Table 2.1b Summary of Scope of Works under concerned EP

Environmental Permit (EP) No.

Work Contract(s)

Scope of Works under concerned EP(s)

Site Layout Plan under concerned EP(s)

EP-466/2013(Part)

C1

Realign Castle Peak Road and join with the Pak Shek Au Interchange at the western end

Figure 12

EP-467/2013/A(Part)

C1

Construction of new primary distributor road (P1) within Kwu Tung North New Development Area

Figure 13

EP-468/2013/A(Part)

C1

Construction of new primary distributor roads (D1, D3, D4 and part of D5) within Kwu Tung North New Development Area

Figure 14

C3

Development of a nature park at Long Valley and ecological mitigation and enhancement works for the nature park (Condition 2.9)

Figure 15

EP-469/2013(Part)

C2

Construction of one sewage pumping station in Kwu Tung North with installed capacity of more than 2,000 m3 per day

Figure 16

EP-470/2013(Part)

C1

Construction of service reservoir and watermain for the reuse of treated sewage effluent for reuse in Kwu Tung North Development Areas

Figure 17

EP-473/2013/A(Part)

C3

Establishment of alternative egretry sites and enhance the existing egretry site at Ho Sheung Heung and/or its vicinity (Condition 2.7)

Figure 18

EP-473/2013/A(Part)

C5A

Construction of new district distributor inside FLN NDA, which provides a linkage between the Man Kam To Road and the proposed Fanling Bypass Eastern Section

Figure 19

EP-473/2013/A(Part)

C5B

Figure 20

EP-475/2013/A

C6

The re-provisioned wholesale market will have approximately 1,000 market stalls within a site area of around 1.3 ha

Figure21

EP-546/2017

C5A

Construct and operate a temporary sewage pumping station in Fanling North with installed capacity (average dry weather flow) of about 3,600m3/day

Figure 22

Remark: The EP(s) not related to the Project of the First Phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) Development Areas are not included in the Table.