10            ENVIRONMENTAL SITE INSPECTION

Site Audits

10.1       Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures on the Contract site.  The summaries of site audits are presented in Table 10.1 and Appendix P.

Table 10.1   Summary of Site Audit

Environmental Site Inspection

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/04

ND/2019/05

ND/2019/06

ND/2019/07

Weekly site audit with representative of the Supervisor¡¦s Representative and the Contractor

1, 8, 16, 22 and 31 Mar 22

2, 9, 18, 23 and 30 Mar 22

4, 11, 15 and 25 Mar 22

3, 10, 16, 24 and 31 Mar 22

7, 17, 21 and 28 Mar 22

3, 10, 17, 24 and 31 Mar 22

4, 11, 14 and 25 Mar 22

Joint Site Audit with representative of the Supervisor¡¦s Representative, the Contractor and IEC

16 Mar 22

18 Mar 22

15 Mar 22

16 Mar 22

17 Mar 22

10 Mar 22

14 Mar 22

 

10.2       During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarised in Table 10.2.


 

 

Table 10.2       Observations and Recommendations during Site Audits

 

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

 

Waste/ Chemical Management

01/03/2022

Construction waste shall be disposed of regularly.

Improvement/Rectification was observed during follow-up audit session on 8 March 2022.

Air Quality

16/03/2022

Access road should be kept clean and free from dust.

Improvement/Rectification was observed during follow-up audit session on 22 March 2022.

Contract No.: ND/2019/02

Water Quality

23/02/2022

To enhance water mitigation measure to prevent surface runoff to pavement.

Improvement/Rectification was observed during follow-up audit session on 2 March 2022.

Waste/ Chemical Management

23/02/2022

Drip tray should be provided for chemical storage.

Improvement/Rectification was observed during follow-up audit session on 2 March 2022.

Air Quality

02/03/2022

Dusty haul road should be sprayed with water regularly.

Improvement/Rectification was observed during follow-up audit session on 9 March 2022.

Landscape and Visual

02/03/2022

To erect 2m dull green barrier fences around active work area. (3 locations shown in the photo)

Item was remarked as 220309- R01.

09/03/2022

To erect 2m dull green barrier fences around active work area. (3 locations shown in the photo)

Item was remarked as 220318- R01.

18/03/2022

To erect 2m dull green barrier fences around active work area. (3 locations shown in the photo)

Improvement/Rectification was observed during follow-up audit session on 23 March 2022.

Water Quality

23/03/2022

Enhance water mitigation measures to prevent muddy stagnant water runoff.

Improvement/Rectification was observed during follow-up audit session on 30 March 2022.

30/03/2022

Remove the stagnant water inside U-channel.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/03

Water Quality

25/02/2022

To enhance water mitigation measures around water stream near ¥¨»«, exposed slope of the stream should be covered to prevent further debris from entering the irrigation water channels.

Item was remarked as 220304- O01.

25/02/2022

Wheel-washing Bay should be cleared and cleaned regularly.

Item was remarked as 220304- R01.

04/03/2022

To enhance water mitigation measures around water stream near ¥¨»«, exposed slope of the stream should be covered to prevent further debris from entering the irrigation water channels.

Improvement/Rectification was observed during follow-up audit session on 11 March 2022.

04/03/2022

Wheel-washing Bay should be cleared and cleaned regularly.

Improvement/Rectification was observed during follow-up audit session on 11 March 2022.

Contract No.: ND/2019/04

Water Quality

23/02/2022

Direct the muddy stagnant water to de-silting facility before discharge to drainage and U-channel. (Portion B)

Item was remarked as 220303- O01.

03/03/2022

Direct the muddy stagnant water to de-silting facility before discharge to drainage and U-channel. (Portion B)

Item was remarked as 220310- O01.

03/03/2022

Dusty stockpile should be covered by impervious sheeting.

Improvement/Rectification was observed during follow-up audit session on 10 March 2022.

03/03/2022

To enhance the drainage system and the capacity of de-silting facility to prevent surface runoff.

Item was remarked as 220310- R02.

10/03/2022

Direct the muddy stagnant water to de-silting facility before discharge to drainage and U-channel. (Portion B)

Improvement/Rectification was observed during follow-up audit session on 16 March 2022.

10/03/2022

To enhance the drainage system and the capacity of de-silting facility to prevent surface runoff.

Item was remarked as 220316- R01.

16/03/2022

To enhance the drainage system and the capacity of de-silting facility to prevent surface runoff.

