Table IV Summary Table for Site Activities in the coming Three
Months
Contract No. |
Site Activities (August 2022 to October 2022) |
ND/2019/01 |
(a)
Site
Clearance, tree felling, remove of existing structures, site formation and
G.I. works in Portion 1a (b)
Sheet
piling, excavation, backfilling and drainage works in Portion 1b (c)
Site
clearance, removal of existing structures and site formation in Portion 1c (d)
Site
clearance and site formation in Portion 1e (e)
Site
clearance, tree felling, site formation work and construction of subway in
Portion 2 (f)
Site
clearance, excavation, backfilling and drainage works in Portion 3 (g)
Drainage
works, watermain, excavation, backfilling and road
works in Portion 5 (h)
Construction
of retaining wall, drainage works and backfilling in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
formation, sheet piling, excavation and drainage works in Portion 7 (k)
Construction
of retaining wall, slope cutting, slope drainage and maintenance access
construction, RC construction of flushing water service reservoir and fresh
water reservoir, pipe pile wall of WSD¡¦s maintenance access, backfilling
works and site formation in Portion 8a (l)
ELS for
jacking pit at LWSC¡¦s car park, excavation for receiving pit and trenchless
work in Portion 8b (m)
Sheet
piling, excavation, drainage works and construction of retaining wall in
Portion 9b (n)
Stockpile
of soil and excavation in Portion 9c (o)
Excavation,
sheet piling for ELS, drainage works, road construction, utilities works in
Portion 10a (p)
Sheet
piling, excavation and drainage works in Portion 10b (q)
Construction
of MBR in Portion 11b |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b) Long Valley -
Erection
of Permanent Boundary Structure -
Construction
of Irrigation Channel -
Construction
works of Type 1 Storage House -
Construction
works of Type 2 Storage House -
Construction
of Tea House -
Construction
of Decking & Sluices -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Wetland
Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction
of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree
felling (b)
Predrill (c)
Bored
piling (d)
Excavation
(e)
Sheet
piling and ELS |
ND/2019/05 |
(a)
North Team Works -
Pre-drilling for bored piles at B2-03-P3, P5, P6 -
Bored piling at B1, B2 & C1(Portion
II). -
ELS works and Pile cap construction at, C2-03a,
C2-04a, C3-01a, C3-02 & D1-02 -
C3-03 & C3-04 Portal Beam -
Pier construction at C1-01b, C1-02b, C1-03,
C1-04, C2-01, C2-02, C3-03a, C3-04ab, C4-02, D1-02, D1-03, D1-04, E1-04 &
E2-01. (b)
Viaduct Works -
Segment fabrication for bridge C2 & C3 &
D1 & E1. -
Remaining components of Launching Girder (LG)
delivery to site. -
Erection of 1st pair non match cast segments at
pier C4-03. -
LG assembly works. -
Cast in-situ SOP construction at Pier E2-02,
E3-03. -
2nd set FT delivery. To be used in August-2022. -
3rd set FT design and fabrication. To be used in
Feb-2023. -
4th set FT design and fabrication. To be used in
May-2023. -
Complete construction of pile caps E2-01 and
D2-01 and installation of cast-in rotation bridge components. -
Bridge rotation system fabrication completion and
delivery to site (c)
South Team Works -
Venton Area
¡V Construct new road (section from Venton to Kei Kee). -
Portion 13 ¡V Fw52 bay 1 to 4a, backfilling to
formation level. -
Portion 17 and 18 ¡V Backfilling for new TWSRW. -
Portion 18 ¡V 132kv ducts laying and Gas main
laying. -
TWSR (West) ¡V Backfilling and form new road
behind FW06 and FS04 slope works. -
TWSR (East) ¡V Form new road -
HKY FB (East) ¡V construction of P01 -
Portion 11 ¡V DN600 watermain
laying work. -
E2-03 ¡V Pile cap and Pier construction. -
E3-01 ¡V Pier construction. -
E3-02 ¡V Cap and Pier construction -
D2-02 ¡V Pier construction. -
D2-03 ¡V Cap and Pier construction. -
E3-04a ¡V Piling works. -
E3-04b, E3-05M and E4-01 ¡V predrilling and
piling. -
NB109 ¡V base slab construction. |
ND/2019/06 |
The construction phase has been completed and handed over to AFCD since 4
April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding
at Portion 4 (c)
C&D waste disposal at
Portion 1, 2, 4 and 5 (d)
Construction of box culvert
at Portion 2 (e)
Filling works at Portion 1,
2 and 4 (f)
Construction of site haul
road at Portion 4 (g)
Drainage works, Sewerage
works at Portion 1, 3, 4 and 5 (h)
Mini
piling works at Portion 4 (i)
Construction
of noise barrier at Portion 4 and 5 (j)
Waterworks
at Portion 1 |