Table IV       Summary Table for Site Activities in the coming Two Months

Contract No.

Site Activities (April 2022 and May 2022)

ND/2019/01

 

(a)           Site Clearance, remove of existing structures and tree felling in Portion 1a

(b)           Site clearance, ground investigation, sheet piling, excavation and drainage in Portion 1b

(c)           Site Clearance and tree felling in Portion 1e

(d)          Site clearance, tree felling, temporary road construction and site formation work in Portion 2

(e)           Site clearance, backfilling, excavation and tree felling in Portion 3

(f)            Site clearance, sheet piling and excavation, drainage works and temporary road construction in Portion 5

(g)           Site Clearance, sheet piling and excavation, pipes laying, backfilling, construction of KB01 retaining wall, haul road construction in Portion 6a

(h)           Operation of HAC treatment facility in Portion 6b

(i)            Site clearance, sheetpiling and excavation, pipes laying in Portion 7

(j)            Construction of retaining Wall, slope cutting, slope drainage and maintenance access construction, RC construction of flushing water service reservoir and fresh water reservoir in Portion 8a

(k)           Sheet piling for receiving pit, trenchless works, excavation in Portion 8b

(l)            Sheet piling and excavation, pipes laying, demolition of existing structures, GI works in Portion 9b

(m)         Stockpile of soil and excavation in Portion 9c

(n)           Excavation, sheetpiling for ELS, drainage works, road construction and utilities laying in Portion 10a

(o)           Sheetpiling and excavation, drainage works in Portion 10b

(p)           Construction of MBR at 11b

(q)           Construction of temporary sewage pumping station in Portion 14

ND/2019/02

(a)           Pipe Jacking

(b)           ELS

(c)           Concreting

(d)          Backfilling

(e)           Sheet Pile Installation

(f)            Bedding and Pipe Laying

(g)           Cut and Fill of Slope

(h)           Manhole Construction

(i)            Open cut

(j)            Preparation works

ND/2019/03

 

(a)         Portion 1 & Portion 1A

-            Drainage works at Yin Kong Road

-            Construction of Pai Lau

(b)         Long Valley

-          Erection of Permanent Boundary Structure

-          Construction of Compacted Earth Path / Walkway

-          Construction of Ditches

-          Construction of Irrigation Channel

-          Construction of Decking & Sluices

-          Construction of Wetland Boardwalk

-          Construction of Type 1 Storage House

-          Construction of Type 2 Storage House

-          Construction of Tea House

-          Construction of Composting Facility

-          Construction of Bird Hide

-          Construction of Outdoor Classroom

-          Construction of Storage Sheds

-          Wetland Creation & Restoration works

ND/2019/04

 

(a)           Tree felling

(b)          Predrill

(c)           Bored piling

(d)          Excavation

(e)           Sheet piling

(f)           ELS

ND/2019/05

(a)            North Team Works

-          Pre-drilling for bored piles at B1 & B2(Portion II), C1(Portion II)

-          Bored piling at B1(Portion I), B1&B2(Portion II), C1(Portion II), C1-03, C2-02, C2-03a, C2-03b, C3-02, C3-04a, D2-01 & E2-01.

-          ELS and Pile cap construction at C1-04, C3-04b, D1-01, D1-02, D1-03, D1-04, E1-01, E1-02, E1-03 & E1-04

-          C4-01 Portal Beam

-          Bailey bridge construction

-          Piling platform & haul road construction from B2-03 to C1-02a at Portion II

-          Footing construction at C4-02

-          Pier construction at C3-03b, C4-03, C4-04aM, D1-01, E1-01, E1-02, E1-03 & E1-04

(b)            Viaduct Works

-          1st SOP is targeted to cast by the middle of Mar 2022.

-          Target to cast in 36 segments in Mar 2022 and 42 segments in Apr 2022.

-          LG component (main winch trolley) testing resumed after heavy snow and completed in February 2022.All testing to be completed and disassemble for minor adjustment will be carried out.

-          Remaining components of E2-02 Form Traveller (FT) design was endorsed by ICE and submitted via CSF on 4 Mar 2022.

-          Main truss of E3-03 FT design was endorsed by ICE and submitted via CSF on 4 Mar 2022.

-          External PT design for Bridge C3, C4, E2 and E3 was in progress.

-          Rotation Bridge Design for E2-01 and D2-01 was in progress.

(c)            South Team Works

-          Venton Area ¡V Gas main laying.

-          Portion 13 ¡V Twin DN1200 storm drain construction. Backfill FW 52 bay 1 and bay 2.

-          Portion 17 and 18 ¡V Construction of DN 600 and DN450 sewer. RW 52 bay 6

-          Portion 18 ¡V Gas main laying

-          TWSR (West) ¡V RW06 construction and FS04 slope works.

-          HKY FB (East) ¡V construction of LT1, P02

-          Portion 11 ¡V DN1200 and DN600 watermain laying work.

-          E2-02 pier ¡V Construction of tower crane foundation. Construction of SOP

-          E2-03 ¡V Pile cap construction.

-          E3-01 ¡V Pile cap construction.

-          E3-03 ¡V Pier Head and SOP construction

-          D2-02 ¡V Pile cap construction.

-          D2-03 ¡V Piling works.

-          E3-04a ¡V predrilling and piling works.

ND/2019/06

 

(a)           Finishing works for the additional water tank and pump house at Portion 3.

(b)           Installation of handrails at MOB at Portion 4.

(c)           Joint sealant application for carriageway at Portion 3.

(d)          Grating installation at Portion 3.

(e)           Installation of signage of the market at Portion 3.

(f)            Installation of the main gate.

ND/2019/07

(a)        Site clearance at Portion 4

(b)       Erection of site hoarding at Portion 4

(c)        C&D waste disposal at Portion 1, 2, 4 and 5

(d)       G.I. works at Portion 4

(e)        Construction of box culvert at Portion 2

(f)        Filling works at Portion 1, 2 and 4

(g)        Tree felling/ Disposal of yard waste at Portion 4

(h)       Construction of site haul road at Portion 4

(i)         Drainage works and sewage works at Portion 1, 3 and 4

(j)         Mini piling works at Portion 4 and 5

(k)       Construction of noise barrier at Portion 5