13.1
This Monthly
EM&A Report presents the EM&A work undertaken in October 2021 in accordance with Updated EM&A Manual.
13.2 No Action/Limit Level exceedance were recorded for air quality,
construction noise, additional water quality monitoring, ambient arsenic and landfill gas monitoring in the reporting month
Contract No.
ND/2019/01
13.3
Environmental
site inspection were conducted on 5, 12, 19 and 25 October 2021 by
ET in the reporting month.
Contract No. ND/2019/02
13.4
Environmental
site inspection were conducted on 6, 12, 22 and 27 October 2021 by
ET in the reporting month.
Contract No.
ND/2019/03
13.5
Environmental
site inspection were conducted on 8, 15, 19 and 29 October 2021 by
ET in the reporting month.
Contract No.
ND/2019/04
13.6
Environmental
site inspection were conducted on 7, 15, 22 and 28 October 2021 by
ET in the reporting month.
Contract No. ND/2019/05
13.7
Environmental
site inspections were conducted on 4,
15, 18 and 25 October 2021 by
ET in the reporting month.
Contract No.
ND/2019/06
13.8
Environmental
site inspections were conducted on 7,
15, 18 and 28 October 2021 by ET in the reporting month.
Contract No.
ND/2019/07
13.9
Environmental
site inspections were conducted on 8,
15, 19, and 29 October 2021 by ET in the reporting month.
13.10 There were no
environmental complaint, no notification of summons or successful prosecutions
received in the reporting month.
13.11 The ET would keep track on the
EM&A programme to ensure compliance of
environmental requirements and the proper implementation of all necessary
mitigation measures.
13.12 According to the environmental audits performed in the reporting
month, the following recommendations were made:
Air Quality Impact
· To regular watering haul road;
· To provide vehicle washing
facilities with high pressure water jet at every discernible or designated vehicle
exit point;
· To maintain the impervious material to entirely cover the stockpile
of dusty materials; and
· To ensure all regulated machines displayed with valid Non-road Mobile Machinery (NRMM) labels.
Construction Noise Impact
· To ensure compressor was operating
with doors closed.
Water Impact
· To review and implement temporary
drainage system;
· To prevent any surface runoff
discharge into Sheung Yuen River, Ma Wat River or public
road;
· To provide sandbags or construct berm to prevent any outflow of
muddy water from site area;
· To ensure all vehicle clear of earth
and mud before leaving site;
· To ensure the drainage facilities would not be clogged with waste or
sediment to avoid overflow;
· To regularly check the condition of desilting materials for
ensuring proper function;
· To regularly maintain and ensure
water treatment facilities proper operation and functioning;
· To divert all the water generated from construction site to
de-silting facilities with sufficient handling capacity before discharge; and
· To avoid or regularly clear the stagnant water in
drip tray;
Waste/Chemical Management
· To dispose of general refuse properly;
· To clear and avoid the oil stain at site area;
· To provide proper storage area for chemical storage; and
· To maintain drip tray for chemical storage well.
Landfill Gas Hazard
· “No Smoking” and “No Naked Flame” notices in Chinese and English should be posted prominently around the
construction site.
Land Contamination
· Stockpiling site(s) should be lined with
impermeable sheeting and bunded. Stockpiles should be properly covered by
impermeable sheeting to reduce dust emission during dry season or contaminated
run-off during rainy season. Watering should be avoided on stockpiles of soil
to minimize runoff.
Ecology
· Properly erect and maintain 2m high solid barriers for protecting
Siu Hang San Tsuen Stream.
Permit/ Licences
· To display valid Permit or Licences on
site entrance.