5.1
In
accordance with the Updated EM&A Manual, impact water quality monitoring
shall be carried out three days per week at all the designated monitoring stations
during the construction period. The measurement periods are during the
construction of channel specified in Table 4.1 of Updated EM&A Manual. The
interval between two sets of monitoring shall not be less than 36 hours.
5.2
Replicate
in-situ measurements of Dissolved Oxygen (DO), temperature, turbidity, pH,
Suspended Solids (SS) and samples for Suspended Solids (SS), ammonia nitrogen,
unionized ammonia, nitrate nitrogen and orthophosphate from each independent
sampling event shall be collected to ensure a robust statistically
interpretable database.
5.3
Appendix B shows the established Action
and Limit Levels for the water quality monitoring work according to pre-construction ET¡¦s Updated EM&A Manual and
Baseline Water Quality Monitoring Report (KTN & FLN NDA).
5.4
Table 5.1
summarized the monitoring parameters, monitoring periods and frequencies of the
water quality monitoring.
Table 5.1 Water
Quality Monitoring Parameters and Frequency
Parameters, unit |
Depth |
Frequency |
¡P
Temperature(¢XC) ¡P
pH(pH unit) ¡P
turbidity (NTU) ¡P
water depth (m) ¡P
salinity (ppt) ¡P
DO (mg/L and % of saturation) ¡P
SS (mg/L) ¡P
Ammonia Nitrogen (NH3-N)
(mg NH3-N/L) ¡P
Unionized Ammonia (UIA) (mg/L) ¡P
Nitrate-nitrogen (NO3-N)
(mg NO3--N/L) ¡P
Ortho-phosphate (PO4)
(mg PO43--P/L) |
¡P
3 water depths: 1m below
water surface, mid-depth and 1m above river bed. ¡P
If the water depth was less than 3m, mid-depth
sampling only. ¡P
If water depth was less than 6m, mid-depth may be
omitted. |
3 days per week during construction of channel |
5.5
According to the
Section 5.6.1.2 of approved EIA Report, the potential water quality impact
during construction is due to the alternation of natural streams (i.e.
channelization of Ma Tso Lung Stream and Siu Hang San Tsuen Stream) as these
two streams are the ecological importance streams.
5.6
No construction of
channel was carried out at Ma Tso Lung Stream and Siu Hang San Tsuen Stream
during the reporting month. Therefore, no water quality monitoring was
conducted.
Additional Water Quality Monitoring
5.7
Additional Water
Quality Monitoring shall be carried out at River Beas, River Indus and near Siu
Hang San Tsuen Stream three days per week at all designated monitoring stations
during the construction period. The measurement period are during the
construction site drainage along River Beas, construction of footbridge across
River Beas and during construction of bridge across River Indus.
5.8
Replicate in-situ
measurement and samples from each independent sampling event were collected to
ensure a robust statistically interpretable database. DO, temperature,
turbidity and pH were measured in-situ whereas SS and arsenic were determined
by an accredited laboratory. Other relevant data were recorded, including
monitoring location / position, time, water depth, weather conditions and any
special phenomena or work underway at the construction site.
5.9
For all the
monitoring stations, sampling were taken at 3 water depths, namely 1m below the
water surface, mid depth and 1m above the river bed. For stations that are less
than 3m in depth, only the mid depth sample was taken. Should the water depth
is less than 6m, in which case the mid-depth station may be omitted. The
interval between two sampling surveys was not less than 36 hours.
5.10 Appendix
B shows the established Action and
Limit Levels for the environmental monitoring works
5.11 Additional impact water quality monitoring was
conducted at 6 monitoring stations (SYR-CS1, SYR-IS1, NTR-CS1, NTR-IS1,
SHST-IS2, MWR-IS3) which is summarised in Table
5.2. The location of monitoring stations are shown in Figure 5 and 6.
Table
5.2 Additional
Water Quality Monitoring Stations
Station |
Description |
Locations |
Measurement
Periods |
River Beas |
|||
SYR-CS1 |
Control Station |
Upstream of river |
During the construction site drainage along River
Beas and construction of footbridge across River Beas |
SYR-IS1 |
Impact Station |
Downstream of
river |
|
River Indus and near Siu Hang San Tsuen Stream |
|||
NTR-CS1 |
Control Station |
Upstream of river |
During
construction of bridge across River Indus |
NTR-IS1 |
Impact Station |
Downstream of river |
|
SHST-IS2 |
Impact Station |
Water sensitive receiver at near Siu Hang San Tsuen
Stream |
|
MWR-IS3 |
Impact Station |
Water sensitive receiver at near
Ma Wat River |
5.12
A multi-parameter meters (Model YSI EXO)
was used to measure DO, turbidity, salinity, pH and temperature.
