10.1
Site
audits were carried out by ET on weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures on the Contract site. The
summaries of site audits are presented in Table 10.1 and Appendix P.
Table 10.1 Summary
of Site Audit
Environmental
Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly
site audit with representative of the Supervisor¡¦s Representative and the
Contractor |
1, 8, 16, 22 and 31
Mar 22 |
2, 9, 18, 23 and 30
Mar 22 |
4, 11, 15 and 25 Mar
22 |
3, 10, 16, 24 and 31
Mar 22 |
7, 17, 21 and 28 Mar
22 |
3, 10, 17, 24 and 31
Mar 22 |
4, 11, 14 and 25 Mar
22 |
Joint
Site Audit with representative of the Supervisor¡¦s Representative, the
Contractor and IEC |
16 Mar 22 |
18 Mar
22 |
15 Mar
22 |
16 Mar 22 |
17 Mar 22 |
10 Mar 22 |
14 Mar 22 |
10.2
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarised in Table
10.2.
Table 10.2
Observations and Recommendations during Site Audits
|
Date |
Observations and Recommendations |
Follow-up |
Contract No.: ND/2019/01 |
|||
Waste/ Chemical Management |
01/03/2022 |
Construction waste shall be disposed of regularly. |
Improvement/Rectification
was observed during follow-up audit session on 8 March 2022. |
Air Quality |
16/03/2022 |
Access road should be kept clean and free from dust. |
Improvement/Rectification
was observed during follow-up audit session on 22 March 2022. |
Contract No.: ND/2019/02 |
|||
Water Quality |
23/02/2022 |
To enhance water mitigation measure to prevent
surface runoff to pavement. |
Improvement/Rectification was observed during
follow-up audit session on 2 March 2022. |
Waste/ Chemical Management |
23/02/2022 |
Drip tray should be provided for chemical
storage. |
Improvement/Rectification was observed during
follow-up audit session on 2 March 2022. |
Air Quality |
02/03/2022 |
Dusty haul road should be sprayed with water
regularly. |
Improvement/Rectification was observed during
follow-up audit session on 9 March 2022. |
Landscape and Visual |
02/03/2022 |
To erect 2m dull green barrier fences around
active work area. (3 locations shown in the photo) |
Item was remarked as 220309- R01. |
09/03/2022 |
To erect 2m dull green barrier fences around
active work area. (3 locations shown in the photo) |
Item was remarked as 220318- R01. |
|
18/03/2022 |
To erect 2m dull green barrier fences around
active work area. (3 locations shown in the photo) |
Improvement/Rectification was observed during
follow-up audit session on 23 March 2022. |
|
Water Quality |
23/03/2022 |
Enhance water mitigation measures to prevent muddy
stagnant water runoff. |
Improvement/Rectification was observed during
follow-up audit session on 30 March 2022. |
30/03/2022 |
Remove the stagnant water inside U-channel. |
Follow-up action is needed to be reported in the
following month. |
|
Contract No.: ND/2019/03 |
|||
Water Quality |
25/02/2022 |
To enhance water
mitigation measures around water stream near ¥¨»«, exposed slope of the stream should be covered to prevent further
debris from entering the irrigation water channels. |
Item was remarked as 220304- O01. |
25/02/2022 |
Wheel-washing Bay should
be cleared and cleaned regularly. |
Item was remarked as 220304- R01. |
|
04/03/2022 |
To enhance water
mitigation measures around water stream near ¥¨»«, exposed slope of the stream should be covered to prevent further
debris from entering the irrigation water channels. |
Improvement/Rectification was observed during
follow-up audit session on 11 March 2022. |
|
04/03/2022 |
Wheel-washing Bay should
be cleared and cleaned regularly. |
Improvement/Rectification was observed during follow-up
audit session on 11 March 2022. |
|
Contract No.: ND/2019/04 |
|||
Water Quality |
23/02/2022 |
Direct the muddy stagnant
water to de-silting facility before discharge to drainage and U-channel.
(Portion B) |
Item was remarked as 220303- O01. |
03/03/2022 |
Direct the muddy stagnant
water to de-silting facility before discharge to drainage and U-channel.
(Portion B) |
Item was remarked as 220310- O01. |
|
03/03/2022 |
Dusty stockpile should be
covered by impervious sheeting. |
Improvement/Rectification was observed during
follow-up audit session on 10 March 2022. |
|
03/03/2022 |
To enhance the drainage
system and the capacity of de-silting facility to prevent surface runoff. |
Item was remarked as 220310- R02. |
|
10/03/2022 |
Direct the muddy stagnant
water to de-silting facility before discharge to drainage and U-channel.
