Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (June 2022) |
ND/2019/01 |
(a)
Site clearance, tree
felling, demolition of existing structures and site formation works at
Portion 1a (b)
sheet piling, excavation,
tree felling , backfilling, and drainage at Portion 1b (c)
Site clearance, demolition
of existing structures at Portion 1c and 1e (d)
Site clearance, tree
felling, temporary road construction and site formation works at Portion 2 (e)
Site clearance, excavation,
backfilling at Portion 3 (f)
Site clearance, sheet
piling, excavation, drainage works, watermain,
backfill and road work at Portion 5 (g)
Site clearance, drainage
works, backfilling, Retaining wall KB01 construction at Portion 6a (h)
Operation of HAC soil
treatment facility at Portion 6b (i)
Site clearance, sheet
piling and excavation, drainage works, site formation works at Portion 7 (j)
Construction of retaining
wall, slope drainage and maintenance access construction, RC construction of
flushing water service reservoir and fresh water service reservoir, and
backfilling works at Portion 8a (k)
Site clearance, ELS for
jacking pit at LWSC¡¦s car park and sheet piling for receiving pit
at Portion 8b (l)
Site clearance, Sheet
piling and excavation, retaining wall and drainage works at Portion 9b (m)
Stockpile of soil,
excavation at Portion 9c (n)
Excavation, drainage works
and road work and utilities works at Portion 10a (o)
Sheet piling and excavation
at Portion 10b (p)
Construction of MBR at
Portion 11b (q)
Construction of temporary
sewage pumping station at Portion 14 (r)
Construction of CLC at
Portion 16 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
ELS (e)
bedding
an pipe laying (f)
Sheet
Pile Installation |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b)
Long
Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Path / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Tree
felling (b)
Predrill (c)
Bored
piling (d)
Excavation (e)
Sheet
piling and ELS |
ND/2019/05 |
(a)
The rotary drilling rigs, one is located at C2-02
and C2-03. The second is located at B2-02. The RCD rig is located at E3-04
and another RCD rig located at D2-01. (b)
C4-01 Portal Beam, C4-03 cross head, E2-02 SOP
cast in-situ and E3-03 SOP cast in-situ are in progress. (c)
TWSR-East drainage and watermain
from Ch100 to Ch450 install works are in progress. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding
at Portion 4 (c)
C&D waste disposal in
Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 (e)
Construction of box culvert
in Portion 2 (f)
Filling works in Portion 1,
2 and 4 (g)
Tree felling / Disposal of
yard waste in Portion 4 (h)
Construction of site haul
road in Portion 4 (i)
Drainage works and Sewerage
works at Portion 1, 3, 4 and 5 (j)
Mini piling works at
Portion 4 (k)
Construction of noise
barrier at Portion 4 and 5 (l)
Waterworks at Portion 1 |