Table IV Summary Table for Site Activities in the coming Two Months
Contract No. |
Site Activities (May 2022 and June
2022) |
ND/2019/01 |
(a)
Site Clearance, remove of existing structures and tree felling in
Portion 1a (b)
Site clearance, backfilling, ground investigation, sheet piling, excavation and drainage in Portion 1b (c)
Site clearance, demolition of existing structures in Portion 1c (d)
Site Clearance and tree felling in Portion 1e (e)
Site clearance, tree felling, temporary road construction and
site formation work in Portion 2 (f)
Site clearance, backfilling, excavation
and tree felling in
Portion 3 (g)
Site clearance, sheet piling and excavation, drainage works,
temporary road construction and watermain in Portion 5 (h)
Site
Clearance, sheet piling and excavation, pipes laying, backfilling,
construction of KB01 retaining wall, haul road construction in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
clearance, sheetpiling and excavation, pipes laying in Portion 7 (k)
Construction
of retaining Wall, slope cutting, slope drainage and maintenance access
construction, RC construction of flushing water service reservoir and fresh
water reservoir, water service reservoir and fresh water reservoir, GI works,
pipe pile wall of WSD’s maintenance access in Portion 8a (l)
Sheet
piling for receiving pit, trenchless works, excavation, ELS for jacking pit
at LWSC’s car park in Portion 8b (m)
Sheet piling and excavation, pipes laying,
demolition of existing structures, GI works in Portion 9b (n)
Stockpile
of soil and excavation in Portion 9c (o)
Excavation,
sheetpiling for ELS, drainage works, road construction and utilities laying in
Portion 10a (p)
Sheetpiling
and excavation, drainage works in Portion 10b (q)
Construction of MBR at 11b (r)
Construction of temporary sewage pumping station in Portion 14 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
ELS (c)
Concreting (d)
Backfilling (e)
Sheet
Pile Installation (f)
Bedding
and Pipe Laying (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b) Long Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Path / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Tree felling (b)
Predrill (c)
Bored piling (d)
Excavation (e)
Sheet piling (f)
ELS |
ND/2019/05 |
(a)
North Team Works -
Pre-drilling for bored piles at B2-01-P3,
B2-03-P3, P5, P6 -
Bored piling at B1&B2(Portion II), C1(Portion
II), C2-02, C2-03a, C2-03b, C3-02, D2-01 & E2-01. -
ELS and Pile cap construction at C1-02b, C1-03,
C2-01, C2-04a, C3-01a, C3-02, C3-04b, C3-04a, D1-02 & E2-01 -
C3-03 & C3-04 Portal Beam -
Piling platform & haul road construction from
B2-03 to C1-02a at Portion II -
Raft footing construction at C4-02 -
Pier construction at C3-03a, C3-04ab, C4-02,
D1-01, E1-01, D1-02, D1-03, E1-03, D1-04 &E1-04. (b)
Viaduct Works -
Segment fabrication for bridge C4 & C3 &
D1 & E1. -
MJSOP erection at Pier C4-04 a/b M -
Launching Girder (LG) delivery to site. -
LG pre-assembly between pier C4-03 to C4-04a/bM. -
Cast in-situ SOP construction at Pier E2-02,
E3-03. -
1st set Form Traveler (FT) fabrication and
delivery. Target to deliver in Apr-2022. -
2nd set FT fabrication and delivery. Target to
deliver in May-2022. -
3rd set FT design and fabrication. To be used in
Feb-2023. -
4th set FT design and fabrication. To be used in
May-2023. -
Bridge rotation system fabrication1. (c)
South Team Works -
Venton Area – Telecom ducts laying. -
Portion 13 – Twin DN1200 storm drain
construction. Backfill FW 52 bay 1 to bay 3. -
Portion 17 and 18 – Construction of DN 600 and
DN450 sewer. RW 52 bay 4 and 5 -
Portion 18 – 132kv ducts laying and Gas main laying. -
TWSR (West) – RW06 construction and FS04 slope
works. -
HKY FB (East) – construction of P01 -
Portion 11 – DN1200 and DN600 watermain laying
work. -
E2-03 – Pile cap construction. -
E3-01 – Pier construction. -
D2-02 – Reinstatement of Retaining wall and river
slab. Pier construction. -
D2-03 – ELS and cap construction. -
E3-04a – Piling works. |
ND/2019/06 |
(a)
Remedial works for finishing of painting at MOB at Portion 4. (b)
Installation of handrails at MOB at Portion 4. (c)
Grating installation at Portion 3. (d)
Road marking at carpark after removal of temporary ramp at
Portion 3. (e)
Installation of signage of the market at Portion 3. |
ND/2019/07 |
(a)
Site clearance at Portion 4 (b)
Erection of site hoarding at Portion 3, 4 (c)
C&D waste disposal at Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 (e)
Construction of box culvert at Portion 2 (f)
Filling works at Portion 1, 2 and 4 (g)
Tree felling/ Disposal of yard waste at Portion 4 (h)
Construction of site haul road at Portion 4, 5 (i)
Drainage works and sewage works at Portion 1, 3,
4 and 5 (j)
Mini piling works at Portion 4 and 5 (k)
Construction of noise barrier at Portion 5 |