2.1
The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of land
and housing supply in the medium and long term. The development of the KTN and
FLN NDAs will be implemented in phase for full completion by 2031. The Phase 1
of the NDAs development, comprising the Advance Works and First Stage Works, is
targeted to be implemented from the second half of 2019 progressively. The
Advance and First Stage Works would include site formation, engineering
infrastructure works (including roads, drainage, sewerage, waterworks,
landscaping works, pumping stations, and fresh water and flushing water service
reservoirs), soil remediation, reprovisioning of
North District Temporary Wholesale Market, development of a nature park at Long
Valley and implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling
Bypass (FLBP(E)) connecting the FLN NDA to Fanling
Highway and other roads with footpaths and cycle tracks, and associated
junction/ road improvements;
iii) engineering infrastructure works including
drainage. Sewerage (including two sewage pumping stations), waterworks
(including a fresh water service reservoir and a flushing water service
reservoir in the KTN NDA), landscape works and slopeworks;
iv) part expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);
v)
reprovisioning works; and
vi) implementation of environmental mitigation
measures and environmental monitoring and audit (EM&A) programme
for the works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung
Yue River for connection between these two facilities;
ii)
reprovisioning of two egretry sites in the FLN
NDA and enhancement works to an existing egretry site
in the KTN NDA;
iii) site formation of land for a village
resite area and a district police station in the KTN
NDA;
iv) engineering infrastructure works
including roads, drainage, sewerage, waterbirds, and
landscape works; and
v)
implementation of environmental mitigation measures and environmental
monitoring and audit (EM&A) programme for the
works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule
3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October
2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director
of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs
under the Project and the respective Work Contracts are summarised in Tables
2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu Tung North New
Development Area Road P1 and P2 and Associated New Kwu
Tung Interchange and Pak Shek Au Interchange
Improvement |
ü |
¡@ |
|||||||
Kwu Tung North New
Development Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
ü |
¡@ |
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling Bypass Eastern
Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision of temporary
Wholesale Market in Fanling North New Development
Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling North Temporary
Sewage Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental Permit
(EP) No. |
Work Contract(s) |
Scope of Works under
concerned EP(s) |
Site Layout Plan under
concerned EP(s) |
EP-466/2013(Part) |
C1 |
Realign Castle Peak Road and join with the Pak Shek
Au Interchange at the western end |
Figure
12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road (P1) within Kwu Tung North New Development Area |
Figure
13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor roads (D1, D3, D4 and part of
D5) within Kwu Tung North New Development Area |
Figure
14 |
C3 |
Development of a nature park at Long Valley and ecological mitigation
and enhancement works for the nature park (Condition 2.9) |
Figure
15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station in Kwu
Tung North with installed capacity of more than 2,000 m3 per day |
Figure
16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and watermain
for the reuse of treated sewage effluent for reuse in Kwu
Tung North Development Areas |
Figure
17 |
EP-473/2013/A(Part) |
C3 |
Establishment of alternative egretry sites and enhance
the existing egretry site at Ho Sheung
Heung and/or its vicinity (Condition 2.7) |
Figure
18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor inside FLN NDA, which provides
a linkage between the Man Kam To Road and the proposed Fanling
Bypass Eastern Section |
Figure
19 |
EP-473/2013/A(Part) |
C5B |
Figure
20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will have approximately 1,000
market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage pumping station in Fanling North with installed capacity (average dry
weather flow) of about 3,600m3/day |
Figure
22 |
Remark:
The EP(s) not related to the Project of the First
Phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) Development
Areas are not included in the Table.
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
The
required submissions and submission status under Environmental Permits are
shown in Appendix U.
2.6
The
site
layout
plans
under concerned Environmental Permits are shown in Figures
12 - 22.
