10.1
Site
audits were carried out by ET on a weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures on the Contract site. Summary
of the site
audits are presented in Table 10.1 and Appendix P.
Table 10.1 Summary
of Site Audits
Environmental
Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly site audit
with representative of the Supervisor¡¦s Representative and the
Contractor |
5, 13, 19 and 26 July
22 |
6, 15, 20 and 27 July
22 |
8, 15, 19 and 29 July
22 |
7, 14, 21 and 28 July
22 |
4, 14, 18 and 25 July
22 |
7, 14, 21 and 28 July
22 |
8, 15, 22 and 29 July
22 |
Joint Site Audit
with representative of the Supervisor¡¦s Representative, the
Contractor and IEC |
13 July 22 |
15 July
22 |
19
July 22 |
6 July 22 |
14 July 22 |
N/A |
8 July 22 |
10.2
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarised in Table
10.2.
10.3
All
construction activities with significant environmental impact undertaken by
Contract No. ND/2019/06 was substantially completed in March 2022 and the majority
of outstanding works were also completed in April 2022 with defect
rectification works remained. The outstanding installation works
were
the short-duration works which would be completed within 2 months during
the 1-year defect correction period. ET would record the environmental
deficiency, if any, for NDTWM (EP-475/2013/A) during the 1-year defect
correction period under Contract ND/2019/04 site inspection and would
email weekly those inspection records to the Project Team of Contract
ND/2019/06 for information.
Table 10.2
Observations and Recommendations during Site Audits
Parameters |
Date |
Observations
and Recommendations |
Follow-up |
Contract No.: ND/2019/01 |
|||
Permits / Licences |
19/07/2022 |
Environmental Permit should be displayed
conspicuously on site at Portion 9C. |
Improvement/Rectification
was observed during follow-up audit session on 26 July 2022. |
Contract No.: ND/2019/02 |
|||
Landscape and Visual |
15/7/2022 |
To clarify the fallen tree status. |
Item Remarked as 220720-R01. Follow-up action is
needed to be review. |
20/07/2022 |
Item Remarked as 220727-R01. Follow-up action is
needed to be review. |
||
27/07/2022 |
To clarify the nearly fallen tree status. |
Follow-up action is needed to be reported in the
following month. |
|
Ecology |
15/7/2022 |
Dull green barrier should be maintained properly. |
Improvement/Rectification
was observed during follow-up audit session on 20 July 2022. |
Water Quality |
27/07/2022 |
To enhance mitigation measures to prevent surface runoff into the Sheung Yue River near 1.43.7. |
Follow-up action is needed to be reported in the
following month. |
Contract No.: ND/2019/03 |
|||
Air Quality |
08/07/2022 |
Vehicle
entrance within 30m of construction site should be kept clean of dust. |
Improvement/Rectification was
observed during follow-up audit session on 15 July 2022. |
29/07/2022 |
Dusty
debris were observed at Yin Kong Road. Contractor was reminded to clear the
dusty debris immediately. |
Follow-up
action is needed to be reported in the following month. |
|
Waste/ Chemical Management |
08/07/2022 |
Drip
tray should be provided for chemical container. |
Improvement/Rectification was
observed during follow-up audit session on 15 July 2022. |
Contract No.: ND/2019/04 |
|||
Air Quality |
30/06/2022 |
To replace faded NRMM labels. / Replace the faded
NRMM labels. |
Item Remarked as 220707-R01. Follow-up action is
needed to be review. |
07/07/2022 |
Improvement/Rectification
was observed during follow-up audit session on 14 July 2022. |
||
07/07/2022 |
Cover the stockpile of dusty materials at the
site near Ma Wat River. |
Improvement/Rectification
was observed during follow-up audit session on 14 July 2022. |
|
Ecology |
07/07/2022 |
Maintain the silt curtain to avoid muddy water entering the river. |
Improvement/Rectification
was observed during follow-up audit session on 14 July 2022. |
Waste / Chemical Management |
30/06/2022 |
General refuse should be disposed of properly. |
Improvement/Rectification
was observed during follow-up audit session on 7 July 2022. |
Contract No.: ND/2019/05 |
|||
Air Quality |
27/06/2022 |
Dusty stockpile should be covered by impervious
sheeting properly. |
Improvement/Rectification
was observed during follow-up audit session on 4 July 2022. |
Water Quality |
04/07/2022 |
Sand bag barrier should be provided to direct
storm water efficiently. |
Improvement/Rectification
was observed during follow-up audit session on 14 July 2022. |
14/07/2022 |
Should prevent dusty stockpile to enter the river
with sufficient mitigation measure. |
Improvement/Rectification
was observed during follow-up audit session on 18 July 2022. |
|
18/07/2022 |
Should prevent muddy stockpile entering the river with
sufficient mitigation measures. |
Improvement/Rectification
was observed during follow-up audit session on 25 July 2022. |
|
Contract No.: ND/2019/06 |
|||
-- |
-- |
-- |
-- |
Contract No.: ND/2019/07 |
|||
-- |
-- |
-- |
-- |
10.4
According
to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
Q. The photographic records of measures as stipulated in EPs
to mitigate environmental impacts in the reporting month are presented in Table 10.3.
