Table IV Summary
Table for Site Activities in the coming Two Months
Contract No. |
Site Activities (February 2022
and March 2022) |
ND/2019/01 |
(a)
Site Clearance, remove of existing structures and tree felling in
Portion 1a (b)
Site clearance, ground investigation, sheet piling, excavation
and drainage in Portion 1b (c)
Site Clearance and remove of existing structures in Portion 1e (d)
Site clearance, tree felling and temporary road construction in
Portion 2 (e)
Site clearance, backfilling, excavation and tree felling in Portion 3 (f)
Site clearance, sheet piling and excavation, drainage works and
temporary road construction in
Portion 5 (g)
Site
Clearance, sheet piling and excavation, pipes laying, backfilling,
construction of KB01 retaining wall, haul road construction in Portion 6a (h)
Operation
of HAC treatment facility in Portion 6b (i)
Site
clearance, sheetpiling and excavation, pipes laying and construction of APLR
in Portion 7 (j)
Construction
of retaining Wall, slope cutting, slope drainage and maintenance access
construction, RC construction of flushing water service reservoir and fresh
water reservoir, construction of temporary haul road in Portion 8a (k)
Sheet
piling for receiving pit, trenchless works, excavation in Portion 8b (l)
Sheet piling and excavation, pipes laying,
demolition of existing structures, GI works in Portion 9b (m)
Stockpile
of soil and excavation in Portion 9c (n)
Excavation,
sheetpiling for ELS, drainage works and road construction in Portion 10a (o)
Sheetpiling
and excavation, drainage works in Portion 10b (p)
Construction of MBR at 11b (q)
Construction of temporary sewage pumping station in Portion 14 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
ELS (c)
Concreting (d)
Backfilling (e)
Sheet
Pile Installation (f)
Bedding
and Pipe Laying (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b) Long Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Bund / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Site clearance (b)
Tree felling (c)
Predrill (d)
Bored piling (e)
Excavation (f)
Sheet piling (g)
ELS |
ND/2019/05 |
(a)
North Team Works -
Pre-drilling for bored piles at B1 &
B2(Portion II), C1(Portion II) & C1-03 -
Bored piling at B1(Portion I), B1&B2(Portion II),
C1(Portion II), C1-01bM, C1-02b, C1-03, C1-04, C2-01, C2-02, C2-03a, C2-03b,
C3-02, C3-03a, C3-04a, D2-01, E2-01 -
ELS and Pile cap construction at C3-03b, C3-04b,
C4-03, C4-04a, C4-04b, D1-01, D1-02, D1-03, D1-04, E1-01, E1-02, E1-03 &
E1-04 -
Bailey bridge construction near C1-02 -
Piling platform & haul road construction from
B2-03 to C1-02a at Portion II -
Footing construction at C4-02 -
Pier construction at C3-03b, C4-03, C4-04aM,
C4-04bM, D1-01, E1-01, E1-02, E1-03 & E1-04 (b)
Viaduct Works -
Installation of the 4th to 5th typical segment
mould and SOP mould to be completed by the end of Dec 2021 -
Fabrication of 6th to 8th typical segment mould
to be completed by the end of Feb 2022 -
1st SOP is targeted to cast by the end of Jan
2022 -
Target to cast in 13 segments in Jan 2022 and 16
segments in Feb 2022 -
Fabrication of launching girder (LG) is in
progress. Start LG delivery to HK site in Jan 2022 -
Fabrication of 1st set Form Travel (FT) is
targeted to complete in Jan 2022 and delivery to HK site in the end of Jan
2022 -
Bridge rotation design of Pier E2-01 submits to
ICE endorsement in Jan 2022. The design of Pier D2-01 to be completed in Jan
2022 and ICE endorsement in Feb 2022 -
Complete ground beams of segment motorized
trolley in CTC yard in Jan 2022 (c)
South Team Works -
Venton Area – Gas main laying, 11kv and 132kv
cross road duct laying -
Portion 13 – DN1200 storm drain construction -
Portion 17 and 18 – Construction of DN 600 and
DN450 sewer. RW 52 bay 6 -
Portion 18 – Gas main laying -
TWSR (West) – RW06 construction and FS04 slope
works -
HKY FB (East) – construction of LT1, P02 -
Portion 11 – DN1200 and DN600 watermain laying
work -
E2-02 pier – construction of tower crane
foundation -
E2-03 – Pile cap construction -
E3-01 – Pile cap construction -
E3-03 – Pier construction -
D2-02 – Pile cap construction -
D2-03 – Piling works |
ND/2019/06 |
(a)
Rectification works for T&C of E&M installations for the
steel canopy, MOB and additional water tank and pump house at Portion 3 (b)
Electrical board installations at stall area under the steel
canopy at Portion 3 (c)
Application of additional coating and colour strip painting on
stall area at Portion 3 (d)
Finishing works for the additional water tank and pump house at
Portion 3 (e)
Flag pole installation at Portion 3 (f)
Installation of handrails at MOB at Portion 4 and new pump house
at Portion 3 (g)
Road marking / stall marking at Portion 3 (h)
Joint sealant application for carriageway at Portion 3 (i)
CI covers and grating installation at Portion 3 (j)
Road light installation at Portion 3 (k)
Pipe connection to existing drainage MH at Interim Stage Market
at Portion 1 (l)
Drainage system cleaning and CCTV record at Portion 3 (m)
Installation of signage of the market at Portion 3 |
ND/2019/07 |
(a)
Site clearance at Portion 4 and 5 (b)
Erection of site hoarding at Portion 4 (c)
C&D waste disposal at Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 and 5 (e)
Construction of box culvert at Portion 2 (f)
Filling works at Portion 1, 2 and 4 (g)
Tree felling/ Disposal of yard waste at Portion 4 (h)
Construction of site haul road at Portion 4 (i)
Drainage works and sewage works at Portion 1, 3
and 4 (j)
Main piling works and Portion 5 |