Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (November 2022) |
ND/2019/01 |
(a)
Site clearance, removal of existing structures, site formation
and G.I works at Portion 1a (b)
Sheet piling, excavation, backfilling and drainage works at
Portion 1b (c)
Site clearance and site formation at Portion 1c (d)
Temporary storage of material at Portion 1e (e)
Site clearance, site formation and construction of subway at
Portion 2 (f)
Site clearance, excavation, sheet piling and drainage works at
Portion 3 (g)
Drainage works, watermain, excavation, backfilling and sheet
piling at Portion 5 (h)
Drainage works and backfilling at Portion 6a (i)
Operation of HAC soil treatment facility at Portion 6b (j)
Sheet piling, excavation and drainage works at Portion 7 (k)
Construction of retaining wall, maintenance access construction,
RC construction of flushing water service reservoir and fresh water service
reservoir and backfilling works at Portion 8a (l)
ELS for jacking pit at LWSC¡¦s car park and excavation for jacking
pit and trenchless work at Portion 8b (m)
Sheet piling, excavation, drainage works, construction of
retaining wall and watermain construction at Portion 9b (n)
Stockpile of soil at Portion 9c (o)
Excavation, drainage works, road works and utilities works at Portion 10a |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Water
Pipe Laying at Yin Kong Road -
Construction
of Pai Lau (b)
Long
Valley -
Construction of Compacted Earth Bund / Walkway -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction of Wetland Boardwalk -
Construction
works of Type 1 Storage House -
Construction
works of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Storage Sheds -
Construction
of DWFI -
Wetland
Creation & Restoration works -
Soiling work for Planting Shrubs and Trees |
ND/2019/04 |
(a)
Tree Felling (b)
Predrill (c)
Bored Piling (d)
Excavation (e)
Sheet Piling (f)
Drainage Works (g)
Grouting (h)
ELS |
ND/2019/05 |
(a)
The rotary drilling rig is located at B2-03. The
RCD rig located at D2-01, another one RCD rig located at E3-04b. (b)
C2-03 to C3-02 pile cap in progress, C4-02 cross
head and C3-04 portal beam in progress. (c)
TWSR-West sewage and UUs from Ch100 to
Ch450 installation works are in progress. Water main to be commenced while
materials on site. |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Road works at Portion 1 (c)
C&D waste disposal at Portion 1, 2, 4 and 5 (d)
Drainage works, sewerage works at Portion 1, 3 and 4 (e)
Construction of box culvert at Portion 2 (f)
Filling works at Portion 2 and 4 (g)
Construction of site haul road at Portion 4 (h)
Waterworks at Portion 1 |