Dissolved
Oxygen (DO) and Temperature Measuring Equipment
5.13 The instrument for measuring dissolved oxygen and
temperature should be portable and weatherproof complete with cable, sensor,
and use DC power source. The equipment was capable of measuring:
¡P
A dissolved
oxygen level in the range of 0-20mg/L and 0-200% saturation; and
¡P
The temperature
within 0-45 degree Celsius.
5.14 The equipment had a membrane electrode with
automatic temperature compensation complete with a cable.
5.15 Sufficient stocks of spare electrodes and cables
were available for replacement where necessary.
5.16 Salinity compensation was built-in in the DO
equipment. In-situ salinity was
measured to calibrate the DO equipment prior to each DO measurement.
5.17 Turbidity was measured in situ by using the
nephelometric method. The instrument was portable and weatherproof using a DC
power sources complete with cable, sensor and comprehensive operation manuals.
The equipment was capable of measuring turbidity between 0-1000 NTU. The probe
cable was not less than 25m in length. The meter was calibrated in order to establish
the relationship between NTU units and the levels of suspended Solids.
5.18 A portable salinometer capable of recording
salinity within the range of 0-40 parts per thousand (ppt) was used for
salinity measurement.
5.19 A portable, battery-operated and hand held echo
sounder was used for the determination of water depth at each designated
monitoring station.
pH
5.20 The instrument was consisting of a potentiometer, a
glass electrode, a reference electrode and a temperature-compensating device.
It was readable to 0.1pH in a range of 0 to 14. Standard buffer solutions of at
least pH 7 and pH 10 were used for calibration of the instrument before and
after use.
Water Sampling
for Laboratory Analysis
5.21
A water sampler, consisting of a
transparent Polyvinyl Chloride (PVC) of a capacity of not less than two litres
which can be effectively sealed with cups at both ends was used. The water
sampler had a positive latching system to keep it open and prevent premature
closure until released by a messenger when the sampler was at the selected
water depth. In addition, a sampling cup attached to a fixed or extendable rod
was also used for sampling at the monitoring stations with swallow water.
Sample Container and Storage
5.22
Following collection, water samples for
laboratory analysis were stored in high density polyethylene bottles with
appropriate preservatives added, packed in the ice (cooled to 4oC
without being frozen). The sample were delivered to WELLAB Limited (HOKLAS
Registration No.083) and analysed as soon as possible after collection of the
water samples. Sufficient volume of samples was collected to achieve the
detection limit.
Calibration of
In Situ Instruments
5.23
The pH meter, DO meter and turbidimeter
were checked and calibrated before use. DO meter and turbidimeter were
certified by WELLAB Limited before use and subsequently re-calibrated at
quarterly basis throughout all stage of water quality monitoring programme.
Response of sensors and electrodes were checked with certified standard
solutions before each use. Wet bulb calibration for a DO meter was carried out
before measurement at each monitoring station.
5.24
For the on-site calibration of field
equipment (Multi-parameter Water Quality System), the BS 1427:2009, ¡§Guide to
on-site test methods for analysis of waters¡¨ was observed.
Back-up Equipment
5.25
Sufficient stocks of spare parts were
maintained for replacements when necessary. Backup monitoring equipment was
also be made available so that monitoring can proceed uninterrupted even when
some equipment is under maintenance, calibration, etc.
5.26
Table
5.3
summarizes the equipment used in the water quality monitoring program. The
copies of the calibration certificates of multi-parameter water quality system
are shown in the Appendix C.
Table 5.3 Water
Quality Monitoring Equipment
Equipment |
Model and Make |
Qty. |
Water sampler and sampling cup |
A 2-Litre transparent PVC cylinder with latex cups at both ends and
sampling cup for monitoring stations with swallow water |
1 |
Sonar Water Depth Detector |
Garmin Striker plus 4 |
1 |
Multi-parameter Water Quality System |
YSI EXO 1 |
2 |
5.27
Table
5.4 summarizes
the monitoring parameters and frequencies of the additional water quality
monitoring. The water quality monitoring schedule for the reporting month is
shown in Appendix D.
