Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (January 2022)

ND/2019/01

(a)          Site clearance, tree felling, demolition of existing structures in Portion 1a

(b)         Site clearance, sheet piling, excavation, drainage and demolition of existing structures in Protion 1b

(c)          Site clearance in Portion 1e

(d)         Site clearance, tree felling, temporary road construction in Portion 2

(e)          Site clearance, excavation, backfilling in Portion 3

(f)          Site clearance, sheet piling, excavation, drainage works, watermain, backfill in Portion 5

(g)         Site clearance, drainage works, backfill in Portion 6a

(h)         Operation of HAC soil treatment facility in Portion 6b

(i)           Site clearance, sheet piling and excavation, drainage works in Portion 7

(j)           Construction of retaining wall, slope cutting, slope drainage and maintenance access construction, excavation for fresh water service reservoir, RC construction of flushing water service reservoir in Portion 8a

(k)         Site clearance, excavation for jacking pit in Portion 8b

(l)           Sheet piling and excavation, drainage works in Portion 9b

(m)       Stockpile of soil and excavation in Portion 9c

(n)         Excavation, sheet piling for ELS, drainage works and road work in Portion 10a

(o)         Sheet piling and excavation in Portion 10b

(p)         Construction of MBR in Portion 11b

(q)         Construction of temporary sewage pumping station in Portion 14

(r)          Construction of CLC in Portion 16

ND/2019/02

(a)          Sheet Pile Installation

(b)         Backfilling

(c)          Concreting

(d)         ELS

(e)          Pipe jacking

(f)          Grout Breaking

ND/2019/03

(a)        Portion 1 & Portion 1A

-            Drainage works at Yin Kong Road

-            Construction of Pai Lau

(b)       Long Valley

-          Erection of Permanent Boundary Structure

-          Construction of Compacted Earth Bund / Walkway

-          Construction of Ditches

-          Construction of Irrigation Channel

-          Construction of Decking & Sluices

-          Construction of Wetland Boardwalk

-          Construction of Type 1 Storage House

-          Construction of Type 2 Storage House

-          Construction of Tea House

-          Construction of Composting Facility

-          Construction of Bird Hide

-          Construction of Outdoor Classroom

-          Construction of Storage Sheds

-          Wetland Creation & Restoration works

ND/2019/04

(a)           Site clearance

(b)           Tree felling

(c)           Predrill

(d)           Bored piling

(e)           Excavation

(f)            Sheet piling and ELS

ND/2019/05

(a)            Pre-drilling of C1-01a, C1-02a and C1-03 in Portion III

(b)           Rotary drilling rigs at B1, C1-02b, C2-01, C3-02 and C2-03 and C2-02

(c)            RCD rig at D2-03

(d)           Portal Beam at C4-01, E3-03 and E2-02

(e)            LT1 of HKY abutment third pour

(f)            Pipe piling at TWSR-West FW06

ND/2019/06

(a)          E&M installations for the Management Office Building (MOB) at Portion 4

(b)         Finishing works for the Management Office Building (MOB) at Portion 4

(c)          Erection of the steel members and seam roof of steel canopy at Portion 3

(d)         E&M installations for the steel canopy at Portion 3

(e)          Construction of concrete carriageway at Portion 3

(f)          Construction of screeding on stall area at Portion 3

(g)         Construction of underground utilities in the final stage market at Portion 3

(h)         E&M installations for the additional water tank and pump house at Portion 3

(i)           Finishing works for the additional water tank and pump house at Portion 3

ND/2019/07

(a)            Site clearance at Portion 2 and 5

(b)           Erection of site hoarding at Portion 2

(c)            C&D waste disposal in Portion 1, 2, 4 and 5

(d)           G.I. works at Portion 3 and 4

(e)            Drainage works at Portion 1 and 3

(f)            Construction of box culvert in Portion 2

(g)           Filling works in Portion 1 and 4

(h)           Tree felling / Disposal of yard waste in Portion 2, 4 and 5

(i)             Construction of site haul road in Portion 4

(j)             Demolition of villagers houses in Portion 4 and 5