10           ENVIRONMENTAL SITE INSPECTION

Site Audits

10.1     Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures on the Contract site.  The summaries of site audits are presented in Table 10.1 and Appendix P.

Table 10.1   Summary of Site Audit

Environmental Site Inspection

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/04

ND/2019/05

ND/2019/06

ND/2019/07

Weekly site audit with representative of the Supervisor’s Representative and the Contractor

4, 13, 18, 25 and 31 Jan 22

5, 12, 21, 26 and 31 Jan 22

7, 14, 18 and 28 Jan 22

6, 14, 20 and 27 Jan 22

3, 10, 20, 24 and 31 Jan 22

6, 13, 18, 27 and 31 Jan 22

7, 12, 21 and 28 Jan 22

Joint Site Audit with representative of the Supervisor’s Representative, the Contractor and IEC

13 Jan 22

21 Jan 22

18 Jan 22

14 Jan 22

20 Jan 22

18 Jan 22

12 Jan 22

 

10.2     During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarised in Table 10.2.


 

 

Table 10.2       Observations and Recommendations during Site Audits

 

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

 

Waste/ Chemical Management

28/12/2021

Drip tray should be provided for chemical storage.

Improvement/Rectification was observed during follow-up audit session on 4 January 2022.

25/01/2022

Chemical waste shall be labelled clearly.

Improvement/Rectification was observed during follow-up audit session on 31 January 2022.

Contract No.: ND/2019/02

Air Quality

21/01/2022

Dusty haul road should be sprayed with water regularly.

Improvement/Rectification was observed during follow-up audit session on 26 January 2022.

Water Quality

29/12/2021

Remove dusty materials beside the U-channel and clear the stagnant water inside the U-channel. (South Bridge)

Improvement/Rectification was observed during follow-up audit session on 5 January 2022.

29/12/2021

To enhance water control measure to prevent any discharge of muddy water to Sheung Yue River. (河口)

Improvement/Rectification was observed during follow-up audit session on 5 January 2022.

29/12/2021

To enhance water control measure to prevent any discharge of muddy water to Sheung Yue River. (North Bridge)

Improvement/Rectification was observed during follow-up audit session on 5 January 2022.

29/12/2021

Clear and treat the stagnant muddy water inside the U-Channel with desilting facilities before discharge. (North Bridge)

Improvement/Rectification was observed during follow-up audit session on 5 January 2022.

12/01/2022

Enhance water mitigation measure to prevent muddy water runoff to U-channel.

Improvement/Rectification was observed during follow-up audit session on 21 January 2022.

21/01/2022

Clear the stagnant water insider the U-channel.

Improvement/Rectification was observed during follow-up audit session on 26 January 2022.

31/01/2022

Enhance water mitigation measure to prevent muddy water runoff to U-channel.

Follow-up action is needed to be reported in the following month.

Ecology

26/01/2022

Erect 2m high dull green barrier around active works area.

Item was remarked as 220131-R01. Follow-up action is needed to be reviewed.

31/01/2022

Erect 2m high dull green barrier around active works area.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/03

Air Quality

14/01/2022

Dusty stockpiles should be properly covered with impervious sheeting.

Item was remarked as 220118-R01. Follow-up action is needed to be reviewed.

18/01/2022

Dusty stockpiles should be properly covered with impervious sheeting.

Improvement/Rectification was observed during follow-up audit session on 28 January 2022.

Water Quality

31/12/2021

To clean wheel-washing bay regularly.

Improvement/Rectification was observed during follow-up audit session on 7 January 2022.

18/01/2022

Wheel-washing bay should be cleared regularly.

Item was remarked as 220128-R01. Follow-up action is needed to be reviewed.

18/01/2022

To enhance water mitigation measures around water stream near 巨賓.

Item was remarked as 220128-R02. Follow-up action is needed to be reviewed.

28/01/2022

Wheel-washing bay should be cleared regularly.

Follow-up action is needed to be reported in the following month.

28/01/2022

To enhance water mitigation measures around water stream near 巨賓.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/04

Air Quality

06/01/2022

Faded NRMM label shall be replaced.

Improvement/Rectification was observed during follow-up audit session on 14 January 2022.

20/01/2022

Faded NRMM label shall be replaced.

Item was remarked as 220127-R01. Follow-up action is needed to be reviewed.

27/01/2022

Faded NRMM label shall be replaced.

