10.1
Site
audits were carried out by ET on weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures on the Contract site. The
summaries of site audits are presented in Table 10.1 and Appendix P.
Table 10.1 Summary
of Site Audit
Environmental Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly site audit with representative of the Supervisor’s
Representative and the Contractor |
3, 10, 18, 25 and 31 May
22 |
4, 11, 20 and 25 May
22 |
6, 13, 17 and 27 May
22 |
5, 11, 19 and 26 May 22 |
3, 10, 16, 23 and 31 May
22 |
5, 11, 19 and 26 May
22 |
6, 13, 20, and 27 May 22 |
Joint Site Audit with representative of the Supervisor’s
Representative, the Contractor and IEC |
18 May 22 |
20 May
22 |
17 May
22 |
11 May 22 |
16 May 22 |
N/A |
20 May 22 |
10.2
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarised in Table 10.2.
10.3
All
construction activities with significant environmental impact undertaken by
Contract No. ND/2019/06 was substantially completed in March 2022 and majority
of outstanding works have also been completed in April 2022 with defect
rectification works remain. The outstanding installation works are the
short-duration works which will be completed within 2 months during the 1-year
defect correction period. ET would record the environmental deficiency, if any
for NDTWM (EP-475/2013/A) during the 1-year defect correction period under
Contract ND/2019/04 site inspection and will email those inspection records to
the Project Team of Contract ND/2019/06 for information weekly.
Table 10.2 Observations and Recommendations during
Site Audits
|
Date |
Observations
and Recommendations |
Follow-up |
Contract No.: ND/2019/01 |
|||
-- |
-- |
-- |
-- |
Contract No.: ND/2019/02 |
|||
Water Quality |
11/05/2022 |
Enhance water mitigation measure to prevent surface runoff. |
Improvement/Rectification
was observed during follow-up audit session on 20 May 2022. |
Air Quality |
27/04/2022 |
Dusty haul road shall be watered regularly. |
Improvement/Rectification
was observed during follow-up audit session on 4 May 2022. |
11/05/2022 |
Vehicles shall be switched off while not in use. |
Improvement/Rectification
was observed during follow-up audit session on 20 May 2022. |
|
20/05/2022 |
Faded NRMM label shall be replaced. |
Improvement/Rectification
was observed during follow-up audit session on 25 May 2022. |
|
Waste / Chemical Management |
04/05/2022 |
Drip tray shall be provided for chemical storage. |
Improvement/Rectification
was observed during follow-up audit session on 11 May 2022. |
Ecology |
11/05/2022 |
The silt curtain should be properly surrounded the works and ensure
it is intact. |
Item was remarked as 220520-R01. |
20/05/2022 |
The silt curtain should be properly surrounded the works and ensure
it is intact. |
Item was remarked as 220525-R01. |
|
25/05/2022 |
The silt curtain should be properly surrounded the works and ensure
it is intact. |
Follow-up
action is needed to be reported in the following month. |
|
Contract No.: ND/2019/03 |
|||
Ecology |
17/05/2022 |
Green hoarding should be properly maintained. |
Improvement/Rectification
was observed during follow-up audit session on 27 May 2022. |
Contract No.: ND/2019/04 |
|||
Water Quality |
25/04/2022 |
To review and modify the implemented mitigation measures
to avoid the muddy surface runoff discharging to the river. |
Improvement/Rectification
was observed during follow-up audit session on 5 May 2022. |
25/04/2022 |
To enhance the drainage system and increase the
capacity of de-silting facilities. (Portion H) |
Item
was remarked as 220505-R01. |
|
05/05/2022 |
To enhance the drainage system and increase the
capacity of de-silting facilities. (Portion H) |
Item
was remarked as 220511-R01. |
|
11/05/2022 |
To enhance the drainage system and increase the
capacity of de-silting facilities. (Portion H) |
Improvement/Rectification
was observed during follow-up audit session on 19 May 2022. |
|
05/05/2022 |
To clear the U-channel regularly. |
Item
was remarked as 220511-R01. |
|
11/05/2022 |
To clear the U-channel regularly. |
Improvement/Rectification
was observed during follow-up audit session on 19 May 2022. |
|
11/05/2022 |
