Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (July 2022 to September 2022)

ND/2019/01

 

(a)           Site Clearance, remove of existing structures, tree felling in Portion 1a

(b)           Site clearance, backfilling, ground investigation, sheet piling, excavation and drainage in Portion 1b

(c)           Site clearance, demolition of existing structures in Portion 1c

(d)          Site clearance, tree felling in Portion 1e

(e)           Site clearance, tree felling, temporary road construction, site formation work in Portion 2

(f)            Site clearance, backfilling, excavation, tree felling and drainage works in Portion 3

(g)           Site Clearance, sheet piling and excavation, drainage works and temporary road constructure, watermain in Portion 5

(h)           Site Clearance, sheet piling and excavation, pipes laying, backfilling, construction of KB01 retaining wall in Portion 6a

(i)            Operation of HAC treatment facility in Portion 6b

(j)            Site Clearance,

(k)           sheet piling and excavation, pipes laying in Portion 7

(l)            Construction of retaining wall, slope cutting, slope drainage and maintenance access construction, RC construction of flushing water service reservoir and fresh water reservoir, pipe pile wall of WSD¡¦s maintenance access, backfilling works in Portion 8a

(m)         Grouting for receiving pit , trenchless works, excavation, ELS for jacking pit at LWSC¡¦s car park in Portion 8b

(n)           Site clearance, Sheet piling and excavation, drainage works , GI works and retaining wall in Portion 9b

(o)           Stockpile of soil, excavation in Portion 9c

(p)           Excavation, sheet piling for ELS, drainage works, road construction, utilities laying in Portion 10a

(q)           Sheet piling and excavation, drainage works in Portion 10b

(r)            Construction of MBR in Portion 11b

(s)            Construction of temporary sewage pumping station in Portion 14

ND/2019/02

(a)             Pipe Jacking

(b)            Backfilling

(c)             Concreting

(d)            Bedding & Pipe Laying

(e)             ELS

(f)             Sheet Pile Installation

(g)            Cut and Fill of Slope

ND/2019/03

 

(a)         Portion 1 & Portion 1A

-            Drainage works at Yin Kong Road

-            Construction of Pai Lau

(b)       Portion 2 to Portion 20C

-          Erection of Permanent Boundary Structure

-          Construction of Irrigation Channel

-          Construction works of Type 1 Storage House

-          Construction works of Type 2 Storage House

-          Construction of Tea House

-          Construction of Decking & Sluices

-          Construction of Composting Facility

-          Construction works of Bird Hide

-          Construction works of Outdoor Classroom

-          Wetland Creation & Restoration works

-          Construction of Compacted Earth Path/ Walkway

-          Construction of Wetland Boardwalk

ND/2019/04

 

(a)           Tree felling

(b)          Predrill

(c)           Bored piling

(d)          Excavation

(e)           Sheet piling and ELS

ND/2019/05

(a)            North Team Works

-          Pre-drilling for bored piles at B2-03-P3, P5, P6

-          Bored piling at B1& B2(Portion II), C1(Portion II) & D2-01.

-          ELS and Pile cap construction at C1-01b, C1-02b, C1-03, C1-04, C2-02, C2-03a, C2-04a, C3-01a, C3-02, D1-02 & E2-01

-          C3-03 & C3-04 Portal Beam

-          Raft footing construction at C4-02

-          Pier construction at C1-01b, C1-02b, C1-03, C1-04, C2-01, C2-02, C3-03a, C3-04ab, C4-02, D1-02, D1-03, D1-04, E1-04 & E2-01.

 

(b)            Viaduct Works

-          Segment fabrication for bridge C2 & C3 & D1 & E1.

-          Remaining components of Launching Girder (LG) delivery to site.

-          Erection of 1st pair non match cast segments at pier C4-03.

-          LG pre-assembly between pier C4-03 to C4-04a/bM.

-          Cast in-situ SOP construction at Pier E2-02, E3-03.

-          1st set FT delivery. To be used in July-2022.

-          2nd set FT fabrication and delivery. To be used in July-2022.

-          3rd set FT design and fabrication. To be used in Feb-2023.

-          4th set FT design and fabrication. To be used in May-2023.

-          Complete construction of pile caps E2-01 and D2-01 and installation of cast-in rotation bridge components.

-          Bridge rotation system fabrication completion and delivery to site

 

(c)            South Team Works

-          Venton Area ¡V Construct new road (section from Venton to Kei Kee).

-          Portion 13 ¡V UU ducts laying after backfilling completed at FW 52 bay 1 to bay 3.

-          Portion 17 and 18 ¡V Construction of DN 600 and DN450 sewer. RW 52 bay 4a, 4b and 5

-          Portion 18 ¡V 132kv ducts laying and Gas main laying.

-          TWSR (West) ¡V Backfilling and form new road behind FW06 and FS04 slope works.

-          TWSR (East) ¡V Form new road

-          HKY FB (East) ¡V construction of P01

-          Portion 11 ¡V DN1200 and DN600 watermain laying work.

-          E2-03 ¡V Pile cap and Pier construction.

-          E3-01 ¡V Pier construction.

-          E3-02 ¡V Cap and Pier construction

-          D2-02 ¡V Pier construction.

-          D2-03 ¡V Cap and Pier construction.

-          E3-04a ¡V Piling works.

-          E3-04b, E3-05M and E4-01 ¡V predrilling and piling.

-          NB109 ¡V base slab construction.

ND/2019/06

 

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Site clearance at Portion 4

(b)       Erection of site hoarding at Portion 4

(c)        C&D waste disposal at Portion 1, 2, 4 and 5

(d)       G.I. works at Portion 4

(e)        Construction of box culvert at Portion 2

(f)        Filling works at Portion 1, 2 and 4

(g)        Tree felling / Disposal of yard waste at Portion 4

(h)       Construction of site haul road at Portion 4

(i)         Drainage works, Sewerage works at Portion 1, 3, 4 and 5

(j)         Mini piling works at Portion 4

(k)       Construction of noise barrier at Portion 4 and 5

(l)         Waterworks at Portion 1