for tower crane
construction. -
D2-03 ¡V Cap and Pier construction. -
E3-04b, E3-05M and E4-01 ¡V predrilling and
piling. -
NB109 ¡V base slab construction. |
ND/2019/06 |
The construction phase has been completed and handed over to AFCD since 4
April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding
at Portion 4 (c)
C&D waste disposal at
Portion 1, 2, 4 and 5 (d)
Construction of box culvert
at Portion 2 (e)
Filling works at Portion 1,
2 and 4 (f)
Construction of site haul
road at Portion 4 (g)
Drainage works, Sewerage
works at Portion 1, 3, 4 and 5 (h)
Mini
piling works at Portion 4 (i)
Construction
of noise barrier at Portion 4 and 5 (j)
Waterworks
at Portion 1 |