11.1 No
Action/Limit Level exceedance for air quality, water quality, construction
noise, ambient arsenic and landfill gas monitoring was recorded in the
reporting month. The summary of exceedance record in the reporting month is
shown in Appendix O.
11.2 Ecological monitoring was carried out in the reporting
month. The Action and Limit Level will be compared after the issue of Final
Baseline Ecological Report.
11.3 Should the monitoring results of the environmental
monitoring parameters at any designated monitoring stations indicate that the
Action / Limit Levels are exceeded, the actions in accordance with the Event
and Action Plans in Appendix N would
be carried out.
11.4 No environmental non-compliance was recorded in the
reporting month.
11.5 No
environmental complaint was received in the reporting month. The Cumulative Complaint Log since the
commencement of the Project is presented in Appendix S.
11.6
There was no
successful environmental prosecution or notification of summons received since
the Project commencement. The Cumulative Log for environmental summon and
successful prosecution since the commencement of the Project is presented in Appendix T.