2.1
The
Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs) are
one of the important sources of land and housing supply in the medium and long
term. The development of the KTN and FLN NDAs will be implemented in phase for
full completion by 2031. The Phase 1 of the NDAs development, comprising the
Advance Works and First Stage Works, is targeted to be implemented from the
second half of 2019 progressively. The Advance and First Stage Works would
include site formation, engineering infrastructure works (including roads,
drainage, sewerage, waterworks, landscaping works, pumping stations, and fresh
water and flushing water service reservoirs), soil remediation, reprovisioning
of North District Temporary Wholesale Market, development of a nature park at
Long Valley and implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling Bypass (FLBP(E)) connecting
the FLN NDA to Fanling Highway and other roads with footpaths and cycle tracks,
and associated junction/ road improvements;
iii)
engineering
infrastructure works including drainage. Sewerage (including two sewage pumping
stations), waterworks (including a fresh water service reservoir and a flushing
water service reservoir in the KTN NDA), landscape works and slopeworks;
iv)
part
expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);
v)
reprovisioning
works; and
vi)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a
footbridge spanning across Sheung Yue River for connection between these two
facilities;
ii)
reprovisioning
of two egretry sites in the FLN NDA and enhancement works to an existing
egretry site in the KTN NDA;
iii)
site
formation of land for a village resite area and a district police station in
the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds, and
landscape works; and
v)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under
Schedule 3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499).
In October 2013, the EIA Report (AEIAR-175/2013) for the Project was approved
by the Director of Environmental Protection pursuant to the EIA Ordinance. The
relevant EPs under the Project and the respective Work Contracts are summarised
in Tables 2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu Tung North New Development Area Road P1 and
P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange
Improvement |
ü |
¡@ |
|||||||
Kwu Tung North New Development Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage Pumping Stations in Kwu Tung North New
Development Area |
ü |
¡@ |
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling Bypass Eastern Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision of temporary Wholesale Market in
Fanling North New Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling North Temporary Sewage Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental
Permit (EP) No. |
Work
Contract(s) |
Scope
of Works under concerned EP(s) |
Site
Layout Plan under concerned EP(s) |
EP-466/2013(Part) |
C1 |
Realign Castle Peak Road and join with the Pak
Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road (P1)
within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor roads (D1,
D3, D4 and part of D5) within Kwu Tung North New Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley and
ecological mitigation and enhancement works for the nature park (Condition 2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station in Kwu
Tung North with installed capacity of more than 2,000 m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and watermain for
the reuse of treated sewage effluent for reuse in Kwu Tung North Development
Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment of alternative
egretry sites and enhance the existing
egretry site at Ho Sheung Heung and/or its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor inside
FLN NDA, which provides a linkage between the Man Kam To Road and the
proposed Fanling Bypass Eastern Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will have
approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage pumping
station in Fanling North with installed capacity (average dry weather flow)
of about 3,600m3/day |
Figure 22 |
Remark: The EP(s) not related to the Project of the First Phase of the Kwu Tung North (KTN) and
Fanling North (FLN) New Development Area (NDA) Development Areas are not
included in the Table.
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
The
required submissions and submission status under Environmental Permits are
shown in Appendix U.
2.6
The
site
layout
plans
under concerned Environmental Permits are shown in Figures
12 - 22.
2.7
Different
parties with different levels of involvement in the Project organisation
include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM
Environmental Team (ET) ¡V Wellab
Limited
Independent Environmental Checker
(IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
names and contact numbers of key personnel are summarised in Table 2.2.
Table 2.2 Key Contacts of the
Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil
Engineering and Development Department, HKSAR (CEDD) |
Project Proponent |
Mr.
Raymond Cheng |
3619
3919 |
3547 1658 |
Supervisor /
Supervisor's Representative (AECOM) |
Chief
Resident Engineer |
Mr. Alan
Lee |
6398 5982 |
2645 3900 |
Environmental
Team (Wellab
Limited) |
Environmental Team Leader |
Dr.
