10.1
Site
audits were carried out by ET on weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures on the Contract site. The
summaries of site audits are presented in Table 10.1 and Appendix P.
Table 10.1 Summary
of Site Audit
Environmental Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly site audit with representative of the Supervisor’s
Representative and the Contractor |
5, 12, 19 and 25 Oct 21 |
6, 12, 22 and 27 Oct 21 |
8, 15, 19 and 29 Oct 21 |
7, 15, 22 and 28 Oct 21 |
4, 15, 18 and 25 Oct 21 |
7, 15, 18 and 28 Oct 21 |
8, 15, 19, and 29 Oct 21 |
Joint Site Audit with representative of the Supervisor’s
Representative, the Contractor and IEC |
25 Oct 21 |
22 Oct 21 |
19 Oct 21 |
22 Oct 21 |
15 Oct 21 |
18 Oct 21 |
19 Oct 21 |
10.2
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarised in Table 10.2.
Table 10.2 Observations and Recommendations during
Site Audits
|
Date |
Observations
and Recommendations |
Follow-up |
Contract No.: ND/2019/01 |
|||
Waste/ Chemical Management |
5/10/2021 |
Drip trays should be provided for chemical
storage. |
Improvement/Rectification
was observed during follow-up audit session on 12 October 2021. |
Contract No.: ND/2019/02 |
|||
Air Quality |
22/10/2021 |
Dusty haul road should be watered regularly. |
Improvement/Rectification
was observed during follow-up audit session on 27 October 2021. |
Water Quality |
29/9/2021 |
Contractor was reminded to provide sandbags along the cycle track to
prevent muddy water flow offsite. (North Bridge) |
Improvement/Rectification
was observed during follow-up audit session on 6 October 2021. |
29/9/2021 |
To
remove general refuse inside the drainage. |
Improvement/Rectification
was observed during follow-up audit session on 6 October 2021. |
|
29/9/2021 |
To
provide wheel washing facilities at every site exit. (South Bridge) |
Improvement/Rectification
was observed during follow-up audit session on 6 October 2021. |
|
29/9/2021 |
Clear
the stagnant muddy water and provide sufficient wastewater treatment before
discharge. |
Improvement/Rectification
was observed during follow-up audit session on 6 October 2021. |
|
6/10/2021 |
Clear the stagnant muddy water and provide
sufficient wastewater treatment before discharge. (North bridge) |
Improvement/Rectification
was observed during follow-up audit session on 12 October 2021. |
|
6/10/2021 |
Clear the sediment and stagnant water in the U-channel and provide
sufficient wastewater treatment before discharge. (South bridge) |
Improvement/Rectification
was observed during follow-up audit session on 12 October 2021. |
|
12/10/2021 |
To
clear the stagnant water in drip tray. |
Improvement/Rectification
was observed during follow-up audit session on 22 October 2021. |
|
Contract No.: ND/2019/03 |
|||
Waste/ Chemical Management |
30/9/2021 |
Clear the rubbish at near the storage area to 巨賓. |
Item
was remarked as 211008-R01. Follow-up action is needed to be reviewed. |
8/10/2021 |
Clear the rubbish at near the storage area to 巨賓. |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2021. |
|
Contract No.: ND/2019/04 |
|||
Air Quality |
30/9/2021 |
To replace the faded NRMM Label for the air
compressor. |
Improvement/Rectification
was observed during follow-up audit session on 7 October 2021. |
Water Quality |
30/9/2021 |
Properly erect and maintain the desilting
materials along green barriers at Bridge A2. |
Improvement/Rectification
was observed during follow-up audit session on 7 October 2021. |
30/9/2021 |
Regularly
clear the U-channel and provide desilting materials as sediment control
measure at Bridge A2 and Portion H. |
Item
was remarked as 211007-O03. Follow-up action is needed to be reviewed. |
|
30/9/2021 |
Regularly
clear the U-channel and provide the desilting materials as a sediment control
measure at Bridge F. |
Improvement/Rectification
was observed during follow-up audit session on 7 October 2021. |
|
7/10/2021 |
Regularly
clear the U-channel and provide desilting materials as sediment control
measure at Bridge A2 and Portion H. |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2021. |
|
7/10/2021 |
Regularly clear the U-channel and provide the
desilting materials as a sediment control measure at Portion E. |
Item
was remarked as 211015-O01. Follow-up action is needed to be reviewed. |
|
15/10/2021 |
To ensure sediment in U-Channel was cleared
regularly and avoid accumulation. |
Improvement/Rectification
was observed during follow-up audit session on 22 October 2021. |
|
22/10/2021 |
To
provide desilting materials at U-Channel. |
Improvement/Rectification
was observed during follow-up audit session on 28 October 2021. |
|
Waste/Chemical Management |
30/9/2021 |
To avoid oil leakage from drip tray at Bridge A3. |
Item
was remarked as 211007-O01. Follow-up action is needed to be reviewed. |
30/9/2021 |
Drip tray should be provided for chemical
storage. |
Item
was remarked as 211007-O02. Follow-up action is needed to be reviewed. |
|
7/10/2021 |
To avoid oil leakage from drip tray at Bridge A3. |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2021. |
|
7/10/2021 |
Drip tray should be provided for chemical
