10.1
Site
audits were carried out by ET on weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures on the Contract site. The
summaries of site audits are presented in Table 10.1 and Appendix P.
Table 10.1 Summary
of Site Audit
Environmental Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly site audit with representative of the Supervisor’s
Representative and the Contractor |
4, 13, 18, 25 and 31
Jan 22 |
5, 12, 21, 26 and 31
Jan 22 |
7, 14, 18 and 28 Jan
22 |
6, 14, 20 and 27 Jan
22 |
3, 10, 20, 24 and 31
Jan 22 |
6, 13, 18, 27 and 31
Jan 22 |
7, 12, 21 and 28 Jan
22 |
Joint Site Audit with representative of the Supervisor’s
Representative, the Contractor and IEC |
13 Jan 22 |
21 Jan
22 |
18 Jan
22 |
14 Jan 22 |
20 Jan 22 |
18 Jan 22 |
12 Jan 22 |
10.2
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarised in Table 10.2.
Table 10.2 Observations and Recommendations during
Site Audits
|
Date |
Observations
and Recommendations |
Follow-up |
Contract No.: ND/2019/01 |
|||
Waste/ Chemical Management |
28/12/2021 |
Drip tray should be provided for chemical
storage. |
Improvement/Rectification
was observed during follow-up audit session on 4 January 2022. |
25/01/2022 |
Chemical waste shall be labelled clearly. |
Improvement/Rectification
was observed during follow-up audit session on 31 January 2022. |
|
Contract No.: ND/2019/02 |
|||
Air Quality |
21/01/2022 |
Dusty haul road should be sprayed with water regularly. |
Improvement/Rectification
was observed during follow-up audit session on 26 January 2022. |
Water Quality |
29/12/2021 |
Remove dusty materials beside the U-channel and clear the stagnant
water inside the U-channel. (South Bridge) |
Improvement/Rectification
was observed during follow-up audit session on 5 January 2022. |
29/12/2021 |
To enhance water control measure to prevent any discharge of muddy
water to Sheung Yue River. (河口) |
Improvement/Rectification
was observed during follow-up audit session on 5 January 2022. |
|
29/12/2021 |
To enhance water control measure to prevent any discharge of muddy water
to Sheung Yue River. (North Bridge) |
Improvement/Rectification
was observed during follow-up audit session on 5 January 2022. |
|
29/12/2021 |
Clear and treat the stagnant muddy water inside the U-Channel with
desilting facilities before discharge. (North Bridge) |
Improvement/Rectification
was observed during follow-up audit session on 5 January 2022. |
|
12/01/2022 |
Enhance water mitigation measure to prevent muddy water runoff to
U-channel. |
Improvement/Rectification
was observed during follow-up audit session on 21 January 2022. |
|
21/01/2022 |
Clear the stagnant water insider the U-channel. |
Improvement/Rectification
was observed during follow-up audit session on 26 January 2022. |
|
31/01/2022 |
Enhance water mitigation measure to prevent muddy water runoff to
U-channel. |
Follow-up
action is needed to be reported in the following month. |
|
Ecology |
26/01/2022 |
Erect 2m high dull green barrier around active works area. |
Item
was remarked as 220131-R01. Follow-up action is needed to be reviewed. |
31/01/2022 |
Erect 2m high dull green barrier around active works area. |
Follow-up
action is needed to be reported in the following month. |
|
Contract No.: ND/2019/03 |
|||
Air Quality |
14/01/2022 |
Dusty stockpiles should be properly covered with impervious
sheeting. |
Item
was remarked as 220118-R01. Follow-up action is needed to be reviewed. |
18/01/2022 |
Dusty stockpiles should be properly covered with impervious
sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 28 January 2022. |
|
Water Quality |
31/12/2021 |
To clean wheel-washing bay regularly. |
Improvement/Rectification
was observed during follow-up audit session on 7 January 2022. |
18/01/2022 |
Wheel-washing bay should be cleared regularly. |
Item
was remarked as 220128-R01. Follow-up action is needed to be reviewed. |
|
18/01/2022 |
To enhance water mitigation measures around water
stream near 巨賓. |
Item
was remarked as 220128-R02. Follow-up action is needed to be reviewed. |
|
28/01/2022 |
Wheel-washing bay should be cleared regularly. |
Follow-up
action is needed to be reported in the following month. |
|
28/01/2022 |
To enhance water mitigation measures around water
stream near 巨賓. |
Follow-up
action is needed to be reported in the following month. |
|
Contract No.: ND/2019/04 |
|||
Air Quality |
06/01/2022 |
Faded NRMM label shall be replaced. |
Improvement/Rectification
was observed during follow-up audit session on 14 January 2022. |
20/01/2022 |
Faded NRMM label shall be replaced. |
Item
was remarked as 220127-R01. Follow-up action is needed to be reviewed. |
|
27/01/2022 |
Faded NRMM label shall be replaced. |
Follow-up
action is needed to be reported in the following month. |