Item was remarked as 220324- R01.

24/03/2022

To enhance the drainage system and the capacity of de-silting facility to prevent surface runoff.

Item was remarked as 220331- R01.

24/03/2022

To clear the U-channel regularly.

Improvement/Rectification was observed during follow-up audit session on 31 March 2022.

31/03/2022

To enhance the drainage system and the capacity of de-silting facility to prevent surface runoff.

Follow-up action is needed to be reported in the following month.

Waste/ Chemical Management

16/03/2022

To clear the oil stain on the ground.

Improvement/Rectification was observed during follow-up audit session on 24 March 2022.

Ecology

31/03/2022

Silt curtain was observed oversized and bulky. Please rectify to make sure the silt curtain function properly.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/05

Air Quality

28/02/2022

Dusty worksite shall be watered regularly.

Improvement/Rectification was observed during follow-up audit session on 7 March 2022.

07/03/2022

NRMM label shall be displayed on regulated machine.

Improvement/Rectification was observed during follow-up audit session on 17 March 2022.

17/03/2022

Dusty worksite shall be watered regularly.

Improvement/Rectification was observed during follow-up audit session on 21 March 2022.

21/03/2022

Dusty stockpile shall be covered properly by impervious sheeting.

Improvement/Rectification was observed during follow-up audit session on 28 March 2022.

28/03/2022

Site entrance should be kept clean and free from dust.

Follow-up action is needed to be reported in the following month.

Water Quality

28/02/2022

To enhance water mitigation measure to prevent surface runoff.

Improvement/Rectification was observed during follow-up audit session on 7 March 2022.

21/03/2022

Replace broken sandbags to prevent surface runoff.

Improvement/Rectification was observed during follow-up audit session on 28 March 2022.

Waste/ Chemical Management

07/03/2022

Drip tray shall be provided for chemical storage.

Improvement/Rectification was observed during follow-up audit session on 17 March 2022.

17/03/2022

General refuse shall be disposed of regularly.

Improvement/Rectification was observed during follow-up audit session on 21 March 2022.

Contract No.: ND/2019/06

Waste/ Chemical Management

03/03/2022

Drip tray should be provided for chemical storage.

Item was remarked as 220310- R01.

10/03/2022

Drip tray should be provided for chemical storage.

Improvement/Rectification was observed during follow-up audit session on 17 March 2022.

Contract No.: ND/2019/07

 

--

--

--

--

 

 

Implementation Status of Environmental Mitigation Measures

10.3       According to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix Q. The photographic records of measures as stipulated in EP to mitigate environmental impacts in the reporting month are presented in Table 10.3.

Table 10.3   Photographic Records and Implementation Status of Measures

EP No.

Condition

Photographic Record

Implementation Status

EP-466/2013

2.9

To minimise adverse impacts on habitats of ecological imprtance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

EP-468/2013/A

2.11

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

EP-469/2013

2.7

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

EP-473/2013/A

2.13

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

EP-475/2013/A

2.7

 

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

Implementation status:

^         Mitigation measure was fully implemented

*         Observation/reminder was made during site audit but improved/rectified by the contractor

#         Observation/reminder was made during site audit but not yet improved/ rectified by the            contractor

X        Non-compliance of mitigation measure

¡P         Non-compliance but rectified by the contractor

N/A   Not Applicable at this stage as no such site activities were conducted in the reporting     period

[1]:       Barrier fences might be subjected to change according to phasing plan designed at detailed design stage

 

10.4       Under EP-467/2013/A (Condition 2.9), to minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas. As the Works programme under above EPs were still under preparation work and the barrier fences erection was still progressing in the Reporting Month, 2m high solid dull green site barrier fences will be checked once in place. The Hoarding Plan of the above EPs refer to EP submission.

Implementation Status of Air Quality and Noise Mitigation Measures

10.5       According to the EIA Report and the Updated EM&A Manual, the Air quality and Noise mitigation measures detailed in the documents are recommended to be implemented during the construction phase. Air quality and Noise mitigation measures implemented by the contractors were closely monitored to prevent water pollution, especially during dry season. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix Q. Specific Air quality and Noise mitigation measures for major construction works in the reporting month are presented in Table 10.4.

