Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (March 2022) |
ND/2019/01 |
(a)
Site clearance, tree
felling, demolition of existing structures and site formation works in
Portion 1a (b)
Site clearance, sheet piling,
excavation, drainage and demolition of existing structures in Portion 1b (c)
Site clearance, demolition
of existing structures in Portion 1e (d)
Site clearance, tree
felling, temporary road construction and site formation works in Portion 2 (e)
Site clearance, excavation,
backfilling in Portion 3 (f)
Site clearance, sheet
piling, excavation, drainage works, watermain,
backfill in
Portion 5 (g)
Site
clearance, drainage works, backfill and retaining wall KB01 construction in
Portion 6a (h)
Operation
of HAC soil treatment facility in Portion 6b (i)
Site clearance, sheet
piling and excavation, drainage works and site formation works in Portion 7 (j)
Construction of retaining
wall, slope cutting, slope drainage and maintenance access construction, RC
construction of flushing water service reservoir and fresh water service
reservoir in Portion 8a (k)
Site clearance, excavation
for jacking pit, sheet piling for receiving pit in Portion 8b (l)
Sheet piling and
excavation, drainage works in Portion 9b (m)
Stockpile of soil and
excavation in Portion 9c (n)
Excavation, sheet piling
for ELS, drainage works and road work, utilities works in Portion 10a (o)
Sheet piling
and excavation in Portion 10b (p)
Construction of MBR in Portion 11b (q)
Construction of temporary sewage pumping station in Portion 14 (r)
Construction of CLC in Portion 16 |
ND/2019/02 |
(a)
Sheet
Pile Installation (b)
Concreting (c)
Sheet Pile Installation (d)
ELS (e)
Open cut (f)
Preparation
works |
ND/2019/03 |
(a) Portion 1 & Portion
1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b) Long
Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Bund / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Site
clearance (b)
Tree
felling (c)
Predrill (d)
Bored
piling (e)
Excavation (f)
Sheet
piling and ELS |
ND/2019/05 |
(a)
The pre-drilling will start at the B2 bridge in Portion III. (b)
The rotary drilling rigs, one is located at B1.
The second is located at C1-01b. The third one is located at C2-03. The
fourth one rig is located at C3-02, C3-03a and C2-04a. The RCD rig is located
at E2-01 and another RCD rig located at D2-03. C2-04a. (c)
C4-01 Portal Beam support system, C4-03 cross
head, C4-04 pier head and E3-03 pier head are in progress. (d)
The 3rd Pour include roof of LT1 for HKY is in progress. (e)
TWSR-East drainage and watermain
from Ch250 to Ch350 install works are in progress. |
ND/2019/06 |
(a)
Rectification works for
E&M installations for the steel canopy, MOB and additional water tank and
pump house at Portion 3 have been completed. (b)
Flag pole installation at
Portion 3 has been completed. (c)
Finishing works for the
additional water tank and pump house at Portion 3 are in progress. (d)
Installation of handrails
at new pump house at Portion 3 has been completed. (e)
Joint sealant application
for carriageway at Portion 3 is in progress. (f)
Grating cover installation
at Portion 3 is in progress. |
ND/2019/07 |
(a)
Site clearance at Portion 2
and 4 (b)
Erection of site hoarding
at Portion 2 and 4 (c)
C&D waste disposal in
Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 and
5 (e)
Drainage works and Sewerage
works at Portion 1, 3 and 4 (f)
Construction of box culvert
in Portion 2 (g)
Filling works in Portion 1,
2 and 4 (h)
Tree felling / Disposal of
yard waste in Portion 4 (i)
Construction of site haul
road in Portion 4 |