|
Noise |
30/12/2021 |
To enhance noise mitigation measures along Shek Wu San Tsuen. |
Item
was remarked as 220106-R01. Follow-up action is needed to be reviewed. |
06/01/2022 |
To enhance noise mitigation measures along Shek Wu San Tsuen. |
Improvement/Rectification
was observed during follow-up audit session on 14 January 2022. |
|
Water Quality |
14/01/2022 |
Clear the sediment and debris along the
U-channel. |
Improvement/Rectification
was observed during follow-up audit session on 20 January 2022. |
20/01/2022 |
Clear the sediment and provide desilting
facilities inside the drainage. |
Item
was remarked as 220127-R02. Follow-up action is needed to be reviewed. |
|
27/01/2022 |
Clear the sediment and provide desilting
facilities inside the drainage. |
Follow-up
action is needed to be reported in the following month. |
|
Contract No.: ND/2019/05 |
|||
Air Quality |
03/01/2022 |
Stockpile should be covered by impervious
sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 10 January 2022. |
24/01/2022 |
Dusty stockpile should be covered by impervious sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 31 January 2022. |
|
Water Quality |
28/12/2021 |
Enhance mitigation measures to prevent surface
runoff to Ma Wat River. |
Improvement/Rectification
was observed during follow-up audit session on 3 January 2022. |
10/01/2022 |
Enhance water mitigation measure to prevent muddy
water runoff to the U-channel. |
Improvement/Rectification
was observed during follow-up audit session on 20 January 2022. |
|
Waste / Chemical Management |
20/01/2022 |
Clear the oil stains on the ground. |
Improvement/Rectification
was observed during follow-up audit session on 24 January 2022. |
Contract No.: ND/2019/06 |
|||
Ecology |
13/01/2022 |
Dull green hoarding should be properly
maintained. |
Improvement/Rectification
was observed during follow-up audit session on 18 January 2022. |
27/01/2022 |
Dull green hoarding should be properly
maintained. |
Improvement/Rectification
was observed during follow-up audit session on 31 January 2022. |
|
Water Quality |
18/01/2022 |
Clear the stagnant water and avoid chemical
leakage to U-channel. |
Improvement/Rectification
was observed during follow-up audit session on 27 January 2022. |
31/01/2022 |
Exposed slope surface should be covered. |
Follow-up
action is needed to be reported in the following month. |
|
Contract No.: ND/2019/07 |
|||
-- |
-- |
-- |
-- |
10.3
According
to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
Q. The photographic records of measures as stipulated in EP to mitigate
environmental impacts in the reporting month are presented in Table 10.3.
Table 10.3 Photographic Records and Implementation
Status of Measures
EP No. |
Condition |
Photographic Record |
Implementation Status |
EP-466/2013 |
2.9 |
To
minimise adverse impacts on habitats of ecological imprtance in the vicinity of the Project, 2m high solid
dull green site barrier fences shall be erected around all active works
areas.(Figure 12) |
^[1] |
EP-468/2013/A |
2.11 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 14) |
^[1] |
EP-469/2013 |
2.7 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 15) |
#[1] |
EP-473/2013/A |
2.13 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 16) |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 17) |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance of mitigation measure · Non-compliance
but rectified by the contractor N/A Not
Applicable at this stage as no such site activities were conducted in the
reporting period |
[1]: Barrier
fences might be subjected to change according to phasing plan designed at
detailed design stage
10.4
Under
EP-467/2013/A (Condition 2.9), to minimise adverse
impacts on habitats of ecological importance in the vicinity of the Project, 2m
high solid dull green site barrier fences shall be erected around all active
works areas. As the Works programme under above EPs
were still under preparation work and the
barrier fences erection was still progressing in the Reporting Month, 2m high
solid dull green site barrier fences will be checked once in place. The
Hoarding Plan of the above EPs is shown in Figure
13.
10.5
According
to the EIA Report and the Updated EM&A Manual, the Air quality and Noise
mitigation measures detailed in the documents are recommended to be implemented
during the construction phase. Air quality and Noise mitigation measures implemented
by the contractors were closely monitored to prevent water pollution,
especially during dry season. An updated summary of the Environmental
Mitigation Implementation Schedule is provided in Appendix Q. Specific Air quality and Noise mitigation measures for
major construction works in the reporting month are presented in Table 10.4.