Table 10.3 Photographic Records and
Implementation Status of Measures
EP No. |
Condition |
Photographic Record |
Implementation Status |
EP-466/2013 |
2.9 |
To
minimise adverse impacts on habitats of ecological
importance
in the vicinity of the Project, 2m high solid dull green site barrier fences
shall be erected around all active works areas. |
^[1] |
EP-467/2013/A |
2.9 |
To
minimise adverse impacts on habitats of ecological
importance
in the vicinity of the Project, 2m high solid dull green site barrier fences
shall be erected around all active works areas. |
^[1] |
EP-468/2013/A |
2.11 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-469/2013 |
2.7 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-473/2013/A |
2.13 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance
of mitigation measure ¡P Non-compliance
but rectified by the contractor N/A Not Applicable at this stage as no such
site activities were conducted in the reporting period |
Remark:
[1]: Barrier
fences might be subjected to change according to the phasing plan designed at
detailed design stage
10.5
The water quality mitigation measures
detailed in the EIA Report and the Updated EM&A Manual are recommended to
be implemented during the construction phase. Water quality mitigation measures
implemented by the contractors were closely monitored to prevent water
pollution, especially during rainy season. An updated summary of the Environmental
Mitigation Implementation Schedule is provided in Appendix Q. Specific
water quality mitigation measures for major construction works in the reporting
month are presented in Table 10.4.
Table 10.4 Specific Water Quality
Mitigation Measures for Major Construction Works in the Reporting Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Hydroseeding for slope area |
ND/2019/02 |
Hard paved exposed
haul road |
Hard paved exposed slope surface |
ND/2019/03 |
Hard paved exposed
haul road |
Regular clearance of
water for wheel washing facility |
ND/2019/04 |
Hard paved exposed slope surface |
Deployment of silt curtain around works area
in Ng Tung River |
ND/2019/05 |
Covering dusty
stockpile |
Provision of sand bags around works area |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
De-silting waste water before discharge |
Water quality mitigation measures for site(s) in
operation phase, remaining defect works |
||
ND/2019/06 |
Hard paved exposed
haul road |
Hard paved exposed haul road |
10.6
Waste generated
from Contract Nos.
ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05 and ND/2019/07
included
inert construction and demolition (C&D) materials and non-inert C&D
wastes in the reporting
month.
The site of ND/2019/06 was handed over to AFCD for operation since 4 April
2022.
10.7
The amount of wastes generated by
the construction works of the Contract Nos. ND/2019/01,
ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05 and ND/2019/07 during the reporting month
are shown in Appendix R. The
site of ND/2019/06 was handed over to AFCD for operation since 4 April 2022.
10.8
The
Contractors are advised to minimise
the wastes generated through recycling or reusing. All mitigation measures
stipulated in the Updated EM&A Manual and waste management plans shall be
fully implemented. The status of implementation of waste management and
reduction measures are summited in Appendix
Q.
10.9
Based on the findings of the EIA
Report, the area of Long Valley has been assessed as of high to very high
ecological value and is the largest contiguous area of freshwater wetland
habitats in Hong Kong. To safeguard the ecological value of Long Valley, about
37 hectares of land in Long Valley has been proposed to develop into Long
Valley Nature Park (LVNP) for conserving and enhancing the ecologically
important environment as well as for compensation of the wetland loss due to
the NDA development.
10.10
LVNP is developed according to the approved
Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. HCMP
provides a framework and specifications for development and management of LVNP
and guides the development to maintain and enhance the 37 hectares of low-lying
wetland habitats.
10.11
Regarding
the design, the zoning of land use in LVNP is intended to maintain the existing
mosaic pattern of wet and dry agriculture, while controlling the activities
that could potentially disturb target habitats and species. LVNP will be divided
into three broad zones of land use as below:
•
Biodiversity
Zone of about 21 hectares largely designated for biodiversity conservation
through cultivation of specified crops and habitat management.
•
Agricultural
Zone of about 11 hectares designated for commercially focuses crop production
and eco-friendly agricultural practice for farming.
•
Visitor
Zone of about 5 hectares designed to accommodate visitors as well as storage
and other facilities and for educational purposes.
10.12
The
construction of LVNP started in late 2019 and was expected to be completed in 2023.
During the construction
period, the progress of construction and wetland enhancement works has been
under observation by different stakeholders including AFCD and green groups.
Close communication between AFCD and CEDD were conducted to exchange views on
conservation, restoration and management of habitats as well as on the planning
and design of the park. In addition, advices from green groups, Hong
Kong Bird Watching Society (HKBWS) and The Conservancy Association (CA), have been
taken on habitat management of Long Valley and potential effects on habitat and
wildlife of each individual work conducted in Long Valley. A regular
meeting was held
monthly (on
15 July 2022 in the reporting month) to share the progress of LVNP with
different stakeholders, including CEDD, AFCD, CA, HKBWS, Contractor, ET, IEC
and farmers.
10.13
Proposals
on wetland creation and restoration, dry agricultural land creation, pond
creation, water treatment wetland and design of irrigation channel were
submitted by the Contractor to achieve the objectives stated in HCMP and
accepted by the Engineer with consent from AFCD before implementation. The
Contractor would
consult the stakeholders for recommendations and suggestions on mitigation
measures to minimise the environmental impacts
arising from construction works. The progress of works would
be arranged to minimise impacts to avifauna and
maintain the habitat for avifauna. The photographic records of site activities
in LVNP are presented in Table 10.5.
Table 10.5 Photographic Records of Site Activities in LVNP
Continuing agricultural practice in existing
farmland to maintain habitats in Long Valley |
||
Open
water Habitat |
Open
water Habitat |
|
Creation of wetland with designated
habitat for biodiversity conservation |
||
Planting of paddy rice to provide
foraging ground for Yellow-breasted Bunting |
||
Retention of washing bay for amphibians
breeding |
Enhancement of irrigation channel
to provide reliable water source for farmland in Long Valley |
|
Provision of bird island (hidden area) |
Restoring of water flea pond to provide
food source to water birds |
|
Construction of storage sheds for farmers |
A Glareola maldivarum was
recorded |
|
Wet agricultural land |
Provision of noise barrier for noisy
works in Long Valley |
|