Table 10.2       Observations and Recommendations during Site Audits

 

Parameters

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

 

Permits / Licences

19/07/2022

Environmental Permit should be displayed conspicuously on site at Portion 9C.

Improvement/Rectification was observed during follow-up audit session on 26 July 2022.

Contract No.: ND/2019/02

Landscape and Visual

15/7/2022

To clarify the fallen tree status.

Item Remarked as 220720-R01. Follow-up action is needed to be review.

20/07/2022

Item Remarked as 220727-R01. Follow-up action is needed to be review.

27/07/2022

To clarify the nearly fallen tree status.

Follow-up action is needed to be reported in the following month.

Ecology

15/7/2022

Dull green barrier should be maintained properly.

Improvement/Rectification was observed during follow-up audit session on 20 July 2022.

Water Quality

27/07/2022

To enhance mitigation measures to prevent surface runoff into the Sheung Yue River near 1.43.7.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/03

Air Quality

08/07/2022

Vehicle entrance within 30m of construction site should be kept clean of dust.

Improvement/Rectification was observed during follow-up audit session on 15 July 2022.

29/07/2022

Dusty debris were observed at Yin Kong Road. Contractor was reminded to clear the dusty debris immediately.

Follow-up action is needed to be reported in the following month.

Waste/ Chemical Management

08/07/2022

Drip tray should be provided for chemical container.

Improvement/Rectification was observed during follow-up audit session on 15 July 2022.

Contract No.: ND/2019/04

Air Quality

30/06/2022

To replace faded NRMM labels. / Replace the faded NRMM labels.

Item Remarked as 220707-R01. Follow-up action is needed to be review.

07/07/2022

Improvement/Rectification was observed during follow-up audit session on 14 July 2022.

07/07/2022

Cover the stockpile of dusty materials at the site near Ma Wat River.

Improvement/Rectification was observed during follow-up audit session on 14 July 2022.

Ecology

07/07/2022

Maintain the silt curtain to avoid muddy

water entering the river.

Improvement/Rectification was observed during follow-up audit session on 14 July 2022.

Waste / Chemical Management

30/06/2022

General refuse should be disposed of properly.

Improvement/Rectification was observed during follow-up audit session on 7 July 2022.

Contract No.: ND/2019/05

Air Quality

27/06/2022

Dusty stockpile should be covered by impervious sheeting properly.

Improvement/Rectification was observed during follow-up audit session on 4 July 2022.

Water Quality

04/07/2022

Sand bag barrier should be provided to direct storm water efficiently.

Improvement/Rectification was observed during follow-up audit session on 14 July 2022.

14/07/2022

Should prevent dusty stockpile to enter the river with sufficient mitigation measure.

Improvement/Rectification was observed during follow-up audit session on 18 July 2022.

18/07/2022

Should prevent muddy stockpile entering the

river with sufficient mitigation measures.

Improvement/Rectification was observed during follow-up audit session on 25 July 2022.

Contract No.: ND/2019/06

--

--

--

--

Contract No.: ND/2019/07

 

--

--

--

--