 


 

Table 10.4    Specific Air Quality and Noise Mitigation Measures for Major Construction Works in the Reporting Month

Works Contracts

Photographic Records

ND/2019/01

Hard paved exposed slope surface

Access road watered regularly

ND/2019/02

Hard paved exposed haul road

Hard paved exposed slope surface

ND/2019/03

Deployment of noise barriers between construction site and NSRs

Vehicle washing facilities at exit point

ND/2019/04

Haul road watered regularly

Regulated machines display with Non-road Mobile Machinery labels

ND/2019/05

Covering dusty stockpile

Access road watered regularly

ND/2019/06

Regulated machines display with  Non-road Mobile Machinery labels

Hard paved exposed haul road

ND/2019/07

Covering exposed slope surface with tarpaulin

Access road watered regularly

Solid and Liquid Waste Management Status

10.6       Waste generated from Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and ND/2019/07 include inert construction and demolition (C&D) materials and non-inert C&D wastes in the Reporting Month.

10.7       The amount of wastes generated by the construction works of the Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and ND/2019/07 during the reporting month are shown in Appendix R.

10.8       The Contractors are advised to minimize the wastes generated through recycling or reusing. All mitigation measures stipulated in the Updated EM&A Manual and waste management plans shall be fully implemented. The status of implementation of waste management and reduction measures are summited in Appendix Q.


 

Ecological Mitigation Measures ¡V Creation of Long Valley Nature Park (LVNP)

10.9       From the findings of EIA Report, the area of Long Valley has been assessed as of high to very high ecological value and is the largest contiguous area of freshwater wetland habitats in Hong Kong. To safeguard the ecological value of Long Valley, about 37 hectares of land in Long Valley has been proposed to develop into Long Valley Nature Park (LVNP) for conserving and enhancing the ecologically important environment as well as for compensation of the wetland loss due to the NDA development.

10.10    LVNP is developed according to approved Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. The HCMP provides a framework and specifications for development and management of the LVNP and guides the development to maintain and enhance the 37ha of low-lying wetland habitats.

10.11   Regarding to the design, the zoning of land use in the LVNP is intended to maintain the existing mosaic pattern of wet and dry agriculture, while controlling the activities that could potentially disturb target habitats and species. The LVNP will divide into three broad zones of land use as below:

       Biodiversity Zone of about 21 hectares largely designated for biodiversity conservation through cultivation of specified crops and habitat management.

       Agricultural Zone of about 11 hectares designated for commercially focuses crop production and eco-friendly agricultural practice for farming.

       Visitor Zone of about 5 hectares designed to accommodate visitors as well as storage and other facilities and for educational purposes.

10.12   The construction of the LVNP started in late 2019 and is expected to be completed in 2023. During construction period, the progress of construction and wetland enhancement works are under observation by different stakeholders including AFCD and green groups. Close communication between AFCD and CEDD are conducted to exchange views on conservation, restoration and management of habitats as well as on the planning and design of the park. Also, advices from green groups, Hong Kong Bird Watching Society (HKBWS) and The Conservancy Association (CA), are taken on habitat management of Long Valley and potential effects on habitat and wildlife of each individual work conducted in Long Valley. Regular meeting are held monthly to share the progress of LVNP with different stakeholders, including CEDD, AFCD, CA, HKBWS, Contractor, ET, IEC and farmers. However, meeting in March was canceled due to pandemic outbreak.

10.13   Proposals on wetland creation and restoration, dry agricultural land creation, pond creation, water treatment wetland and design of irrigation channel are submitted by the Contractor to achieve the objectives stated in HCMP and accepted by the Engineer with consent from AFCD before implementation. The Contractor will consult with the stakeholders for recommendations and suggestions on mitigation measures to minimise the environmental impacts arising from construction works. The progress of works will be arranged to minimise impacts to avifauna and maintain the habitat for avifauna. The photographic records of site activities in LVNP are presented in Table 10.5.

 


 

Table 10.5       Photographic Records of Site Activities in LVNP

Agricultural practice are continued in existing farmland to maintain habitats in Long Valley

 Open water Habitat      

Open water Habitat      

Chinese arrowhead pond

Creation of wetland with designated habitat for biodiversity conservation

Planting of paddy rice to provide foraging ground for Yellow-breasted Bunting

Retention of washing bay for amphibians breeding

Enhancement of irrigation channel to provide reliable water source for farmland in Long Valley

Provision of bird island (hidden area)

Restoring of water flea pond to provide food source to water birds

Construction of storage sheds for farmers

WhatsApp Image 2022-04-11 at 10.21.54 AM

A Calidris ferruginea was recorded

Wet agricultural land

Provision of noise barrier for noisy works in Long Valley