11.1 No
exceedance of Action and Limit Levels of air quality, construction noise, additional
water quality monitoring, ambient arsenic and landfill
gas monitoring in the reporting month. The summary of exceedance record in
reporting month is shown in Appendix O.
11.1 Ecological monitoring was carried out in the reporting
month. The Action and Limit Level will be compared after the issue of Final
Baseline Ecological Report.
11.2 Should the monitoring results of the environmental
monitoring parameters at any designated monitoring stations indicate that the
Action / Limit Levels are exceeded, the actions in accordance with the Event
and Action Plans in Appendix N would
be carried out.
11.3 No environmental non-compliance was recorded in the
reporting month.
11.4 Two
environmental complaint for ND/2019/04 and ND/2019/02 were received in the
reporting month.. The Cumulative Complaint Log since the
commencement of the Project is presented in Appendix S.
11.5
There was no
successful environmental prosecution or notification of summons received since
the Project commencement. The Cumulative Log for environmental summon and
successful prosecution since the commencement of the Project is presented in Appendix T.