Table I Works
Contracts under relevant Environmental Permit(s) in the Reporting Month
Works Contracts |
Environmental
Permit No. |
Designated Project
(DP) |
Commencement date
of construction |
Contract No. ND/2019/01 – Kwu Tung North New Development Area,
Phase 1: Site Formation and Infrastructure Works |
Castle Peak Road
Diversion |
12 August 2020 |
|
Kwu Tung North New Development Area Road P1 and P2
and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement |
12 August 2020 |
||
Kwu Tung North New Development Area Road D1 to D5 |
1 June 2020 |
||
Utilization of
Treated Sewage Effluent (TSE) from Shek Wu Hui
Sewage Treatment Works |
23 March 2020 |
||
Contract No. ND/2019/02 – Kwu Tung North New Development Area,
Phase 1: Roads and Drains between Kwu Tung North
New Development Area and Shek Wu Hui |
Sewage Pumping
Stations in Kwu Tung North New Development Area |
28 October 2020 |
|
Contract No. ND/2019/03 – Kwu Tung North and Fanling North New Development Areas, Phase 1: Development
of Long Valley Nature Park |
Kwu Tung North New Development Area Road D1 to D5 |
3 July 2020 |
|
Fanling Bypass Eastern Section (New Road) |
6 October 2020 |
||
Contract No. ND/2019/04 –
Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shek
Wu San Tsuen North to Lung Yeuk Tau) |
|
Fanling Bypass Eastern Section (New Road) |
23 February 2021 |
EP-546/2017 |
Fanling North Temporary Sewage Pumping Station |
16 February 2021 |
|
Contract No.
ND/2019/05 –
Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shung
Him Tong to Kau Lung Hang) |
Fanling Bypass Eastern Section (New Road) |
1 August 2020 |
|
Contract No. ND/2019/06 –
Fanling North
New Development Area, Phase 1: Re-provisioning of North District Temporary
Wholesale Market for Agricultural Products |
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
29 October 2019 |
|
Contract No. ND/2019/07 –
Fanling North New
Development Area, Phase 1: Site Formation and Infrastructure Works |
Works area not under relevant Environmental
Permit for Phase 1 of the Project. |
1 March 2021 |