Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (January to March 2023)

ND/2019/01

 

(a)          Site Clearance, tree felling, removal of existing structures, site formation and G.I works in Portion 1a

(b)         Sheet piling, excavation, backfilling, drainage works, construction of hoarding/fencing, road works and noise barrier in Portion 1b

(c)          Site clearance, site formation and construction of hoarding in Portion 1c

(d)         Temporary storage of material and site formation in Portion 1e

(e)          Site clearance, tree felling, site formation work and construction of subway in Portion 2

(f)          Excavation, backfilling and drainage works in Portion 3

(g)         Drainage works, watermain, excavation, backfilling, road works, sheet piling and pipe jacking in Portion 5

(h)         Drainage works, backfilling, road works and watermains work in Portion 6a

(i)           Operation of HAC treatment facility in Portion 6b

(j)           Site formation, sheet piling, excavation and drainage works in Portion 7

(k)         Construction of retaining wall, maintenance access construction, RC construction of flushing water service reservoir and fresh water reservoir, pipe pile wall of WSD¡¦s maintenance access and backfilling works in Portion 8a

(l)           ELS for jacking pit at LWSC¡¦s car park and trenchless work, excavation and watermain construction in Portion 8b

(m)       Sheet piling, excavation, drainage works and constructure of retaining wall, soil nail and watermain construction in Portion 9b

(n)         Stockpile of soil in Portion 9c

(o)         Excavation, drainage works, road construction and utilities works in Portion 10a

(p)         Sheet piling, excavation and drainage works in Portion 10b

(q)         Site clearance in Portion 13

ND/2019/02

(a)           Pipe Jacking

(b)           Backfilling

(c)           Concreting

(d)           Bedding & Pipe Laying

(e)           ELS

(f)            Sheet Pile Installation

(g)           Cut and Fill of Slope

ND/2019/03

 

(a)        Portion 1 & Portion 1A

-            Road work at Yin Kong Road

-            Construction of Pai Lau

(b)     Portion 2 to Portion 20C

-          Erection of Permanent Boundary Structure

-          Construction of Type 1 Storage House

-          Construction of Type 2 Storage House

-          Construction of Tea House

-          Construction of Composting Facility

-          Construction works of Bird Hide

-          Construction works of Outdoor Classroom

-          Wetland Creation & Restoration works

-          Construction of Compacted Earth Path/ Walkway

-          Construction of Wetland Boardwalk

ND/2019/04

 

(a)           Tree Felling

(b)           Pile Cap

(c)           Bored Piling

(d)           Excavation

(e)           Sheet Piling

(f)            Drainage Works

(g)           Grouting

(h)           Road works

(i)            ELS

ND/2019/05

(a)           North Team Works

-            Bored piling at B2 (Portion II)

-            ELS works and Pile cap construction at B1-01M, B2-02, B2-03, C1-01a, C2-03b, C2-04b, C3-01b, D2-01

-            Pier construction at B1-02b, C1-01ab, C1-02ab, C2-03b, C2-04b, C3-01b & E2-01.

-            Slope works, road works and drainage works at Jockey Club Road (3SW-C/F63) and Tong Hang Junction.

(b)          Viaduct Works

-          Segment fabrication for bridge C2 & C3 & D1 & E1.

-          Segments erection for bridges C3, D1 and E1.

-          T-span in-situ construction by form traveler at E2-02 and E3-03.

-          3rd set FT design and fabrication. To be used in Feb-2023.

-          4th set FT design and fabrication. To be used in May-2023.

-          Complete construction of pile cap D2-01 and installation of cast-in rotation bridge components.

(b)       South Team Works

-          Segment fabrication for bridge C2 & C3 & D1 & E1.

-          Segments erection for bridges D1 and E1.

-          2nd set FT delivery remaining components. To be used in October-2022.

-          3rd set FT design and fabrication. To be used in Feb-2023.

-          4th set FT design and fabrication. To be used in May-2023.

-          Complete construction of pile caps E2-01 and D2-01 and installation of cast-in rotation bridge components.

-          Bridge rotation system delivery to site.

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 4 and 5

(b)        C&D waste disposal at Portion 1, 2, 4 and 5

(c)        Construction of box culvert at Portion 2

(d)        Filling works at Portion 2 and 4

(e)        Construction of site haul road at Portion 4

(f)         Drainage works, Sewerage works at Portion 1, 3, 4 and 5

(g)        Mini piling works at Portion 4

(h)        Construction of noise barrier at Portion 4 and 5

(i)         Waterworks at Portion 1