13.1
This monthly EM&A Report
presents the EM&A work undertaken in August
2022
in accordance with the Updated EM&A Manual.
13.2 No Action/Limit Level exceedance for air quality, water quality, construction
noise, ambient arsenic, landfill gas monitoring and build heritage monitoring was
recorded in the reporting month.
Contract No.
ND/2019/01
13.3
Environmental
site inspection were conducted on 2, 9, 17, 23 and 30 Aug 22 by ET in the reporting month.
Contract No. ND/2019/02
13.4
Environmental
site inspection were conducted on 3, 10, 19, 24 and 31 Aug 22 by ET in the reporting month.
Contract No.
ND/2019/03
13.5
Environmental
site inspection were conducted on 5, 12, 16 and 26 Aug 22 by ET in the reporting month.
Contract No.
ND/2019/04
13.6
Environmental
site inspection were conducted on 4, 11, 16 and 24 Aug 22 by ET in the reporting month.
Contract No.
ND/2019/05
13.7
Environmental
site inspections were conducted on 1, 8, 18, 22 and 29 Aug 22 by ET in the reporting month.
Contract No.
ND/2019/06
13.8
Environmental
site inspections were conducted on 4, 11, 16 and 24 Aug 22 by ET in the reporting month.
Contract No.
ND/2019/07
13.9
Environmental
site inspections were conducted on 5, 12, 19, 26 and 31 Aug 22 by ET in the reporting month.
13.10
Four
environmental complaints were received in the reporting month. No notification of summons or
successful prosecutions was received in the reporting month.
13.11
The
ET would keep track on the EM&A programme to
ensure compliance of environmental requirements and the proper implementation
of all necessary mitigation measures.
13.12 According to the
environmental audits performed in the reporting month, the following
recommendations were made:
Air
Quality Impact
¡P To regular water haul roads;
¡P To provide vehicle washing
facilities with high pressure water jet at every discernible or designated
vehicle exit point;
¡P To maintain the impervious
material to entirely cover the stockpile of dusty materials; and
¡P To ensure all regulated
machines displayed with valid Non-road Mobile Machinery (NRMM) labels.
Construction
Noise Impact
¡P To ensure compressor operated
with doors closed.
Water
Impact
¡P To review and implement temporary
drainage system;
¡P To prevent any surface runoff
discharge into Sheung Yuen River, Ma Wat River or public
road;
¡P To provide sandbags or
construct berm to prevent any outflow of muddy water from site area;
¡P To ensure all vehicle clear of earth
and mud before leaving the site areas;
¡P To ensure the drainage
facilities would not be clogged with waste or sediment to avoid overflow;
¡P To regularly check the
condition of desilting materials for proper function;
¡P To regularly maintain and ensure
water treatment facilities proper operation and function;
¡P To divert all the water
generated from the construction site to
de-silting facilities with sufficient handling capacity before discharge; and
¡P To avoid or regularly clear the stagnant water in
drip trays;
Waste/Chemical
Management
¡P To dispose of general refuse
properly;
¡P To clear and avoid oil stains at site areas;
¡P To provide proper storage
areas for chemical; and
¡P To maintain drip trays for chemical storage well.
Landfill
Gas Hazard
¡P ¡§No
Smoking¡¨
and ¡§No
Naked Flame¡¨
notices in Chinese and English should be posted prominently around the
construction site.
Land
Contamination
¡P Stockpiling
site(s) should be lined with impermeable sheeting and bunded.
Stockpiles should be properly covered by impermeable sheeting to reduce dust
emission during dry season or contaminated run-off during rainy season.
Watering should be avoided on stockpiles of soil to minimise
runoff.
Ecology
¡P Properly erect and maintain
2m high solid barriers for protecting Siu Hang San Tsuen Stream.
Permit/
Licences
¡P To display valid Permit or Licences at
the
site entrances.