Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities
(January to March 2023) |
ND/2019/01 |
(a)
Site
Clearance, tree felling, removal of existing structures, site formation and
G.I works in Portion 1a (b)
Sheet
piling, excavation, backfilling, drainage works, construction of hoarding/fencing,
road works and noise barrier in Portion 1b (c)
Site
clearance, site formation and construction of hoarding in Portion 1c (d)
Temporary
storage of material and site formation in Portion 1e (e)
Site
clearance, tree felling, site formation work and construction of subway in
Portion 2 (f)
Excavation,
backfilling and drainage works in Portion 3 (g)
Drainage
works, watermain, excavation, backfilling, road works, sheet piling and pipe
jacking in Portion 5 (h)
Drainage
works, backfilling, road works and watermains work in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
formation, sheet piling, excavation and drainage works in Portion 7 (k)
Construction
of retaining wall, maintenance access construction, RC construction of
flushing water service reservoir and fresh water reservoir, pipe pile wall of
WSD¡¦s maintenance access and backfilling works in Portion 8a (l)
ELS for
jacking pit at LWSC¡¦s car park and trenchless work, excavation and watermain
construction in Portion 8b (m)
Sheet
piling, excavation, drainage works and constructure of retaining wall, soil
nail and watermain construction in Portion 9b (n)
Stockpile
of soil in Portion 9c (o)
Excavation,
drainage works, road construction and utilities works
in Portion 10a (p)
Sheet
piling, excavation and drainage works in Portion 10b (q)
Site clearance in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road work
at Yin Kong Road -
Construction
of Pai Lau (b)
Portion 2
to Portion 20C -
Erection of Permanent Boundary Structure -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Wetland Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree Felling (b)
Pile Cap (c)
Bored Piling (d)
Excavation (e)
Sheet Piling (f)
Drainage Works (g)
Grouting (h)
Road works (i)
ELS |
ND/2019/05 |
(a)
North Team Works -
Bored piling at B2 (Portion II) -
ELS works and Pile cap construction at B1-01M,
B2-02, B2-03, C1-01a, C2-03b, C2-04b, C3-01b, D2-01 -
Pier construction at B1-02b, C1-01ab, C1-02ab,
C2-03b, C2-04b, C3-01b & E2-01. -
Slope works, road works and drainage works at Jockey Club Road (3SW-C/F63) and Tong Hang Junction. (b)
Viaduct Works -
Segment fabrication for bridge C2 & C3 &
D1 & E1. -
Segments erection for bridges C3, D1 and E1. -
T-span in-situ construction by form traveler at
E2-02 and E3-03. -
3rd set FT design and fabrication. To be used in
Feb-2023. -
4th set FT design and fabrication. To be used in
May-2023. -
Complete construction of pile cap D2-01 and
installation of cast-in rotation bridge components. (b) South
Team Works -
Segment fabrication for bridge C2 & C3 &
D1 & E1. -
Segments erection for bridges D1 and E1. -
2nd set FT delivery remaining components. To be
used in October-2022. -
3rd set FT design and fabrication. To be used in
Feb-2023. -
4th set FT design and fabrication. To be used in May-2023. -
Complete construction of pile caps E2-01 and
D2-01 and installation of cast-in rotation bridge components. -
Bridge rotation system delivery to site. |
ND/2019/06 |
The construction phase has
been completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1,
2, 4 and 5 (c)
Construction of box culvert at Portion
2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at
Portion 4 (f)
Drainage works, Sewerage works at Portion
1, 3, 4 and 5 (g)
Mini piling works at Portion 4 (h)
Construction of noise barrier at
Portion 4 and 5 (i)
Waterworks at Portion 1 |