Table IV Summary Table for Site Activities in the coming Three
Months
Contract No. |
Site Activities (July 2022 to September 2022) |
ND/2019/01 |
(a)
Site
Clearance, remove of existing structures, tree felling in Portion 1a (b)
Site
clearance, backfilling, ground investigation, sheet piling, excavation and
drainage in Portion 1b (c)
Site
clearance, demolition of existing structures in Portion 1c (d)
Site
clearance, tree felling in Portion 1e (e)
Site
clearance, tree felling, temporary road construction, site formation work in
Portion 2 (f)
Site
clearance, backfilling, excavation, tree felling and drainage works in
Portion 3 (g)
Site
Clearance, sheet piling and excavation, drainage works and temporary road constructure, watermain in
Portion 5 (h)
Site
Clearance, sheet piling and excavation, pipes laying, backfilling,
construction of KB01 retaining wall in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
Clearance, (k)
sheet
piling and excavation, pipes laying in Portion 7 (l)
Construction
of retaining wall, slope cutting, slope drainage and maintenance access
construction, RC construction of flushing water service reservoir and fresh
water reservoir, pipe pile wall of WSD¡¦s maintenance access, backfilling
works in Portion 8a (m)
Grouting
for receiving pit , trenchless works, excavation, ELS for jacking pit at
LWSC¡¦s car park in Portion 8b (n)
Site
clearance, Sheet piling and excavation, drainage works , GI works and
retaining wall in Portion 9b (o)
Stockpile
of soil, excavation in Portion 9c (p)
Excavation,
sheet piling for ELS, drainage works, road construction, utilities laying in
Portion 10a (q)
Sheet
piling and excavation, drainage works in Portion 10b (r)
Construction
of MBR in Portion 11b (s)
Construction
of temporary sewage pumping station in Portion 14 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b) Portion 2 to Portion 20C -
Erection
of Permanent Boundary Structure -
Construction
of Irrigation Channel -
Construction
works of Type 1 Storage House -
Construction
works of Type 2 Storage House -
Construction
of Tea House -
Construction
of Decking & Sluices -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Wetland
Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction
of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree
felling (b)
Predrill (c)
Bored
piling (d)
Excavation
(e)
Sheet
piling and ELS |
ND/2019/05 |
(a)
North Team Works -
Pre-drilling for bored piles at B2-03-P3, P5, P6 -
Bored piling at B1& B2(Portion
II), C1(Portion II) & D2-01. -
ELS and Pile cap construction at C1-01b, C1-02b,
C1-03, C1-04, C2-02, C2-03a, C2-04a, C3-01a, C3-02, D1-02 & E2-01 -
C3-03 & C3-04 Portal Beam -
Raft footing construction at C4-02 -
Pier construction at C1-01b, C1-02b, C1-03,
C1-04, C2-01, C2-02, C3-03a, C3-04ab, C4-02, D1-02, D1-03, D1-04, E1-04 &
E2-01. (b)
Viaduct Works -
Segment fabrication for bridge C2 & C3 &
D1 & E1. -
Remaining components of Launching Girder (LG)
delivery to site. -
Erection of 1st pair non match cast segments at
pier C4-03. -
LG pre-assembly between pier
C4-03 to C4-04a/bM. -
Cast in-situ SOP construction at Pier E2-02,
E3-03. -
1st set FT delivery. To be used in July-2022. -
2nd set FT fabrication and delivery. To be used
in July-2022. -
3rd set FT design and fabrication. To be used in Feb-2023. -
4th set FT design and fabrication. To be used in
May-2023. -
Complete construction of pile caps E2-01 and
D2-01 and installation of cast-in rotation bridge components. -
Bridge rotation system fabrication completion and
delivery to site (c)
South Team Works -
Venton Area
¡V Construct new road (section from Venton to Kei Kee). -
Portion 13 ¡V UU ducts laying after backfilling
completed at FW 52 bay 1 to bay 3. -
Portion 17 and 18 ¡V Construction of DN 600 and
DN450 sewer. RW 52 bay 4a, 4b and 5 -
Portion 18 ¡V 132kv ducts laying and Gas main
laying. -
TWSR (West) ¡V Backfilling and form new road
behind FW06 and FS04 slope works. -
TWSR (East) ¡V Form new road -
HKY FB (East) ¡V construction of P01 -
Portion 11 ¡V DN1200 and DN600 watermain
laying work. -
E2-03 ¡V Pile cap and Pier construction. -
E3-01 ¡V Pier construction. -
E3-02 ¡V Cap and Pier construction -
D2-02 ¡V Pier construction. -
D2-03 ¡V Cap and Pier construction. -
E3-04a ¡V Piling works. -
E3-04b, E3-05M and E4-01 ¡V predrilling and
piling. -
NB109 ¡V base slab construction. |
ND/2019/06 |
The construction phase has been completed and handed over to AFCD since 4
April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding
at Portion 4 (c)
C&D waste disposal at
Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 (e)
Construction of box culvert
at Portion 2 (f)
Filling works at Portion 1,
2 and 4 (g)
Tree felling / Disposal of
yard waste at Portion 4 (h)
Construction of site haul
road at Portion 4 (i)
Drainage works, Sewerage
works at Portion 1, 3, 4 and 5 (j)
Mini
piling works at Portion 4 (k)
Construction
of noise barrier at Portion 4 and 5 (l)
Waterworks
at Portion 1 |