Table IV Summary Table for Site Activities in the coming Two
Months
Contract
No. |
Site
Activities (April 2022 and May 2022) |
ND/2019/01 |
(a)
Site Clearance, remove of
existing structures and tree felling in Portion 1a (b)
Site clearance, ground
investigation, sheet piling, excavation and drainage in Portion 1b (c)
Site Clearance and tree
felling in Portion 1e (d)
Site clearance, tree
felling, temporary road construction and site formation work in Portion 2 (e)
Site clearance, backfilling,
excavation and tree felling in
Portion 3 (f)
Site clearance, sheet
piling and excavation, drainage works and temporary road construction in Portion 5 (g)
Site
Clearance, sheet piling and excavation, pipes laying, backfilling,
construction of KB01 retaining wall, haul road construction in Portion 6a (h)
Operation
of HAC treatment facility in Portion 6b (i)
Site
clearance, sheetpiling and excavation, pipes laying in Portion 7 (j)
Construction
of retaining Wall, slope cutting, slope drainage and maintenance access
construction, RC construction of flushing water service reservoir and fresh
water reservoir in Portion 8a (k)
Sheet
piling for receiving pit, trenchless works, excavation in Portion 8b (l)
Sheet piling and excavation, pipes laying,
demolition of existing structures, GI works in Portion 9b (m)
Stockpile
of soil and excavation in Portion 9c (n)
Excavation,
sheetpiling for ELS, drainage works, road construction and utilities laying in
Portion 10a (o)
Sheetpiling
and excavation, drainage works in Portion 10b (p)
Construction of MBR at 11b (q)
Construction of temporary sewage pumping station in Portion 14 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
ELS (c)
Concreting (d)
Backfilling (e)
Sheet
Pile Installation (f)
Bedding
and Pipe Laying (g)
Cut and
Fill of Slope (h)
Manhole Construction (i)
Open cut (j)
Preparation works |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b)
Long
Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Path / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Tree
felling (b)
Predrill (c)
Bored
piling (d)
Excavation
(e)
Sheet
piling (f)
ELS |
ND/2019/05 |
(a)
North Team Works -
Pre-drilling for bored piles at B1 &
B2(Portion II), C1(Portion II) -
Bored piling at B1(Portion I), B1&B2(Portion
II), C1(Portion II), C1-03, C2-02, C2-03a, C2-03b, C3-02, C3-04a, D2-01 &
E2-01. -
ELS and Pile cap construction at C1-04, C3-04b,
D1-01, D1-02, D1-03, D1-04, E1-01, E1-02, E1-03 & E1-04 -
C4-01 Portal Beam -
Bailey bridge construction -
Piling platform & haul road construction from
B2-03 to C1-02a at Portion II -
Footing construction at C4-02 -
Pier construction at C3-03b, C4-03, C4-04aM,
D1-01, E1-01, E1-02, E1-03 & E1-04 (b)
Viaduct Works -
1st SOP is targeted to cast by the middle of Mar
2022. -
Target to cast in 36 segments in Mar 2022 and 42
segments in Apr 2022. -
LG component (main winch trolley) testing resumed
after heavy snow and completed in February 2022.All testing to be completed
and disassemble for minor adjustment will be carried out. -
Remaining components of E2-02 Form Traveller (FT)
design was endorsed by ICE and submitted via CSF on 4 Mar 2022. -
Main truss of E3-03 FT design was endorsed by ICE
and submitted via CSF on 4 Mar 2022. -
External PT design for Bridge C3, C4, E2 and E3
was in progress. -
Rotation Bridge Design for E2-01 and D2-01 was in
progress. (c)
South Team Works -
Venton Area ¡V Gas main laying. -
Portion 13 ¡V Twin DN1200 storm drain
construction. Backfill FW 52 bay 1 and bay 2. -
Portion 17 and 18 ¡V Construction of DN 600 and
DN450 sewer. RW 52 bay 6 -
Portion 18 ¡V Gas main laying -
TWSR (West) ¡V RW06 construction and FS04 slope
works. -
HKY FB (East) ¡V construction of LT1, P02 -
Portion 11 ¡V DN1200 and DN600 watermain laying
work. -
E2-02 pier ¡V Construction of tower crane
foundation. Construction of SOP -
E2-03 ¡V Pile cap construction. -
E3-01 ¡V Pile cap construction. -
E3-03 ¡V Pier Head and SOP construction -
D2-02 ¡V Pile cap construction. -
D2-03 ¡V Piling works. -
E3-04a ¡V predrilling and piling works. |
ND/2019/06 |
(a)
Finishing works for the
additional water tank and pump house at Portion 3. (b)
Installation of handrails
at MOB at Portion 4. (c)
Joint sealant application
for carriageway at Portion 3. (d)
Grating installation at
Portion 3. (e)
Installation of signage of
the market at Portion 3. (f)
Installation of the main
gate. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding
at Portion 4 (c)
C&D waste disposal at
Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 (e)
Construction of box culvert
at Portion 2 (f)
Filling works at Portion 1,
2 and 4 (g)
Tree felling/ Disposal of
yard waste at Portion 4 (h)
Construction of site haul
road at Portion 4 (i)
Drainage works and sewage
works at Portion 1, 3 and 4 (j)
Mini piling works at
Portion 4 and 5 (k)
Construction of noise
barrier at Portion 5 |