Table 10.4 Specific Air Quality and Noise Mitigation Measures for Major
Construction Works in the Reporting Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Access road watered
regularly |
ND/2019/02 |
Hard paved exposed
haul road |
Hard paved exposed slope surface |
ND/2019/03 |
Deployment of noise
barriers between construction site and NSRs |
Dusty material
covered by impervious sheeting |
ND/2019/04 |
Access road watered regularly |
Regulated machines display with Non-road
Mobile Machinery labels |
ND/2019/05 |
Covering dusty
stockpile |
Access road watered regularly |
ND/2019/06 |
Covering dusty stockpile |
Hard paved exposed haul road |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
Vehicle washing facilities at exit point |
10.6
Waste generated
from Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06
and ND/2019/07 include inert construction and demolition (C&D) materials
and non-inert C&D wastes in the Reporting Month.
10.7
The amount of
wastes generated by the construction works of the Contract
No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and
ND/2019/07 during the
reporting month are shown in Appendix R.
10.8
The
Contractors are advised to minimize the wastes generated through recycling or
reusing. All mitigation measures stipulated in the Updated EM&A Manual and
waste management plans shall be fully implemented. The status of implementation
of waste management and reduction measures are summited in Appendix Q.
10.9
From
the findings of EIA Report, the area of Long Valley has been assessed as of
high to very high ecological value and is the largest contiguous area of
freshwater wetland habitats in Hong Kong. To safeguard the ecological value of
Long Valley, about 37 hectares of land in Long Valley has been proposed to
develop into Long Valley Nature Park (LVNP) for conserving and enhancing the
ecologically important environment as well as for compensation of the wetland
loss due to the NDA development.
10.10
LVNP is developed according to approved
Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. The
HCMP provides a framework and specifications for development and management of
the LVNP and guides the development to maintain and enhance the 37ha of low-lying
wetland habitats.
10.11
Regarding
to the design, the zoning of land use in the LVNP is intended to maintain the
existing mosaic pattern of wet and dry agriculture, while controlling the
activities that could potentially disturb target habitats and species. The LVNP
will divide into three broad zones of land use as below:
•
Biodiversity
Zone of about 21 hectares largely designated for biodiversity conservation
through cultivation of specified crops and habitat management.
•
Agricultural
Zone of about 11 hectares designated for commercially focuses crop production
and eco-friendly agricultural practice for farming.
•
Visitor
Zone of about 5 hectares designed to accommodate visitors as well as storage
and other facilities and for educational purposes.
10.12
The
construction of the LVNP started in late 2019 and is expected to be completed
in 2023. During construction period, the progress of construction and wetland
enhancement works are under observation by different stakeholders including
AFCD and green groups. Close communication between AFCD and CEDD are conducted
to exchange views on conservation, restoration and management of habitats as
well as on the planning and design of the park. Also, advices from green
groups, Hong Kong Bird Watching Society (HKBWS) and The Conservancy Association
(CA), are taken on habitat management of Long Valley and potential effects on
habitat and wildlife of each individual work conducted in Long Valley. Regular
meeting are held monthly on 28th January 2022 in the reporting month
to share the progress of LVNP with different stakeholders, including CEDD,
AFCD, CA, HKBWS, Contractor, ET, IEC and farmers.
10.13 Proposals on wetland creation and
restoration, dry agricultural land creation, pond creation, water treatment
wetland and design of irrigation channel are submitted by the Contractor to
achieve the objectives stated in HCMP and accepted by the Engineer with consent
from AFCD before implementation. The Contractor will consult with the
stakeholders for recommendations and suggestions on mitigation measures to minimise the environmental impacts arising from
construction works. The progress of works will be arranged to minimise impacts to avifauna and maintain the habitat for
avifauna. The photographic records of site activities in LVNP are presented in Table 10.5.
Table 10.5 Photographic
Records of Site Activities in LVNP
Agricultural practice are continued in
existing farmland to maintain habitats in Long Valley |
|||
Lotus
pond |
Open
water Habitat |
Chinese
arrowhead pond |
|
Creation of wetland with designated
habitat for biodiversity conservation |
|||
Planting of paddy rice to provide
foraging ground for Yellow-breasted Bunting |
|||
Retention of washing bay for amphibians
breeding |
Enhancement of irrigation channel
to provide reliable water source for farmland in Long Valley |
||
Provision of bird island (hidden area) |
Restoring of water flea pond to provide
food source to water birds |
||
Construction of storage sheds for farmers |
An Upupa
epops was recorded |
||
Provision of wastewater treatment
facilities |
Provision of noise barrier for noisy
works in Long Valley |
||