2.7
Different
parties with different levels of involvement in the Project organisation include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM
Environmental Team (ET) ¡V Wellab Limited
Independent Environmental Checker
(IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
names and contact numbers of key personnel are summarised in Table
2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil Engineering and Development
Department, HKSAR (CEDD) |
Project Proponent |
Mr. Raymond Cheng |
3619 3919 |
3547 1658 |
Supervisor
/ Supervisor's Representative (AECOM) |
Chief
Resident Engineer |
Mr. Alan Lee |
6398 5982 |
2645 3900 |
Environmental
Team (Wellab Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898 7388 |
2898
7076 |
Independent
Environmental Checker (MottMac) |
Independent
Environmental Checker |
Mr. Thomas Chan |
2828
5967 |
2827
1823 |
Contract No. ND/2019/01 Contractor (Build King
¡V Richwell Engineering Joint Venture) |
Site
Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental
Officer |
Mr. Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor (Chun Wo ¡V
Kwan Lee Joint Venture.) |
Site
Agent |
Mr. Andy Chan |
3485 9780 |
-- |
Environmental
Officer |
Mr. Kenneth Chan |
9300 2182 |
||
Contract No. ND/2019/03 Contractor (Sang Hing Kuly Joint Venture) |
Site
Agent |
Mr. Tang Wing Kai |
9300 7037 |
-- |
Environmental
Officer |
Mr. Vincent Hung |
6742
5596 |
||
Contract No. ND/2019/04 Contractor (Daewoo ¡V
Chun Wo ¡V Kwan Lee Joint Venture) |
Site
Agent |
Mr. Bear Ding |
6483
6198 |
-- |
Environmental
Officer |
Ms. Donna Tso |
9283
7167 |
||
Environmental
Supervisor |
Ms. Peggie Hon |
9714
3308 |
||
Contract No. ND/2019/05 Contractor (CRCC ¡V
Paul Y. Joint Venture) |
Site
Agent |
Mr. Darvin
Lo |
9467
5891 |
-- |
Environmental
Manager |
Mr. Pan Fong |
9436
9435 |
||
Environmental
Officer |
Ms. Louise Poon |
5272
5709 |
||
Contract No. ND/2019/06 Contractor (New
Concepts Engineering Development Ltd.) |
Site
Agent |
Mr. Anson Chan |
9349
1320 |
2363
2162 |
Environmental
Officer |
Mr. Alex Choy |
9409
9608 |
||
Environmental
Coordinator |
Ms. Gloria Wong |
64398946 |
||
Contract No. ND/2019/07 Contractor (China Road
and Bridge Corporation) |
Site
Agent |
Mr. Daniel Wong |
5335
9572 |
-- |
Environmental
Officer |
Mr. K. M. Lui |
5113
8223 |
||
Environmental
Supervisor |
Mr. Attlee Chau |
6386
9018 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract
No. |
Site
Activities (July 2022) |
ND/2019/01 |
(a)
Site clearance, tree
felling, removal of existing structure s, site formation and G.I works at
Portion 1a (b)
Sheet piling, excavation,
backfilling and drainage works at Portion 1b (c)
Site clearance, removal of
existing structures and site formation at Portion 1c and 1e (d)
Site clearance, tree
felling and site formation at Portion 2 (e)
Site clearance, excavation,
backfilling and drainage works at Portion 3 (f)
Drainage works, watermain, excavation, backfilling and road work at
Portion 5 (g)
Construction of retaining
wall, drainage works, and backfilling at Portion 6a (h)
Operation of HAC soil
treatment facility at Portion 6b (i)
Site formations, sheet
piling, excavation and drainage works at Portion 7 (j)
Construction of retaining
wall, slope drainage and maintenance access construction, RC construction of
flushing water service reservoir and fresh water service reservoir, GI works
and backfilling works at Portion 8a (k)
ELS for jacking pit at LWSC¡¦s
car park and excavation for receiving pit and trenchless work at Portion 8b (l)
Sheet piling, excavation,
drainage works and construction of retaining wall at Portion 9b (m)
Stockpile of soil and
excavation. at Portion 9c (n)
Excavation, sheet piling
for ELS, drainage works, road works and utilities works at Portion 10a (o)
Sheet piling and excavation
at Portion 10b (p)
Construction of MBR at
Portion 11b (q)
Construction of CLC at
Portion 16 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
and pipe laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut
and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b)
Long
Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Bund / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Tree
felling (b)
Predrill (c)
Bored
piling (d)
Excavation (e)
Sheet
piling and ELS |
ND/2019/05 |
(a)
The rotary drilling rigs, one is located at C2-02
and C2-03. The second is located at B2-02. The third one is located at E3-04.
