Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (January 2022) |
ND/2019/01 |
(a)
Site clearance, tree felling, demolition of existing structures
in Portion 1a (b)
Site clearance, sheet piling, excavation, drainage
and demolition of existing structures in Protion 1b (c)
Site clearance in Portion 1e (d)
Site clearance, tree felling, temporary road construction in
Portion 2 (e)
Site clearance, excavation, backfilling in Portion 3 (f)
Site clearance, sheet piling, excavation, drainage works,
watermain, backfill in
Portion 5 (g)
Site
clearance, drainage works, backfill in Portion 6a (h)
Operation
of HAC soil treatment facility in Portion 6b (i)
Site clearance, sheet piling and excavation, drainage works in
Portion 7 (j)
Construction of retaining wall, slope cutting, slope drainage and
maintenance access construction, excavation for fresh water service
reservoir, RC construction of flushing water service reservoir in Portion 8a (k)
Site clearance, excavation for jacking pit in Portion 8b (l)
Sheet piling and excavation, drainage works in Portion 9b (m)
Stockpile of soil and excavation in Portion 9c (n)
Excavation, sheet piling for ELS, drainage works and road work in
Portion 10a (o)
Sheet
piling and excavation in Portion 10b (p)
Construction of MBR in Portion 11b (q)
Construction of temporary sewage pumping station in Portion 14 (r)
Construction of CLC in Portion 16 |
ND/2019/02 |
(a)
Sheet Pile Installation (b)
Backfilling (c)
Concreting (d)
ELS (e)
Pipe
jacking (f)
Grout Breaking |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b) Long Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Bund / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Site clearance (b)
Tree felling (c)
Predrill (d)
Bored piling (e)
Excavation (f)
Sheet piling and ELS |
ND/2019/05 |
(a)
Pre-drilling of C1-01a, C1-02a and C1-03 in
Portion III (b)
Rotary drilling rigs at B1, C1-02b, C2-01, C3-02
and C2-03 and C2-02 (c)
RCD rig at D2-03 (d)
Portal Beam at C4-01, E3-03 and E2-02 (e)
LT1 of HKY abutment third pour (f)
Pipe piling at TWSR-West FW06 |
ND/2019/06 |
(a)
E&M installations for the Management Office Building (MOB) at
Portion 4 (b)
Finishing works for the Management Office Building (MOB) at
Portion 4 (c)
Erection of the steel members and seam roof of steel canopy at
Portion 3 (d)
E&M installations for the steel canopy at Portion 3 (e)
Construction of concrete carriageway at Portion 3 (f)
Construction of screeding on stall area at Portion 3 (g)
Construction of underground utilities in the final stage market
at Portion 3 (h)
E&M installations for the additional water tank and pump
house at Portion 3 (i)
Finishing works for the additional water tank and pump house at
Portion 3 |
ND/2019/07 |
(a)
Site clearance at Portion 2 and 5 (b)
Erection of site hoarding at Portion 2 (c)
C&D waste disposal in Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 3 and 4 (e)
Drainage works at Portion 1 and 3 (f)
Construction of box culvert in Portion 2 (g)
Filling works in Portion 1 and 4 (h)
Tree felling / Disposal of yard waste in Portion 2, 4 and 5 (i)
Construction of site haul road in Portion 4 (j)
Demolition of villager’s houses in Portion 4 and 5 |