Priscilla Choy |
2898 7388 |
2898 7076 |
Independent Environmental Checker (MottMac) |
Independent
Environmental Checker |
Mr. Thomas
Chan |
2828
5967 |
2827
1823 |
Contract No. ND/2019/01 Contractor (Build King ¡V Richwell Engineering Joint
Venture) |
Site Agent |
Mr. Ivan
Leung |
9640 8340 |
-- |
Environmental
Officer |
Mr. Edward
Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor (Chun Wo ¡V Kwan Lee Joint Venture.) |
Site Agent |
Mr. Andy
Chan |
3485 9780 |
-- |
Environmental
Officer |
Mr.
Kenneth Chan |
9300 2182 |
||
Contract No. ND/2019/03 Contractor (Sang Hing Kuly Joint Venture) |
Site Agent |
Mr. Tang
Wing Kai |
9300 7037 |
-- |
Environmental
Officer |
Mr.
Vincent Hung |
6742
5596 |
||
Contract No. ND/2019/04 Contractor (Daewoo ¡V Chun Wo ¡V Kwan Lee Joint
Venture) |
Site Agent |
Mr. Eric
Wu |
9786
8630 |
-- |
Environmental
Manager |
Mr. Jimmy Cheng |
9609
5916 |
||
Environmental
Officer |
Mr. Sam
Lam |
6178
3179 |
||
Contract No. ND/2019/05 Contractor (CRCC ¡V Paul Y. Joint Venture) |
Site Agent |
Mr. Darvin
Lo |
9467
5891 |
-- |
Environmental
Manager |
Mr. Pan
Fong |
9436
9435 |
||
Environmental
Officer |
Ms. Louise
Poon |
5272
5709 |
||
Contract No. ND/2019/06 Contractor (New Concepts Engineering Development
Ltd.) |
Project Manager |
Mr. Joe Cheng |
9861 0060 |
-- |
Environmental
Officer |
Mr. Jimmy
Cheng |
9609
5916 |
||
Contract No. ND/2019/07 Contractor (China Road and Bridge Corporation) |
Site Agent |
Mr. Daniel
Wong |
5335
9572 |
-- |
Environmental
Officer |
Mr. K. M.
Lui |
5113
8223 |
||
Environmental
Supervisor |
Mr. Attlee
Chau |
6386
9018 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (August 2022) |
ND/2019/01 |
(a)
Site clearance, tree
felling, removal of existing structures, site formation and G.I works at
Portion 1a (b)
Sheet piling, excavation,
backfilling and drainage works at Portion 1b (c)
Site clearance, removal of
existing structures and site formation at Portion 1c and 1e (d)
Site clearance, tree
felling, site formation and contructin of subway at Portion 2 (e)
Site clearance, excavation,
backfilling and drainage works at Portion 3 (f)
Drainage works, watermain,
excavation, backfilling and road work at Portion 5 (g)
Construction of retaining
wall, drainage works, and backfilling at Portion 6a (h)
Operation of HAC soil
treatment facility at Portion 6b (i)
Site formations, sheet
piling, excavation and drainage works at Portion 7 (j)
Construction of retaining
wall, slope drainage and maintenance access construction, RC construction of
flushing water service reservoir and fresh water service reservoir and
backfilling works at Portion 8a (k)
ELS for jacking pit at LWSC¡¦s
car park and excavation for receiving pit and trenchless work at Portion 8b (l)
Sheet piling, excavation,
drainage works and construction of retaining wall at Portion 9b (m)
Stockpile of soil at
Portion 9c (n)
Excavation, sheet piling
for ELS, drainage works, road works and utilities works at Portion 10a (o)
Sheet piling and excavation
at Portion 10b (p)
Construction of MBR at
Portion 11b |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
and pipe laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut
and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b)
Long
Valley -
Erection
of Permanent Boundary Structure -
Construction
of Irrigation Channel -
Construction
works of Type 1 Storage House -
Construction
works of Type 2 Storage House -
Construction
of Tea House -
Construction
of Decking & Sluices -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Wetland
Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction
of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree
felling (b)
Predrill (c)
Bored
piling (d)
Excavation (e)
Sheet
piling and ELS (f)
Pile
cap construction (g)
Drainage
works |
ND/2019/05 |
(a)
The rotary drilling rig is located at B2-02. The
RCD rig located at D2-01. (b)
C1-03 to C2-02 ELS in progress, C4-02 column,
C3-04 pier head, D1-04 pier head and E3-03 SOP cast in-situ are in progress. (c)
TWSR-West sewage and UUs from Ch100 to Ch450
installation works are in progress.Water main to be commenced while materials
on site. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding
at Portion 4 (c)
C&D waste disposal in
Portion 1, 2, 4 and 5 (d)
Drainage works and Sewerage
works at Portion 1, 3 and 4 (e)
Construction of box culvert
in Portion 2 (f)
Filling works in Portion 1,
2 and 4 (g)
Construction of site haul
road in Portion 4 (h)
Waterworks at Portion 1 |
2.10
Copies of Contractors¡¦ construction
programmes
are
provided in Appendix A.
