11.1 One (1)
Limit Level for DO, two (2) Limit Level for turbidity, three
(3) Limit Level exceedances for suspended solids of impact water quality
monitoring were recorded. After investigation, all exceedances were considered due
to the other external factors rather than the contract works. No Action/Limit
Level exceedance for air quality, construction noise, ambient arsenic, landfill
gas monitoring and build heritage monitoring was recorded in the reporting
month. The summary of exceedance recorded
in the reporting month is shown in Appendix O.
11.2 Ecological monitoring was carried out in the reporting
month. The results will be compared with Action and Limit Levels after issuance
of the Final Baseline Ecological Report.
11.3 Should the monitoring results of the environmental
monitoring parameters at any designated monitoring stations indicate that
Action / Limit Levels are exceeded, the actions in accordance with the Event/Action
Plan in Appendix N would be carried out.
11.4 No environmental non-compliance was recorded in the
reporting month.
11.5 No
environmental complaint was received in the reporting month. The Cumulative Complaint Log since the
commencement of the Project is presented in Appendix S.
11.6
There was no
successful environmental prosecution or notification of summons received since
the Project commencement. The Cumulative Log for environmental summon and
successful prosecution since the commencement of the Project is presented in Appendix T.