To clear the muddy debris on piling platform. |
Improvement/Rectification
was observed during follow-up audit session on 19 May 2022. |
|
Ecology |
25/04/2022 |
The silt curtain should be properly surrounding
the works at near bridge F and ensure it is intact. |
Improvement/Rectification
was observed during follow-up audit session on 5 May 2022. |
Contract No.: ND/2019/05 |
|||
Air Quality |
25/04/2022 |
Dusty stockpile shall be covered properly by
impervious sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 3 May 2022. |
03/05/2022 |
Dusty stockpile should be covered by impervious sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 10 May 2022. |
|
16/05/2022 |
Regulated machines should have NRMM label
displayed properly. |
Improvement/Rectification
was observed during follow-up audit session on 23 May 2022. |
|
Waste / Chemical Management |
23/05/2022 |
Clear the oil stain on the ground. |
Follow-up
action is needed to be reported in the following month. |
Contract No.: ND/2019/06 |
|||
-- |
-- |
-- |
-- |
Contract No.: ND/2019/07 |
|||
Water Quality |
13/05/2022 |
To enhance mitigation measures to prevent muddy
water overflow after rainstorms. |
Improvement/Rectification
was observed during follow-up audit session on 20 May 2022. |
10.4
According
to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
Q. The photographic records of measures as stipulated in EP to mitigate
environmental impacts in the reporting month are presented in Table 10.3.
Table 10.3 Photographic Records and Implementation
Status of Measures
EP No. |
Condition |
Photographic Record |
Implementation Status |
EP-466/2013 |
2.9 |
To
minimise adverse impacts on habitats of ecological imprtance in the vicinity of the Project, 2m high solid
dull green site barrier fences shall be erected around all active works
areas. |
^[1] |
EP-467/2013/A |
2.9 |
To
minimise adverse impacts on habitats of ecological imprtance in the vicinity of the Project, 2m high solid
dull green site barrier fences shall be erected around all active works
areas. |
^[1] |
EP-468/2013/A |
2.11 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-469/2013 |
2.7 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-473/2013/A |
2.13 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance of mitigation measure · Non-compliance
but rectified by the contractor N/A Not
Applicable at this stage as no such site activities were conducted in the
reporting period |
[1]: Barrier fences might be subjected to
change according to phasing plan designed at detailed design stage
10.5
According
to the EIA Report and the Updated EM&A Manual, the water quality mitigation
measures detailed in the documents are recommended to be implemented during the
construction phase. Water quality mitigation measures implemented by the
contractors were closely monitored to prevent water pollution, especially
during rainy season. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix Q. Specific water
quality mitigation measures for major construction works in the reporting month
are presented in Table 10.4.
Table 10.4 Specific Water Quality Mitigation Measures for Major
Construction Works in the Reporting Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Hydroseeding for
slope area |
ND/2019/02 |
Hard paved exposed
haul road |
Hard paved exposed slope surface |
ND/2019/03 |
Hard paved exposed
haul road |
Regular clearance of
water for wheel washing facility |
ND/2019/04 |
Hard paved exposed slope surface |
Deployment of silt curtain around works area
in Ng Tung River |
ND/2019/05 |
Covering dusty
stockpile |
Provision of sand bags around works area |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
De-silting waste water before discharge |
Water quality mitigation measures for site(s) in operation
phase, remaining defect works |
||
ND/2019/06 |
Hard paved exposed
haul road |
Hard paved exposed haul road |
10.6
Waste generated
from Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05
and ND/2019/07 include inert construction and demolition (C&D) materials
and non-inert C&D wastes in the Reporting Month. The site of ND/2019/06 was
handed over to AFCD for operation since 4 April 2022.
