2.1
The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of
land and housing supply in the medium and long term. The development of the KTN
and FLN NDAs will be implemented in phase for full completion by 2031. The
Phase 1 of the NDAs development, comprising the Advance Works and First Stage
Works, is targeted to be implemented from the second half of 2019
progressively. The Advance and First Stage Works would include site formation,
engineering infrastructure works (including roads, drainage, sewerage,
waterworks, landscaping works, pumping stations, and fresh water and flushing
water service reservoirs), soil remediation, reprovisioning of North District
Temporary Wholesale Market, development of a nature park at Long Valley and
implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling
Bypass (FLBP(E)) connecting the FLN NDA to Fanling
Highway and other roads with footpaths and cycle tracks, and associated junction/
road improvements;
iii)
engineering
infrastructure works including drainage. Sewerage (including two sewage pumping stations), waterworks (including a fresh
water service reservoir and a flushing water service reservoir in the KTN NDA),
landscape works and slopeworks;
iv)
part
expansion and upgrading of Shek Wu Hui Sewage
Treatment Works (SWHSTW);
v)
reprovisioning
works; and
vi)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River
for connection between these two facilities;
ii)
reprovisioning
of two egretry sites in the FLN NDA and enhancement
works to an existing egretry site in the KTN NDA;
iii)
site
formation of land for a village resite
area and a district police station in the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds, and
landscape works; and
v)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule
3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October
2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director
of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs
under the Project and the respective Work Contracts are summarized in Table
2.1.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
|
|||||||
Kwu Tung North New
Development Area Road P1 and P2 and Associated New Kwu
Tung Interchange and Pak Shek Au Interchange
Improvement |
ü |
|
|||||||
Kwu Tung North New
Development Area Road D1 to D5 |
ü |
ü |
|
||||||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
ü |
|
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
|
|||||||
Fanling Bypass Eastern
Section |
ü |
ü |
ü |
|
|||||
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
ü |
|
|||||||
EP-546/2017 |
Fanling North Temporary
Sewage Pumping Station |
ü |
|
Note:
C1: ND/2019/01 C2: ND/2019/02 C3: ND/2019/03 C5A:
ND/2019/04
C5B:
ND/2019/05 C6: ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of scope of works under
concerned EP
Environmental Permit (EP)
No. |
Work Contract(s) |
Scope of Works under
concerned EP(s) |
Site Layout Plan under
concerned EP(s) |
EP-466/2013(Part) |
C1 |
Realign Castle Peak Road and join with the Pak Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road (P1)
within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor roads (D1,
D3, D4 and part of D5) within Kwu Tung North New
Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley and
ecological mitigation and enhancement works for the nature park (Condition
2.9) |
Figure 15 |
|
EP-469/2013 |
C2 |
Construction of one sewage pumping station in Kwu Tung North with installed capacity of more than 2,000
m3 per day |
Figure 16 |
EP-470/2013 |
C1 |
Construction of service reservoir and watermain
for the reuse of treated sewage effluent for reuse in Kwu
Tung North Development Areas |
Figure 17 |
EP-473/2013/A |
C3 |
Establishment of alternative egretry sites and enhance
the existing egretry site at Ho Sheung Heung and/or
its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A |
C5A |
Construction of new district distributor inside
FLN NDA, which provides a linkage between the Man Kam To
Road and the proposed Fanling Bypass Eastern
Section |
Figure 19 |
EP-473/2013/A |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will have
approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage pumping
station in Fanling North with installed capacity
(average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remarks: The EP(s) not related to the Project of
First Phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) Development
Areas are not included in the Table.
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
The
required submissions and submission status under Environmental Permits are
shown in Appendix U.
2.6
The
site Layout Plan under concerned Environmental Permits are shown in Figure
12 - 22.
