Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site
Activities (December 2022 to February 2023) |
ND/2019/01 |
(a)
Site
Clearance, tree felling, removal of existing structures, site formation and
G.I works in Portion 1a (b)
Sheet
piling, excavation, backfilling, drainage works, construction of hoarding,
road works and noise barrier in Portion 1b (c)
Site
clearance and site formation in Portion 1c (d)
Temporary
storage of material and site formation in Portion 1e (e)
Site
clearance, tree felling, site formation work and construction of subway in
Portion 2 (f)
Excavation,
backfilling and drainage works in Portion 3 (g)
Drainage
works, watermain, excavation, backfilling, road works and sheet piling in
Portion 5 (h)
Drainage
works, backfilling and road works in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
formation, sheet piling, excavation and drainage works in Portion 7 (k)
Construction
of retaining wall, maintenance access construction, RC construction of
flushing water service reservoir and fresh water reservoir, pipe pile wall of
WSD¡¦s maintenance access and backfilling works in Portion 8a (l)
ELS for
jacking pit at LWSC¡¦s car park and trenchless work, excavation and watermain
construction in Portion 8b (m)
Sheet
piling, excavation, drainage works and constructure of retaining wall and
soil nail in Portion 9b (n)
Stockpile
of soil in Portion 9c (o)
Excavation,
sheet piling for ELS, drainage works, road construction and utilities works
in Portion 10a (p)
Sheet
piling, excavation and drainage works in Portion 10b |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road work
at Yin Kong Road -
Construction
of Pai Lau (b)
Long
Valley -
Erection of Permanent Boundary Structure -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Wetland Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree Felling (b)
Predrill (c)
Bored Piling (d)
Excavation (e)
Sheet Piling (f)
Drainage Works (g)
Grouting (h)
ELS |
ND/2019/05 |
(a)
North Team Works -
Bored piling at B2 (Portion II) -
ELS works and Pile cap construction at B1-01m,
B1-02ab, C1-01ab, C1-02ab, C2-03ab, C2-04b, C3-01b, C3-02, D2-01 and E2-01. -
Pier construction at B1-02ab, C1-01ab, C1-02ab,
C1-03ab, C1-04b, C2-01, C2-02, C3-02, D1-02, E1-04 & E2-01. (b)
Viaduct Works -
Segment fabrication for bridge C2 & C3 &
D1 & E1. -
Segments erection for bridges D1 and E1. -
2nd set FT delivery remaining components. To be
used in October-2022. -
3rd set FT design and fabrication. To be used in
Feb-2023. -
4th set FT design and fabrication. To be used in
May-2023. -
Complete construction of pile caps E2-01 and
D2-01 and installation of cast-in rotation bridge components. -
Bridge rotation system delivery to site (b) South
Team Works -
Venton Area
¡V Construct new road (section from Venton to Kei
Kee). -
Portion 17 and 18 ¡V Telecom ducts laying. Water
main laying. -
TWSR (West) ¡V Slope work for FS06. Soil nail for
FS04. 132KV ducts laying at FS04. -
TWSR (East) ¡V Form D300 new road, BBI footing -
HKY FB (East) ¡V Erection of steel bridge -
E2-03 ¡V Pier construction. -
E3-02 ¡V Pier head construction -
D2-02 ¡V Piling for tower crane construction. -
D2-03 ¡V Cap and Pier construction. -
E3-04b, E3-05M and E4-01 ¡V piling work. -
NB109 ¡V base slab construction. |
ND/2019/06 |
The construction phase has
been completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Road works at Portion 1 (c)
C&D waste disposal at Portion 1,
2, 4 and 5 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Drainage works, sewerage works at Portion
1, 3, 4 and 5 (h)
Mini piling works at Portion 4 (i)
Construction of noise barrier at
Portion 4 and 5 |