The RCD rig located at D2-01. (b)
C4-01 Portal Beam, C4-03 cross head, E2-02 SOP
cast in-situ and E3-03 SOP cast in-situ are in progress. (c)
TWSR-East drainage and watermain
from Ch100 to Ch450 install works are in progress. |
ND/2019/06 |
The
construction phase was completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding
at Portion 4 (c)
C&D waste disposal in
Portion 1, 2, 4 and 5 (d)
Drainage works and Sewerage
works at Portion 1, 3 and 4 (e)
Construction of box culvert
in Portion 2 (f)
Filling works in Portion 1,
2 and 4 (g)
Construction of site haul
road in Portion 4 (h)
Waterworks at Portion 1 |
2.10
Copies of Contractors¡¦ construction programmes are
provided in Appendix A.
2.11 A summary of the relevant permits, licences, and/or notifications on environmental protection
for this Project is presented in Table
2.4.
Table 2.4 Status
of Environmental Licences, Notifications and Permits
Contract
No. |
Permit
/ Licence No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental
Permit (EP) |
||||
ND/2019/01 |
EP-466/2013 |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013 |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
|
ND/2019/04 |
EP/473/2013/A |
27/01/2017 |
N/A |
Valid |
EP/546/2017 |
16/11/2017 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction Noise
Permit (CNP) |
||||
ND/2019/01 |
GW-RN0036-22 |
23/01/2022 |
16/07/2022 |
Expired in reporting month |
GW-RN0619-22 |
17/07/2022 |
16/01/2023 |
Valid |
|
GW-RN0388-22 |
11/05/2022 |
10/11/2022 |
Valid |
|
GW-RN0172-22 |
25/03/2022 |
24/09/2022 |
Valid |
|
GW-RN0173-22 |
08/03/2022 |
07/09/2022 |
Valid |
|
GW-RN0285-22 |
08/04/2022 |
07/10/2022 |
Valid |
|
GW-RN0480-22 |
14/06/2022 |
13/07/2022 |
Expired in reporting month |
|
ND/2019/02 |
GW-RN0047-22 |
01/02/2022 |
31/07/2022 |
Expired in reporting month |
GW-RN0660-22 |
01/08/2022 |
31/01/2023 |
Valid |
|
ND/2019/03 |
GW-RN0055-22 |
01/03/2022 |
31/08/2022 |
Valid |
ND/2019/05 |
GW-RN0316-22 |
28/04/2022 |
27/07/2022 |
Expired in reporting month |
GW-RN0551-22 |
11/07/2022 |
10/10/2022 |
Valid |
|
GW-RN0570-22 |
05/07/2022 |
31/08/2022 |
Valid |
|
ND/2019/06 |
GW-RN0054-22 |
13/02/2022 |
12/08/2022 |
Valid |
Notification pursuant
to Air Pollution Control (Construction Dust)
Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/04 |
461184 |
23/10/2020 |
N/A |
Valid |
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
ND/2019/07 |
459393 |
28/08/2020 |
N/A |
Valid |
Billing Account for
Disposal of Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/04 |
7038391 |
22/09/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
ND/2019/07 |
7038309 |
14/09/2020 |
N/A |
Valid |
Registration
of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/04 |
5211-624-D2709-01 |
26/11/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
ND/2019/07 |
5213-625-C4498-01 |
21/09/2020 |
N/A |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00037191-2020 |
21/04/2022 |
28/02/2026 |
Valid |
|
WT00037204-2020 |
02/02/2021 |
28/02/2025 |
Valid |
|
WT00037412-2021 |
15/04/2021 |
30/04/2026 |
Valid |
|
WT00037564-2021 |
19/04/2021 |
30/04/2026 |
Valid |
|
WT00037886-2021 |
28/06/2021 |
30/06/2026 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
WT00036952-2020 |
17/12/2020 |
31/12/2025 |
Valid |
|
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
WT00036414-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
WT00037771-2021 |
08/07/2021 |
31/07/2026 |
Valid |
|
WT00035984-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
ND/2019/04 |
WT00037539-2021 |
16/04/2021 |
30/04/2026 |
Valid |
ND/2019/05 |
WT00036996-2020 |
22/12/2020 |
31/12/2025 |
Valid |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |
ND/2019/07 |
WT00037526-2021 |
21/04/2022 |
31/05/2026 |
Valid |