2.7
Different
parties with different levels of involvement in the Project organization
include:
Project Proponent – Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative – AECOM
Environmental Team (ET) – Wellab Limited
Independent Environmental Checker
(IEC) – Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
key personnel contact names and numbers are summarised
in Table 2.2
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax
No. |
Civil Engineering and
Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Felix Fan |
3152 3551 |
3547
1658 |
Supervisor / Supervisor's Representative (AECOM) |
Chief Resident Engineer |
Mr. Alan Lee |
6398
5982 |
2645
3900 |
Environmental Team (Wellab
Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898
7388 |
2898 7076 |
Independent
Environmental Checker (MottMac) |
Independent Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract No. ND/2019/01 Contractor
(Build King – Richwell Engineering Joint Venture) |
Site Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr. Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor
(Chun Wo – Kwan Lee Joint Venture.) |
Site Agent |
Mr. Andy Chan |
3485 9780 |
-- |
Environmental Officer |
Ms. Suchi
Law |
6679 6800 |
||
Contract No. ND/2019/03 Contractor
(Sang Hing Kuly Joint Venture) |
Site Agent |
Mr. Tang Wing Kai |
9300 7037 |
-- |
Environmental Officer |
Mr. Jackey Tam |
6742 5596 |
||
Contract No. ND/2019/04 Contractor
(Daewoo – Chun Wo – Kwan Lee Joint Venture) |
Site Agent |
Mr. Bear Ding |
6483 6198 |
-- |
Environmental Officer |
Ms. Donna Tso |
9283 7167 |
||
Environmental Supervisor |
Ms. Peggie Hon |
9714 3308 |
||
Contract No. ND/2019/05 Contractor
(CRCC – Paul Y. Joint Venture) |
Site Agent |
Mr. Darvin Lo |
9467 5891 |
-- |
Environmental Manager |
Mr. Pan Fong |
9436 9435 |
||
Environmental Officer |
Ms. Louise Poon |
5272 5709 |
||
Contract No. ND/2019/06 Contractor
(New Concepts Engineering Development Ltd.) |
Site Agent |
Mr. Anson Chan |
9349 1320 |
2363 2162 |
Environmental Officer |
Mr. Alex Choy |
9409 9608 |
||
Environmental Coordinator |
Ms. Gloria Wong |
64398946 |
||
Contract No. ND/2019/07 Contractor
(China Road and Bridge Corporation) |
Site Agent |
Mr. Daniel Wong |
5335 9572 |
-- |
Environmental Officer |
Mr. K. M. Lui |
5113 8223 |
||
Environmental Supervisor |
Mr. Attlee Chau |
6386 9018 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (April 2022) |
ND/2019/01 |
(a)
Site clearance, tree felling, demolition of existing structures and
site formation works in Portion 1a (b)
Sheet piling, excavation, tree felling, backfilling, drainage and demolition of existing structures in Portion
1b (c)
Site clearance, demolition of existing structures in Portion 1c (d)
Site clearance, demolition of existing structures in Portion 1e (e)
Site clearance, tree felling, temporary road construction and
site formation works in Portion 2 (f)
Site clearance, excavation, backfilling in Portion 3 (g)
Site clearance, sheet piling, excavation, drainage works,
watermain, backfill and road work in Portion 5 (h)
Site
clearance, drainage works, backfill and retaining wall KB01 construction in
Portion 6a (i)
Operation
of HAC soil treatment facility in Portion 6b (j)
Site clearance, sheet piling and excavation, drainage works and
site formation works in Portion 7 (k)
Construction of retaining wall, slope cutting, slope drainage and
maintenance access construction, RC construction of flushing water service
reservoir and fresh water service reservoir, GI works in Portion 8a (l)
Site clearance, excavation for jacking pit at LWSC’s car park, sheet piling for
receiving pit in Portion 8b (m)
Sheet piling and excavation, drainage works in Portion 9b (n)
Stockpile of soil and excavation in Portion 9c (o)
Excavation, sheet piling for ELS, drainage works and road work,
utilities works in Portion 10a (p)
Sheet piling
and excavation in Portion 10b (q)
Construction of MBR in Portion 11b (r)
Construction of temporary sewage pumping station in Portion 14 (s)
Construction of CLC in Portion 16 |
ND/2019/02 |
(a)
Sheet Pile Installation (b)
Concreting (c)
Sheet Pile Installation (d)
ELS (e)
Pipe Jacking |
ND/2019/03 |
(a) Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b) Long
Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Bund / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Tree felling (b)
Predrill (c)
Bored piling (d)
Excavation (e)
Sheet piling and ELS |
ND/2019/05 |
(a)
The pre-drilling was in-prgoress
at the B2 bridge in Portion III. (b)
The rotary drilling rigs, one is located at C2-02
and C2-03. The second is located at C3-02. (c)
The RCD rig is located at E2-01 and another RCD rig
located at D2-03. (d)
C4-01 Portal Beam, C4-03 cross head are in
progress, E2-02 and E3-03 SOP cast in-situ will start on the end of Apr. (a)
TWSR-East drainage and watermain from Ch100 to
Ch250 install works are in progress. |
ND/2019/06 |
(a)
Installation of the main gate at Portion 5 has been completed. (b)
Re-construction of part of carriageway and kerb
for flag pole at Portion 3 has been completed. (c)
Removal of temporary ramp at carpark hat Portion 3 has been
completed. (d)
Remedial works for grasscrete at
Portion 6 has been completed. (e)
Remedial works for finishing of painting at MOB at Portion 4 are
in progress. |
ND/2019/07 |
(a)
Site clearance at Portion 2 and 4 (b)
Erection of site hoarding at Portion 2 and 4 (c)
C&D waste disposal in Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 and 5 (e)
Drainage works and Sewerage works at Portion 1, 3 and 4 (f)
Construction of box culvert in Portion 2 (g)
Filling works in Portion 1, 2 and 4 (h)
Tree felling / Disposal of yard waste in Portion 4 (i)
Construction of site haul road in Portion 4 |
2.10
A
copy of Contractors’ construction programme is
provided in Appendix A.