Table
5.4 Additional
Water Quality Monitoring Parameters and Frequency
Monitoring Station(s) |
Parameters, unit |
Depth |
Frequency |
|
River Beas |
SYR-CS1 SYR-IS1 |
¡P
Temperature (oC) ¡P
pH (pHunit) ¡P
Turbidity (NTU) ¡P
Water depth (m) ¡P
Salinity (ppt) ¡P
Dissolved Oxygen
(DO) (mg/L and % of saturation) ¡P
Suspended Solids
(SS) (mg/L) ¡P
Arsenic (As)
(µg/L) |
¡P
3 water depths:
1m below water surface, mid-depth and 1m above river bed. ¡P
If the water
depth was less than 3m, mid-depth sampling only. ¡P
If water depth
was less than 6m, mid-depth might be omitted. |
3 days per week |
River Indus and near Siu
Hang San Tsuen Stream |
NTR-CS1 NTR-IS1 SHST-IS2 MWR-IS3 |
¡P
Temperature (oC) ¡P
pH (pH unit) ¡P
Turbidity (NTU) ¡P
Water depth (m) ¡P
Salinity (ppt) ¡P
Dissolved Oxygen
(DO) (mg/L and % of saturation) ¡P
Suspended Solids
(SS)(mg/L) |
5.28
Monitoring location and position, time, sampling
depth, weather conditions and any special phenomena or work underway nearby was
also be recorded
Instrumentation
5.29
A multi-parameter meters (Model YSI EXO) was
used to measure DO, turbidity, salinity, pH and temperature.
Operating/Analytical
Procedures
5.30
At each measurement, two consecutive
measurements of DO concentration, DO saturation, salinity, turbidity, pH and
temperature were taken. The probes were retrieved out of the water after the
first measurement and then re-deployed for the second measurement. Where the
difference in the value between the first and second readings of each set was
more than 25% of the value of the first reading, the reading was discarded and
further readings were taken.
Laboratory
Analytical Methods
5.31
Duplicate samples from each independent
sampling event are required for all parameter. Analysis of suspended solids and
arsenic were carried out by WELLAB Ltd. and comprehensive quality assurance and
control procedures in place in order to ensure the quality and consistency in
results. The reporting limit and detection limit are provided in Table 5.5.
Table 5.5 Method
for Laboratory Analysis for Water Samples
Determinant |
Proposed Method |
Limit of Reporting |
Total
Suspend Solids (SS) |
APHA 17ed
2540 D |
2.5 mg/L |
Arsenic
(As) |
In-house
method SOP022 (ICP-AES) and SOP076 (ICP-MS) |
1 µg/L |
5.32
Water sampling equipment used during the course
of the monitoring process was decontaminated by manual washing and rinsed with
distilled water after each sampling event. All of the disposal equipment was
discarded after the sampling.
Sampling
Management and Supervision
5.33
All sampling bottles were labelled with
the sample I.D (Including the sampling station), laboratory number and sampling
date. Water samples were dispatched to the testing laboratory for analysis as
soon as possible. All the collected samples were stored in a cool box to keep
the temperature less than 4oC but without frozen. All water samples
were handled under chain of custody protocols and relinquished to the
laboratory representatives at locations specified by the laboratory.
Quality Control Measures
for Sample Testing
5.34
The samples testing and following QC
programme were performed by WELLAB Ltd. for
every batch of 20 samples:
¡P
One method blank; and
¡P
One set of QC sample.
5.35
All additional water quality monitoring was
conducted as scheduled in the reporting month. The water quality monitoring
schedule for this reporting month is shown in Appendix D.
5.36
The monitoring results and graphical
presentation of additional water quality monitoring at the monitoring stations
are shown in Appendix G.
5.37 Two (2) Limit Level for DO, five (5) Limit Level exceedances for turbidity, five (5) Limit Level exceedances for suspended solids of impact water quality monitoring were recorded. After investigation, all exceedances were considered non-projected related. The summary of exceedance record in the reporting month is shown in Appendix O.
5.38
Should
any project related non-compliance of the criteria occur, action in accordance
with the Action Plan in Appendix N
shall be carried out.