Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (April 2022) |
ND/2019/01 |
(a)
Site clearance, tree felling, demolition of existing structures and
site formation works in Portion 1a (b)
Sheet piling, excavation, tree felling, backfilling, drainage and demolition of existing structures in Portion
1b (c)
Site clearance, demolition of existing structures in Portion 1c (d)
Site clearance, demolition of existing structures in Portion 1e (e)
Site clearance, tree felling, temporary road construction and
site formation works in Portion 2 (f)
Site clearance, excavation, backfilling in Portion 3 (g)
Site clearance, sheet piling, excavation, drainage works,
watermain, backfill and road work in Portion 5 (h)
Site
clearance, drainage works, backfill and retaining wall KB01 construction in
Portion 6a (i)
Operation
of HAC soil treatment facility in Portion 6b (j)
Site clearance, sheet piling and excavation, drainage works and
site formation works in Portion 7 (k)
Construction of retaining wall, slope cutting, slope drainage and
maintenance access construction, RC construction of flushing water service
reservoir and fresh water service reservoir, GI works in Portion 8a (l)
Site clearance, excavation for jacking pit at LWSC’s car park, sheet piling for
receiving pit in Portion 8b (m)
Sheet piling and excavation, drainage works in Portion 9b (n)
Stockpile of soil and excavation in Portion 9c (o)
Excavation, sheet piling for ELS, drainage works and road work,
utilities works in Portion 10a (p)
Sheet piling
and excavation in Portion 10b (q)
Construction of MBR in Portion 11b (r)
Construction of temporary sewage pumping station in Portion 14 (s)
Construction of CLC in Portion 16 |
ND/2019/02 |
(a)
Sheet Pile Installation (b)
Concreting (c)
Sheet Pile Installation (d)
ELS (e)
Pipe Jacking |
ND/2019/03 |
(a) Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road -
Construction
of Pai Lau (b) Long
Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Bund / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Wetland Boardwalk -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Tree felling (b)
Predrill (c)
Bored piling (d)
Excavation (e)
Sheet piling and ELS |
ND/2019/05 |
(a)
The pre-drilling was in-prgoress
at the B2 bridge in Portion III. (b)
The rotary drilling rigs, one is located at C2-02
and C2-03. The second is located at C3-02. (c)
The RCD rig is located at E2-01 and another RCD rig
located at D2-03. (d)
C4-01 Portal Beam, C4-03 cross head are in
progress, E2-02 and E3-03 SOP cast in-situ will start on the end of Apr. (a)
TWSR-East drainage and watermain from Ch100 to
Ch250 install works are in progress. |
ND/2019/06 |
(a)
Installation of the main gate at Portion 5 has been completed. (b)
Re-construction of part of carriageway and kerb
for flag pole at Portion 3 has been completed. (c)
Removal of temporary ramp at carpark hat Portion 3 has been
completed. (d)
Remedial works for grasscrete at
Portion 6 has been completed. (e)
Remedial works for finishing of painting at MOB at Portion 4 are
in progress. |
ND/2019/07 |
(a)
Site clearance at Portion 2 and 4 (b)
Erection of site hoarding at Portion 2 and 4 (c)
C&D waste disposal in Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 and 5 (e)
Drainage works and Sewerage works at Portion 1, 3 and 4 (f)
Construction of box culvert in Portion 2 (g)
Filling works in Portion 1, 2 and 4 (h)
Tree felling / Disposal of yard waste in Portion 4 (i)
Construction of site haul road in Portion 4 |