2.11
A
summary of the relevant permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.4.
Table 2.4 Status
of Environmental Licenses, Notifications and Permits
Contract No. |
Permit / License No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental
Permit (EP) |
||||
ND/2019/01 |
EP-466/2013 |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013 |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
|
ND/2019/04 |
EP/473/2013/A |
27/01/2017 |
N/A |
Valid |
EP/546/2017 |
16/11/2017 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction Noise
Permit (CNP) |
||||
ND/2019/01 |
GW-RN0036-22 |
23/01/2022 |
16/07/2022 |
Valid |
|
GW-RN0975-21 |
08/01/2022 |
07/04/2022 |
Expired
in the reporting month |
|
GW-RN0172-22 |
25/03/2022 |
24/09/2022 |
Valid |
|
GW-RN0173-22 |
08/03/2022 |
07/09/2022 |
Valid |
|
GW-RN0285-22 |
08/04/2022 |
07/10/2022 |
Valid |
ND/2019/02 |
GW-RN0047-22 |
01/02/2022 |
31/07/2022 |
Valid |
ND/2019/03 |
GW-RN0055-22 |
01/03/2022 |
31/08/2022 |
Valid |
ND/2019/04 |
GW-RN0764-21 |
28/10/2021 |
27/04/2022 |
Expired
in the reporting month |
|
GW-RN0162-22 |
03/03/2022 |
02/06/2022 |
Valid |
ND/2019/05 |
GW-RN0782-21 |
27/10/2021 |
26/04/2022 |
Expired
in the reporting month |
|
GW-RN0096-22 |
14/02/2022 |
13/05/2022 |
Valid |
|
GW-RN0095-22 |
11/02/2022 |
10/05/2022 |
Valid |
|
GW-RN0222-22 |
30/03/2022 |
29/06/2022 |
Valid |
|
GW-RN0316-22 |
28/04/2022 |
27/07/2022 |
Valid |
ND/2019/06 |
GW-RN0054-22 |
13/02/2022 |
12/08/2022 |
Valid |
Notification pursuant
to Air Pollution Control (Construction Dust)
Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/04 |
461184 |
23/10/2020 |
N/A |
Valid |
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
ND/2019/07 |
459393 |
28/08/2020 |
N/A |
Valid |
Billing Account for
Disposal of Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/04 |
7038391 |
22/09/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
ND/2019/07 |
7038309 |
14/09/2020 |
N/A |
Valid |
Registration
of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/04 |
5211-624-D2709-01 |
26/11/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
ND/2019/07 |
5213-625-C4498-01 |
21/09/2020 |
N/A |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00037191-2020 |
21/04/2022 |
28/02/2026 |
Valid |
|
WT00037204-2020 |
02/02/2021 |
28/02/2025 |
Valid |
|
WT00037412-2021 |
15/04/2021 |
30/04/2026 |
Valid |
|
WT00037564-2021 |
19/04/2021 |
30/04/2026 |
Valid |
|
WT00037886-2021 |
28/06/2021 |
30/06/2026 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
WT00036952-2020 |
17/12/2020 |
31/12/2025 |
Valid |
|
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
WT00036414-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
WT00037771-2021 |
08/07/2021 |
31/07/2026 |
Valid |
|
WT00035984-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
ND/2019/04 |
WT00037539-2021 |
16/04/2021 |
30/04/2026 |
Valid |
ND/2019/05 |
WT00036996-2020 |
22/12/2020 |
31/12/2025 |
Valid |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |
ND/2019/07 |
WT00037526-2021 |
04/05/2021 |
31/05/2026 |
Valid |