Follow-up action is needed to be reported in the following month.

Noise

 

30/12/2021

To enhance noise mitigation measures along Shek Wu San Tsuen.

Item was remarked as 220106-R01. Follow-up action is needed to be reviewed.

06/01/2022

To enhance noise mitigation measures along Shek Wu San Tsuen.

Improvement/Rectification was observed during follow-up audit session on 14 January 2022.

Water Quality

14/01/2022

Clear the sediment and debris along the U-channel.

Improvement/Rectification was observed during follow-up audit session on 20 January 2022.

20/01/2022

Clear the sediment and provide desilting facilities inside the drainage.

Item was remarked as 220127-R02. Follow-up action is needed to be reviewed.

27/01/2022

Clear the sediment and provide desilting facilities inside the drainage.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/05

Air Quality

03/01/2022

Stockpile should be covered by impervious sheeting.

Improvement/Rectification was observed during follow-up audit session on 10 January 2022.

24/01/2022

Dusty stockpile should be covered by impervious sheeting.

Improvement/Rectification was observed during follow-up audit session on 31 January 2022.

Water Quality

28/12/2021

Enhance mitigation measures to prevent surface runoff to Ma Wat River.

Improvement/Rectification was observed during follow-up audit session on 3 January 2022.

10/01/2022

Enhance water mitigation measure to prevent muddy water runoff to the U-channel.

Improvement/Rectification was observed during follow-up audit session on 20 January 2022.

Waste / Chemical Management

20/01/2022

Clear the oil stains on the ground.

 

Improvement/Rectification was observed during follow-up audit session on 24 January 2022.

Contract No.: ND/2019/06

Ecology

13/01/2022

Dull green hoarding should be properly maintained.

Improvement/Rectification was observed during follow-up audit session on 18 January 2022.

27/01/2022

Dull green hoarding should be properly maintained.

Improvement/Rectification was observed during follow-up audit session on 31 January 2022.

Water Quality

18/01/2022

Clear the stagnant water and avoid chemical leakage to U-channel.

Improvement/Rectification was observed during follow-up audit session on 27 January 2022.

31/01/2022

Exposed slope surface should be covered.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/07

 

--

--

--

--

 

Implementation Status of Environmental Mitigation Measures

10.3     According to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix Q. The photographic records of measures as stipulated in EP to mitigate environmental impacts in the reporting month are presented in Table 10.3.


 

Table 10.3   Photographic Records and Implementation Status of Measures

EP No.

Condition

Photographic Record

Implementation Status

EP-466/2013

2.9

To minimise adverse impacts on habitats of ecological imprtance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 12)

^[1]

EP-468/2013/A

2.11

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 14)

^[1]

EP-469/2013

2.7

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 15)

#[1]

EP-473/2013/A

2.13

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 16)

^[1]

EP-475/2013/A

2.7

 

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.(Figure 17)

^[1]

Implementation status:

^         Mitigation measure was fully implemented

*         Observation/reminder was made during site audit but improved/rectified by the contractor

#         Observation/reminder was made during site audit but not yet improved/ rectified by the            contractor

X        Non-compliance of mitigation measure

·         Non-compliance but rectified by the contractor

N/A   Not Applicable at this stage as no such site activities were conducted in the reporting            period

[1]:       Barrier fences might be subjected to change according to phasing plan designed at detailed design stage

 

10.4     Under EP-467/2013/A (Condition 2.9), to minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas. As the Works programme under above EPs were still under preparation work and the barrier fences erection was still progressing in the Reporting Month, 2m high solid dull green site barrier fences will be checked once in place. The Hoarding Plan of the above EPs is shown in Figure 13.

Implementation Status of Air Quality and Noise Mitigation Measures

10.5     According to the EIA Report and the Updated EM&A Manual, the Air quality and Noise mitigation measures detailed in the documents are recommended to be implemented during the construction phase. Air quality and Noise mitigation measures implemented by the contractors were closely monitored to prevent water pollution, especially during dry season. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix Q. Specific Air quality and Noise mitigation measures for major construction works in the reporting month are presented in Table 10.4.

