Table IV Summary
Table for Site Activities in the coming Two Months
Contract No. |
Site Activities (June 2022 and
July 2022) |
ND/2019/01 |
(a)
Site Clearance, remove of existing structures, tree felling at
Portion 1a (b)
Site clearance, backfilling, ground investigation, sheet piling, excavation and drainage at Portion 1b (c)
Site clearance, demolition of existing structures at Portion 1c (d)
Site clearance, tree felling at Portion 1e (e)
Site clearance, tree felling, temporary road construction, site
formation work at Portion 2 (f)
Site clearance, backfilling, excavation, tree felling at Portion
3 (g)
Site Clearance, sheet piling and excavation, drainage works and
temporary road constructure, watermain at Portion 5 (h)
Site Clearance, sheet piling and excavation, pipes laying,
backfilling, construction of KB01 retaining wall at Portion 6a (i)
Operation of HAC treatment facility at Portion 6b (j)
Site Clearance, sheet piling and excavation, pipes laying at
Portion 7 (k)
Construction of retaining wall, slope cutting, slope drainage and
maintenance access construction, RC construction of flushing water service
reservoir and fresh water reservoir, pipe pile wall of WSD’s maintenance access, backfilling
works at Portion 8a (l)
Grouting for receiving pit , trenchless
works, excavation, , ELS for jacking pit at LWSC’s car park at Protion
8b (m)
Sheet piling and excavation, drainage works ,
GI works at Portion 9b (n)
Stockpile of soil, excavation at Portion 9c (o)
Excavation, sheet piling for ELS, drainage works, road
construction, utilities laying at Portion 10a (p)
Sheet piling and excavation, drainage works at Protion 10b (q)
Construction of MBR at Portion 11b (r)
Construction of temporary sewage pumping station at Portion 14 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation, and (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage works
at Yin Kong Road -
Construction
of Pai Lau (b) Long Valley -
Erection
of Permanent Boundary Structure -
Construction
of Irrigation Channel -
Construction
works of Type 1 Storage House -
Construction
works of Type 2 Storage House -
Construction
of Tea House -
Construction
of Decking & Sluices -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction
of Ditches -
Construction
of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree felling (b)
Predrill (c)
Bored piling (d)
Excavation (e)
Sheet piling (f)
ELS |
ND/2019/05 |
(a)
North Team Works -
Pre-drilling for bored piles at B2-03-P3, P5, P6 -
Bored piling at B1& B2(Portion II), C1(Portion
II) & D2-01. -
ELS and Pile cap construction at C1-01b, C1-02b,
C1-03, C1-04, C2-02, C2-03a, C2-04a, C3- -
01a, C3-02, D1-02 & E2-01 -
C3-03 & C3-04 Portal Beam -
Raft footing construction at C4-02 -
Pier construction at C101b, C102b, C1-03, C1-04,
C2-01, C3-03a, C3-04ab, C4-02, D1-02, D1- -
03, D1-04 & E1-04. (b)
Viaduct Works -
Segment fabrication for bridge C4 & C3 &
D1 & E1. -
Launching Girder (LG) delivery to site. -
Erection of 1st pair non match cast segments at
pier C4-03. -
LG pre-assembly between pier C4-03 to C4-04a/bM. -
Cast in-situ SOP construction at Pier E2-02,
E3-03. -
2nd set FT fabrication and delivery. Target to
deliver in May-2022. -
3rd set FT design and fabrication. To be used in
Feb-2023. -
4th set FT design and fabrication. To be used in
May-2023. -
Bridge rotation system fabrication completion and
delivery to site (c)
South Team Works -
Venton Area
– Telecom ducts laying. -
Portion 13 – UU ducts laying after backfilling
completed at FW 52 bay 1 to bay 3. -
Portion 17 and 18 – Construction of DN 600 and
DN450 sewer. RW 52 bay 4a, 4b and 5 -
Portion 18 – 132kv ducts laying and Gas main
laying. -
TWSR (West) – RW06 construction and FS04 slope
works. -
HKY FB (East) – construction of P01 -
Portion 11 – DN1200 and DN600 watermain laying
work. -
E2-03 – Pile cap construction. -
E3-01 – Pier construction. -
E3-02 – Cap and Pier construction -
D2-02 – Pier construction. -
D2-03 – Cap and Pier construction. -
E3-04a – Piling works. -
E3-04b – predrilling. |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding at Portion 3 and 4 (c)
C&D waste disposal at Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 (e)
Construction of box culvert at Portion 2 (f)
Filling works at Portion 1, 2 and 4 (g)
Tree felling / Disposal of yard waste at Portion 4 (h)
Construction of site haul road at Portion 4 and 5 (i)
Drainage works, Sewage works and Portion 1, 3, 4 and 5 (j)
Mini piling works at Portion 4 and 5 (k)
Construction of noise barrier at
Portion 5 (l)
Waterworks at Portion 1 |