2.11
A
summary of the relevant permits, licences, and/or notifications on
environmental protection for this Project is presented in Table 2.4.
Table 2.4 Status
of Environmental Licences, Notifications and Permits
Contract
No. |
Permit /
Licence No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental Permit
(EP) |
||||
ND/2019/01 |
EP-466/2013 |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013/A |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
|
ND/2019/04 |
EP/473/2013/A |
27/01/2017 |
N/A |
Valid |
EP/546/2017 |
16/11/2017 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction
Noise Permit (CNP) |
||||
ND/2019/01 |
GW-RN0173-22 |
08/03/2022 |
07/09/2022 |
Valid |
GW-RN0172-22 |
25/03/2022 |
24/09/2022 |
Valid |
|
GW-RN0285-22 |
08/04/2022 |
07/10/2022 |
Valid |
|
GW-RN0388-22 |
11/05/2022 |
10/11/2022 |
Valid |
|
GW-RN0642-22 |
09/08/2022 |
08/11/2022 |
Valid |
|
GW-RN0661-22 |
09/08/2022 |
08/11/2022 |
Valid |
|
GW-RN0619-22 |
17/07/2022 |
16/01/2023 |
Valid |
|
ND/2019/02 |
GW-RN0775-22 |
26/08/2022 |
25/11/2022 |
Valid |
GW-RN0660-22 |
01/08/2022 |
31/01/2023 |
Valid |
|
ND/2019/03 |
GW-RN0055-22 |
01/03/2022 |
31/08/2022 |
Expired in reporting month |
ND/2019/04 |
GW-RN0754-22 |
18/08/2022 |
17/11/2022 |
Valid |
GW-RN0762-22 |
23/08/2022 |
22/11/2022 |
Valid |
|
ND/2019/05 |
GW-RN0551-22 |
11/07/2022 |
10/10/2022 |
Valid |
GW-RN0570-22 |
05/07/2022 |
31/08/2022 |
Expired in reporting month |
|
ND/2019/06 |
GW-RN0054-22 |
13/02/2022 |
12/08/2022 |
Expired in reporting month |
Notification
pursuant to Air Pollution Control (Construction Dust) Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/04 |
461184 |
23/10/2020 |
N/A |
Valid |
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
ND/2019/07 |
459393 |
28/08/2020 |
N/A |
Valid |
Billing
Account for Disposal of Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/04 |
7038391 |
22/09/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
ND/2019/07 |
7038309 |
14/09/2020 |
N/A |
Valid |
Registration of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/04 |
5211-624-D2709-01 |
26/11/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
ND/2019/07 |
5213-625-C4498-01 |
21/09/2020 |
N/A |
Valid |
Effluent Discharge License under Water Pollution
Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00037191-2020 |
21/04/2022 |
28/02/2026 |
Valid |
|
WT00037204-2020 |
02/02/2021 |
28/02/2025 |
Valid |
|
WT00037412-2021 |
15/04/2021 |
30/04/2026 |
Valid |
|
WT00037564-2021 |
19/04/2021 |
30/04/2026 |
Valid |
|
WT00037886-2021 |
28/06/2021 |
30/06/2026 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
WT00036952-2020 |
17/12/2020 |
31/12/2025 |
Valid |
|
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
WT00036414-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
WT00037771-2021 |
08/07/2021 |
31/07/2026 |
Valid |
|
WT00035984-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
ND/2019/04 |
WT00037539-2021 |
16/04/2021 |
30/04/2026 |
Valid |
ND/2019/05 |
WT00036996-2020 |
22/12/2020 |
31/12/2025 |
Valid |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |
ND/2019/07 |
WT00037526-2021 |
21/04/2022 |
31/05/2026 |
Valid |