 


 

Table 10.4       Specific Air Quality and Noise Mitigation Measures for Major Construction Works in the Reporting Month

Works Contracts

Photographic Records

ND/2019/01

Hard paved exposed slope surface

Access road watered regularly

ND/2019/02

Hard paved exposed haul road

Hard paved exposed slope surface

ND/2019/03

Deployment of noise barriers between construction site and NSRs

Dusty material covered by impervious sheeting

ND/2019/04

Access road watered regularly

Regulated machines display with Non-road Mobile Machinery labels

ND/2019/05

Covering dusty stockpile

Access road watered regularly

ND/2019/06

Covering dusty stockpile

Hard paved exposed haul road

ND/2019/07

Covering exposed slope surface with tarpaulin

Vehicle washing facilities at exit point

Solid and Liquid Waste Management Status

10.6     Waste generated from Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and ND/2019/07 include inert construction and demolition (C&D) materials and non-inert C&D wastes in the Reporting Month.

10.7     The amount of wastes generated by the construction works of the Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and ND/2019/07 during the reporting month are shown in Appendix R.

10.8     The Contractors are advised to minimize the wastes generated through recycling or reusing. All mitigation measures stipulated in the Updated EM&A Manual and waste management plans shall be fully implemented. The status of implementation of waste management and reduction measures are summited in Appendix Q.


 

Ecological Mitigation Measures – Creation of Long Valley Nature Park (LVNP)

10.9     From the findings of EIA Report, the area of Long Valley has been assessed as of high to very high ecological value and is the largest contiguous area of freshwater wetland habitats in Hong Kong. To safeguard the ecological value of Long Valley, about 37 hectares of land in Long Valley has been proposed to develop into Long Valley Nature Park (LVNP) for conserving and enhancing the ecologically important environment as well as for compensation of the wetland loss due to the NDA development.

10.10  LVNP is developed according to approved Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. The HCMP provides a framework and specifications for development and management of the LVNP and guides the development to maintain and enhance the 37ha of low-lying wetland habitats.

10.11 Regarding to the design, the zoning of land use in the LVNP is intended to maintain the existing mosaic pattern of wet and dry agriculture, while controlling the activities that could potentially disturb target habitats and species. The LVNP will divide into three broad zones of land use as below:

       Biodiversity Zone of about 21 hectares largely designated for biodiversity conservation through cultivation of specified crops and habitat management.

       Agricultural Zone of about 11 hectares designated for commercially focuses crop production and eco-friendly agricultural practice for farming.

       Visitor Zone of about 5 hectares designed to accommodate visitors as well as storage and other facilities and for educational purposes.

10.12 The construction of the LVNP started in late 2019 and is expected to be completed in 2023. During construction period, the progress of construction and wetland enhancement works are under observation by different stakeholders including AFCD and green groups. Close communication between AFCD and CEDD are conducted to exchange views on conservation, restoration and management of habitats as well as on the planning and design of the park. Also, advices from green groups, Hong Kong Bird Watching Society (HKBWS) and The Conservancy Association (CA), are taken on habitat management of Long Valley and potential effects on habitat and wildlife of each individual work conducted in Long Valley. Regular meeting are held monthly on 28th January 2022 in the reporting month to share the progress of LVNP with different stakeholders, including CEDD, AFCD, CA, HKBWS, Contractor, ET, IEC and farmers.

10.13 Proposals on wetland creation and restoration, dry agricultural land creation, pond creation, water treatment wetland and design of irrigation channel are submitted by the Contractor to achieve the objectives stated in HCMP and accepted by the Engineer with consent from AFCD before implementation. The Contractor will consult with the stakeholders for recommendations and suggestions on mitigation measures to minimise the environmental impacts arising from construction works. The progress of works will be arranged to minimise impacts to avifauna and maintain the habitat for avifauna. The photographic records of site activities in LVNP are presented in Table 10.5.

 


 

Table 10.5       Photographic Records of Site Activities in LVNP

Agricultural practice are continued in existing farmland to maintain habitats in Long Valley

Lotus pond

Open water Habitat      

Chinese arrowhead pond

Creation of wetland with designated habitat for biodiversity conservation

Planting of paddy rice to provide foraging ground for Yellow-breasted Bunting

Retention of washing bay for amphibians breeding

Enhancement of irrigation channel to provide reliable water source for farmland in Long Valley

Provision of bird island (hidden area)

Restoring of water flea pond to provide food source to water birds

Construction of storage sheds for farmers

An Upupa epops was recorded

Provision of wastewater treatment facilities

WhatsApp Image 2022-02-07 at 10

Provision of noise barrier for noisy works in Long Valley