(Portion B) |
Improvement/Rectification was observed during
follow-up audit session on 16 March 2022. |
|
10/03/2022 |
To enhance the drainage
system and the capacity of de-silting facility to prevent surface runoff. |
Item was remarked as 220316- R01. |
|
16/03/2022 |
To enhance the drainage
system and the capacity of de-silting facility to prevent surface runoff. |
Item was remarked as 220324- R01. |
|
24/03/2022 |
To enhance the drainage
system and the capacity of de-silting facility to prevent surface runoff. |
Item was remarked as 220331- R01. |
|
24/03/2022 |
To clear the U-channel
regularly. |
Improvement/Rectification was observed during
follow-up audit session on 31 March 2022. |
|
31/03/2022 |
To enhance the drainage system
and the capacity of de-silting facility to prevent surface runoff. |
Follow-up action is needed to be reported in the
following month. |
|
Waste/ Chemical Management |
16/03/2022 |
To clear the oil stain on
the ground. |
Improvement/Rectification was observed during
follow-up audit session on 24 March 2022. |
Ecology |
31/03/2022 |
Silt curtain was observed
oversized and bulky. Please rectify to make sure the silt curtain function
properly. |
Follow-up action is needed to be reported in the
following month. |
Contract No.: ND/2019/05 |
|||
Air Quality |
28/02/2022 |
Dusty worksite shall be
watered regularly. |
Improvement/Rectification was observed during
follow-up audit session on 7 March 2022. |
07/03/2022 |
NRMM label shall be
displayed on regulated machine. |
Improvement/Rectification was observed during
follow-up audit session on 17 March 2022. |
|
17/03/2022 |
Dusty worksite shall be
watered regularly. |
Improvement/Rectification was observed during
follow-up audit session on 21 March 2022. |
|
21/03/2022 |
Dusty stockpile shall be
covered properly by impervious sheeting. |
Improvement/Rectification was observed during
follow-up audit session on 28 March 2022. |
|
28/03/2022 |
Site entrance should be
kept clean and free from dust. |
Follow-up action is needed to be reported in the
following month. |
|
Water Quality |
28/02/2022 |
To enhance water
mitigation measure to prevent surface runoff. |
Improvement/Rectification was observed during
follow-up audit session on 7 March 2022. |
21/03/2022 |
Replace broken sandbags to
prevent surface runoff. |
Improvement/Rectification was observed during
follow-up audit session on 28 March 2022. |
|
Waste/ Chemical Management |
07/03/2022 |
Drip tray shall be
provided for chemical storage. |
Improvement/Rectification was observed during
follow-up audit session on 17 March 2022. |
17/03/2022 |
General refuse shall be
disposed of regularly. |
Improvement/Rectification was observed during
follow-up audit session on 21 March 2022. |
|
Contract No.: ND/2019/06 |
|||
Waste/ Chemical Management |
03/03/2022 |
Drip tray should be provided for chemical
storage. |
Item
was remarked as 220310- R01. |
10/03/2022 |
Drip tray should be provided for chemical
storage. |
Improvement/Rectification
was observed during follow-up audit session on 17 March 2022. |
|
Contract No.: ND/2019/07 |
|||
-- |
-- |
-- |
-- |
10.3
According
to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
Q. The photographic records of measures as stipulated in EP to mitigate
environmental impacts in the reporting month are presented in Table 10.3.
Table 10.3 Photographic Records and
Implementation Status of Measures
EP No. |
Condition |
Photographic Record |
Implementation Status |
EP-466/2013 |
2.9 |
To
minimise adverse impacts on habitats of ecological imprtance in the vicinity of the Project, 2m high solid
dull green site barrier fences shall be erected around all active works
areas. |
^[1] |
EP-468/2013/A |
2.11 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-469/2013 |
2.7 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-473/2013/A |
2.13 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site barrier
fences shall be erected around all active works areas. |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance
of mitigation measure ¡P Non-compliance
but rectified by the contractor N/A Not Applicable at this stage as no such
site activities were conducted in the reporting period |
[1]: Barrier
fences might be subjected to change according to phasing plan designed at
detailed design stage
10.4
Under
EP-467/2013/A (Condition 2.9), to minimise adverse impacts
on habitats of ecological importance in the vicinity of the Project, 2m high
solid dull green site barrier fences shall be erected around all active works
areas. As the Works programme under above EPs were
still under preparation work and the barrier
fences erection was still progressing in the Reporting Month, 2m high solid
dull green site barrier fences will be checked once in place. The Hoarding Plan
of the above EPs refer to EP submission.
10.5
According
to the EIA Report and the Updated EM&A Manual, the Air quality and Noise
mitigation measures detailed in the documents are recommended to be implemented
during the construction phase. Air quality and Noise mitigation measures
implemented by the contractors were closely monitored to prevent water
pollution, especially during dry season. An updated summary of the
Environmental Mitigation Implementation Schedule is provided in Appendix Q. Specific Air quality and
Noise mitigation measures for major construction works in the reporting month
are presented in Table 10.4.
