Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (August 2022) |
ND/2019/01 |
(a)
Site clearance, tree
felling, removal of existing structures, site formation and G.I works at
Portion 1a (b)
Sheet piling, excavation,
backfilling and drainage works at Portion 1b (c)
Site clearance, removal of
existing structures and site formation at Portion 1c and 1e (d)
Site clearance, tree
felling, site formation and contructin of subway at
Portion 2 (e)
Site clearance, excavation,
backfilling and drainage works at Portion 3 (f)
Drainage works, watermain, excavation, backfilling and road work at
Portion 5 (g)
Construction of retaining
wall, drainage works, and backfilling at Portion 6a (h)
Operation of HAC soil
treatment facility at Portion 6b (i)
Site formations, sheet
piling, excavation and drainage works at Portion 7 (j)
Construction of retaining
wall, slope drainage and maintenance access construction, RC construction of
flushing water service reservoir and fresh water service reservoir and
backfilling works at Portion 8a (k)
ELS for jacking pit at LWSC¡¦s
car park and excavation for receiving pit and trenchless work at Portion 8b (l)
Sheet piling, excavation,
drainage works and construction of retaining wall at Portion 9b (m)
Stockpile of soil at
Portion 9c (n)
Excavation, sheet piling
for ELS, drainage works, road works and utilities works at Portion 10a (o)
Sheet piling and excavation
at Portion 10b (p)
Construction of MBR at
Portion 11b |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
and pipe laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut
and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b)
Long
Valley -
Erection
of Permanent Boundary Structure -
Construction
of Irrigation Channel -
Construction
works of Type 1 Storage House -
Construction
works of Type 2 Storage House -
Construction
of Tea House -
Construction
of Decking & Sluices -
Construction
of Composting Facility -
Construction
works of Bird Hide -
Construction
works of Outdoor Classroom -
Wetland
Creation & Restoration works -
Construction
of Compacted Earth Path/ Walkway -
Construction
of Wetland Boardwalk |
ND/2019/04 |
(a)
Tree
felling (b)
Predrill (c)
Bored
piling (d)
Excavation (e)
Sheet
piling and ELS (f)
Pile
cap construction (g)
Drainage
works |
ND/2019/05 |
(a)
The rotary drilling rig is located at B2-02. The
RCD rig located at D2-01. (b)
C1-03 to C2-02 ELS in progress, C4-02 column,
C3-04 pier head, D1-04 pier head and E3-03 SOP cast in-situ are in progress. (c)
TWSR-West sewage and UUs from Ch100 to Ch450
installation works are in progress.Water main to be
commenced while materials on site. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding
at Portion 4 (c)
C&D waste disposal in
Portion 1, 2, 4 and 5 (d)
Drainage works and Sewerage
works at Portion 1, 3 and 4 (e)
Construction of box culvert
in Portion 2 (f)
Filling works in Portion 1,
2 and 4 (g)
Construction of site haul
road in Portion 4 (h)
Waterworks at Portion 1 |