Table 10.2       Observations and Recommendations during Site Audits

Parameters

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

 

Air Quality

01/11/2022

To increase the frequency of watering at Portion 1b.

Improvement/Rectification was observed during follow-up audit session on 8 November 2022.

Contract No.: ND/2019/02

Water Quality

24/10/2022

To enhance and properly maintain existing water mitigation measures at site boundaries.

Item remarked as 221102-R02. Follow-up action is needed to be review.

02/11/2022

Item remarked as 221109-R02. Follow-up action is needed to be review.

09/11/2022

Item remarked as 221116-R01. Follow-up action is needed to be review.

16/11/2022

Item remarked as 221123-R01. Follow-up action is needed to be review.

23/11/2022

Item remarked as 221130-R01. Follow-up action is needed to be review.

30/11/2022

Follow-up action is needed to be reported in the following month.

24/10/2022

To enhance mitigation measures to prevent water quality impact to the River Beas.

Item remarked as 221102-R01. Follow-up action is needed to be review.

02/11/2022

Item remarked as 221109-R01. Follow-up action is needed to be review.

09/11/2022

Improvement/Rectification was observed during follow-up audit session on 16 November 2022.

Contract No.: ND/2019/03

Air Quality

28/10/2022

Dusty debris were observed at the site exit of Yin Kong. Contractor was reminded to clear the dusty debris immediately.

Item remarked as 221104-O01. Follow-up action is needed to be review.

04/11/2022

Item remarked as 221111-O01. Follow-up action is needed to be review.

11/11/2022

Item remarked as 221115-O01. Follow-up action is needed to be review.

15/11/2022

Item remarked as 221125-O01. Follow-up action is needed to be review.

25/11/2022

Follow-up action is needed to be reported in the following month.

28/10/2022

Absence of NRMM label from a regulated machine.

Item Remarked as 221104-R01. Follow-up action is needed to be review.

04/11/2022

Improvement/Rectification was observed during follow-up audit session on 11 November 2022.

15/11/2022

To clear the wheel-washing bay regularly. Vehicles leaving the site should be washed with high pressure water jets.

Item remarked as 221125-R02. Follow-up action is needed to be review.

25/11/2022

Follow-up action is needed to be reported in the following month.

Water Quality

15/11/2022

Contractor was reminded to enhance water mitigation measures around the boundary of works area to avoid muddy runoff from leaking onto Yin Kong Road.

Item remarked as 221125-R01. Follow-up action is needed to be review.

25/11/2022

Follow-up action is needed to be reported in the following month.

15/11/2022

To clear the wheel-washing bay regularly. Vehicles leaving the site should be washed with high pressure water jets.

Item remarked as 221125-R02. Follow-up action is needed to be review.

25/11/2022

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/04

Water Quality

27/10/2022

Covering of stockpile is required to minimize the muddy runoff during rainstorm.

Item remarked as 221103-R01. Follow-up action is needed to be review.

03/11/2022

Item remarked as 221109-R01. Follow-up action is needed to be review.

09/11/2022

Item remarked as 221117-R01. Follow-up action is needed to be review.

17/11/2022

Item remarked as 221124-R01. Follow-up action is needed to be review.

24/11/2022

Follow-up action is needed to be reported in the following month.

09/11/2022

Silt curtain was observed damaged near Bridge F. Should maintain the silt curtain properly and check regularly.

Item remarked as 221117-R02. Follow-up action is needed to be review.

17/11/2022

Item remarked as 221124-R02. Follow-up action is needed to be review.

24/11/2022

Follow-up action is needed to be reported in the following month.

24/11/2022

Discharge of dusty debris was observed. Water mitigation measure should enhance by adding more sand bags or geotextiles.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/05

Air Quality

28/11/2022

Black smoke emission was observed. Please provide maintenance to avoid black smoke emission.

Follow-up action is needed to be reported in the following month.

Water Quality

31/10/2022

Enhance the water mitigation measure in portion 18.

Item remarked as 221107-R01. Follow-up action is needed to be review.

07/11/2022

Polluted water mitigation works still in progress. Should avoid muddy debris outside the site near portion 18.

Improvement/Rectification was observed during follow-up audit session on 17 November 2022.

07/11/2022

Treatment tank observed saturated causing muddy water discharge to public drainage. Contractor was reminded to maintain the treatment facilities properly.

Improvement/Rectification was observed during follow-up audit session on 17 November 2022.

21/11/2022

Sedimentation tank should maintain properly, regularly to provide a stable function.

Improvement/Rectification was observed during follow-up audit session on 28 November 2022.

21/11/2022

Enhance mitigation measure for stockpile. (e. g.  tarpaulin)

Improvement/Rectification was observed during follow-up audit session on 28 November 2022.

Contract No.: ND/2019/06

--

--

--

--

Contract No.: ND/2019/07

 

Waste / Chemical Management

28/10/2022

Drip tray should be provided for chemical /fuel containers.

Improvement/Rectification was observed during follow-up audit session on 4 November 2022.