10.7
The amount of wastes generated by the construction works of the Contract
No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05 and ND/2019/07 during the reporting month are shown in Appendix R. The site of
ND/2019/06 was handed over to AFCD for operation since 4 April 2022.
10.8
The
Contractors are advised to minimize the wastes generated through recycling or
reusing. All mitigation measures stipulated in the Updated EM&A Manual and
waste management plans shall be fully implemented. The status of implementation
of waste management and reduction measures are summited in Appendix Q.
10.9
From
the findings of EIA Report, the area of Long Valley has been assessed as of
high to very high ecological value and is the largest contiguous area of
freshwater wetland habitats in Hong Kong. To safeguard the ecological value of
Long Valley, about 37 hectares of land in Long Valley has been proposed to
develop into Long Valley Nature Park (LVNP) for conserving and enhancing the
ecologically important environment as well as for compensation of the wetland
loss due to the NDA development.
10.10
LVNP is developed according to approved
Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. The
HCMP provides a framework and specifications for development and management of
the LVNP and guides the development to maintain and enhance the 37ha of
low-lying wetland habitats.
10.11
Regarding
to the design, the zoning of land use in the LVNP is intended to maintain the
existing mosaic pattern of wet and dry agriculture, while controlling the
activities that could potentially disturb target habitats and species. The LVNP
will divide into three broad zones of land use as below:
•
Biodiversity
Zone of about 21 hectares largely designated for biodiversity conservation
through cultivation of specified crops and habitat management.
•
Agricultural
Zone of about 11 hectares designated for commercially focuses crop production
and eco-friendly agricultural practice for farming.
•
Visitor
Zone of about 5 hectares designed to accommodate visitors as well as storage
and other facilities and for educational purposes.
10.12
The
construction of the LVNP started in late 2019 and is expected to be completed
in 2023. During construction period, the progress of construction and wetland
enhancement works are under observation by different stakeholders including
AFCD and green groups. Close communication between AFCD and CEDD are conducted
to exchange views on conservation, restoration and
management of habitats as well as on the planning and design of the park. Also,
advices from green groups, Hong Kong Bird Watching Society (HKBWS) and The
Conservancy Association (CA), are taken on habitat management of Long Valley
and potential effects on habitat and wildlife of each individual work conducted
in Long Valley. Regular meeting are held monthly on 13th
May 2022 in the reporting month to share the progress of LVNP with different
stakeholders, including CEDD, AFCD, CA, HKBWS, Contractor, ET, IEC and farmers.
10.13 Proposals on wetland creation and
restoration, dry agricultural land creation, pond creation, water treatment
wetland and design of irrigation channel are submitted by the Contractor to
achieve the objectives stated in HCMP and accepted by the Engineer with consent
from AFCD before implementation. The Contractor will consult with the
stakeholders for recommendations and suggestions on mitigation measures to minimise the environmental impacts arising from
construction works. The progress of works will be arranged to minimise impacts to avifauna and maintain the habitat for
avifauna. The photographic records of site activities in LVNP are presented in Table 10.5.
Table 10.5 Photographic Records of Site Activities in LVNP
Agricultural
practice are continued in existing farmland to
maintain habitats in Long Valley |
|||
Open water Habitat |
Open water Habitat |
Chinese arrowhead pond |
|
Creation
of wetland with designated habitat for biodiversity conservation |
|||
Planting
of paddy rice to provide foraging ground for Yellow-breasted Bunting |
|||
Retention
of washing bay for amphibians breeding |
Enhancement
of irrigation channel to provide reliable water source for farmland in Long
Valley |
||
Provision
of bird island (hidden area) |
Restoring
of water flea pond to provide food source to water birds |
||
Construction
of storage sheds for farmers |
A Chlidonias leucopterus was recorded |
||
Wet
agricultural land |
Provision
of noise barrier for noisy works in Long Valley |
||