Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (July 2022) |
ND/2019/01 |
(a)
Site clearance, tree
felling, removal of existing structure s, site formation and G.I works at
Portion 1a (b)
Sheet piling, excavation,
backfilling and drainage works at Portion 1b (c)
Site clearance, removal of
existing structures and site formation at Portion 1c and 1e (d)
Site clearance, tree
felling and site formation at Portion 2 (e)
Site clearance, excavation,
backfilling and drainage works at Portion 3 (f)
Drainage works, watermain, excavation, backfilling and road work at
Portion 5 (g)
Construction of retaining
wall, drainage works, and backfilling at Portion 6a (h)
Operation of HAC soil
treatment facility at Portion 6b (i)
Site formations, sheet
piling, excavation and drainage works at Portion 7 (j)
Construction of retaining
wall, slope drainage and maintenance access construction, RC construction of
flushing water service reservoir and fresh water service reservoir, GI works
and backfilling works at Portion 8a (k)
ELS for jacking pit at LWSC¡¦s
car park and excavation for receiving pit and trenchless work at Portion 8b (l)
Sheet piling, excavation,
drainage works and construction of retaining wall at Portion 9b (m)
Stockpile of soil and
excavation. at Portion 9c (n)
Excavation, sheet piling
for ELS, drainage works, road works and utilities works at Portion 10a (o)
Sheet piling and excavation
at Portion 10b (p)
Construction of MBR at
Portion 11b (q)
Construction of CLC at
Portion 16 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
and pipe laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut
and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b)
Long
Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Bund / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Tree
felling (b)
Predrill (c)
Bored
piling (d)
Excavation (e)
Sheet
piling and ELS |
ND/2019/05 |
(a)
The rotary drilling rigs, one is located at C2-02
and C2-03. The second is located at B2-02. The third one is located at E3-04.
The RCD rig located at D2-01. (b)
C4-01 Portal Beam, C4-03 cross head, E2-02 SOP
cast in-situ and E3-03 SOP cast in-situ are in progress. (c)
TWSR-East drainage and watermain
from Ch100 to Ch450 install works are in progress. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding
at Portion 4 (c)
C&D waste disposal in
Portion 1, 2, 4 and 5 (d)
Drainage works and Sewerage
works at Portion 1, 3 and 4 (e)
Construction of box culvert
in Portion 2 (f)
Filling works in Portion 1,
2 and 4 (g)
Construction of site haul
road in Portion 4 (h)
Waterworks at Portion 1 |