Table 10.4 Specific
Air Quality and Noise Mitigation Measures for Major Construction Works in the
Reporting Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Access road watered
regularly |
ND/2019/02 |
Hard paved exposed
haul road |
Hard paved exposed slope surface |
ND/2019/03 |
Deployment of noise
barriers between construction site and NSRs |
Vehicle washing facilities at exit point |
ND/2019/04 |
Haul road watered regularly |
Regulated machines display with Non-road
Mobile Machinery labels |
ND/2019/05 |
Covering dusty
stockpile |
Access road watered regularly |
ND/2019/06 |
Regulated machines display with Non-road Mobile Machinery labels |
Hard paved exposed haul road |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
Access road watered regularly |
10.6
Waste generated from
Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05,
ND/2019/06 and ND/2019/07 include inert construction and demolition (C&D)
materials and non-inert C&D wastes in the Reporting Month.
10.7
The amount of wastes generated by
the construction works of the Contract No.
ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and
ND/2019/07 during the reporting month are shown in Appendix R.
10.8
The
Contractors are advised to minimize the wastes generated through recycling or reusing.
All mitigation measures stipulated in the Updated EM&A Manual and waste
management plans shall be fully implemented. The status of implementation of
waste management and reduction measures are summited in Appendix Q.
10.9
From
the findings of EIA Report, the area of Long Valley has been assessed as of
high to very high ecological value and is the largest contiguous area of
freshwater wetland habitats in Hong Kong. To safeguard the ecological value of
Long Valley, about 37 hectares of land in Long Valley has been proposed to
develop into Long Valley Nature Park (LVNP) for conserving and enhancing the
ecologically important environment as well as for compensation of the wetland loss
due to the NDA development.
10.10
LVNP is developed according to approved
Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. The
HCMP provides a framework and specifications for development and management of
the LVNP and guides the development to maintain and enhance the 37ha of
low-lying wetland habitats.
10.11
Regarding
to the design, the zoning of land use in the LVNP is intended to maintain the
existing mosaic pattern of wet and dry agriculture, while controlling the activities
that could potentially disturb target habitats and species. The LVNP will
divide into three broad zones of land use as below:
•
Biodiversity
Zone of about 21 hectares largely designated for biodiversity conservation
through cultivation of specified crops and habitat management.
•
Agricultural
Zone of about 11 hectares designated for commercially focuses crop production
and eco-friendly agricultural practice for farming.
•
Visitor
Zone of about 5 hectares designed to accommodate visitors as well as storage
and other facilities and for educational purposes.
10.12
The
construction of the LVNP started in late 2019 and is expected to be completed
in 2023. During construction period, the progress of construction and wetland
enhancement works are under observation by different stakeholders including
AFCD and green groups. Close communication between AFCD and CEDD are conducted
to exchange views on conservation, restoration and management of habitats as
well as on the planning and design of the park. Also, advices from green
groups, Hong Kong Bird Watching Society (HKBWS) and The Conservancy Association
(CA), are taken on habitat management of Long Valley and potential effects on
habitat and wildlife of each individual work conducted in Long Valley. Regular
meeting are held monthly to share the progress of LVNP with different
stakeholders, including CEDD, AFCD, CA, HKBWS, Contractor, ET, IEC and farmers.
However, meeting in March was canceled due to pandemic outbreak.
10.13
Proposals
on wetland creation and restoration, dry agricultural land creation, pond
creation, water treatment wetland and design of irrigation channel are
submitted by the Contractor to achieve the objectives stated in HCMP and
accepted by the Engineer with consent from AFCD before implementation. The Contractor
will consult with the stakeholders for recommendations and suggestions on
mitigation measures to minimise the environmental
impacts arising from construction works. The progress of works will be arranged
to minimise impacts to avifauna and maintain the
habitat for avifauna. The photographic records of site activities in LVNP are
presented in Table 10.5.
Table 10.5 Photographic Records of Site Activities in LVNP
Agricultural practice are continued in
existing farmland to maintain habitats in Long Valley |
|||
Open water Habitat |
Open
water Habitat |
Chinese
arrowhead pond |
|
Creation of wetland with designated
habitat for biodiversity conservation |
|||
Planting of paddy rice to provide
foraging ground for Yellow-breasted Bunting |
|||
Retention of washing bay for amphibians
breeding |
Enhancement of irrigation channel
to provide reliable water source for farmland in Long Valley |
||
Provision of bird island (hidden area) |
Restoring of water flea pond to provide food
source to water birds |
||
Construction of storage sheds for farmers |
A Calidris ferruginea was
recorded |
||
Wet agricultural land |
Provision of noise barrier for noisy
works in Long Valley |
||