storage. |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2021. |
|
15/10/2021 |
Oil, grease and litters were observed in the
water of nearby drainage at Portion H, Contractor was reminded to avoid any
foam, oil, grease or litter in any watercourse. |
Improvement/Rectification
was observed during follow-up audit session on 22 October 2021. |
|
22/10/2021 |
Drip tray should be provided for chemical
storage. |
Improvement/Rectification
was observed during follow-up audit session on 28 October 2021. |
|
22/10/2021 |
To clear the oil stain at temporary drainage. |
Improvement/Rectification
was observed during follow-up audit session on 28 October 2021. |
|
28/10/2021 |
Drip tray should be provided for chemical
storage. |
Follow-up
action is needed to be reported in the following month. |
|
28/10/2021 |
To avoid oil leakage during maintenance. |
Follow-up
action is needed to be reported in the following month. |
|
Construction Noise Impact |
22/10/2021 |
Compressor should be operated with doors closed. |
Improvement/Rectification
was observed during follow-up audit session on 28 October 2021. |
Ecology |
30/9/2021 |
Properly erect and maintain 2m high solid
barriers for lower reaches of Siu Hang San Tsuen Stream. |
Improvement/Rectification
was observed during follow-up audit session on 7 October 2021. |
Permit / Licences |
28/10/2021 |
To display valid Construction Noise Permit at
site entrance. |
Follow-up
action is needed to be reported in the following month. |
Contract No.: ND/2019/05 |
|||
Air Quality |
4/10/2021 |
Faded NRMM Labels shall be replaced on regulated machines. |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2021. |
15/10/2021 |
Display valid NRMM Labels on regulated machine. |
Improvement/Rectification
was observed during follow-up audit session on 18 October 2021. |
|
15/10/2021 |
Stockpile should be covered properly by imperious
sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 18 October 2021. |
|
Water Quality |
4/10/2021 |
Desilting materials should be provided along the
site barriers to prevent surface runoff to Ma Wat River. |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2021. |
4/10/2021 |
Desilting materials should be provided along the
site barriers to prevent surface runoff to On Kui
Street. |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2021. |
|
25/10/2021 |
Enhance mitigation measures to prevent surface
runoff to Ma Wat River. |
Follow-up
action is needed to be reported in the following month. |
|
Waste / Chemical Management |
15/10/2021 |
Remove the stagnant water in the drip tray. |
Improvement/Rectification
was observed during follow-up audit session on 18 October 2021. |
Contract No.: ND/2019/06 |
|||
Air Quality |
30/9/2021 |
Dusty stockpile should be covered by impervious
sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 7 October 2021. |
28/10/2021 |
The exposed worksite and haul road should be
watered regularly. |
Follow-up
action is needed to be reported in the following month. |
|
28/10/2021 |
Wheel washing facilities should be available at
every designated vehicle exit point. |
Follow-up
action is needed to be reported in the following month. |
|
Contract No.: ND/2019/07 |
|||
-- |
-- |
-- |
-- |
10.3
According
to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
Q. The photographic records of measures as stipulated in EP to mitigate
environmental impacts in the reporting month are presented in Table 10.3.
Table 10.3 Photographic Records and Implementation
Status of Measures
EP No. |
Condition |
Photographic Record |
Implementation Status |
EP-466/2013 |
2.9 |
To
minimise adverse impacts on habitats of ecological imprtance in the vicinity of the Project, 2m high solid
dull green site barrier fences shall be erected around all active works
areas.(Figure 12) |
^[1] |
EP-468/2013/A |
2.11 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 14) |
^[1] |
EP-469/2013 |
2.7 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 15) |
^[1] |
EP-473/2013/A |
2.13 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 16) |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 17) |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance of mitigation measure · Non-compliance
but rectified by the contractor N/A Not
Applicable at this stage as no such site activities were conducted in the
reporting period |
[1]: Barrier fences might be subjected to
change according to phasing plan designed at detailed design stage
10.4
Under
EP-467/2013/A (Condition 2.9), to minimise adverse
impacts on habitats of ecological importance in the vicinity of the Project, 2m
high solid dull green site barrier fences shall be erected around all active
works areas. As the Works programme under above EPs
were still under preparation work and the
barrier fences erection was still progressing in the Reporting Month, 2m high
solid dull green site barrier fences will be checked once in place. The
Hoarding Plan of the above EPs is shown in Figure
13.
10.5
According
to the EIA Report and the Updated EM&A Manual, the water quality mitigation
measures detailed in the documents are recommended to be implemented during the
construction phase. Water quality mitigation measures implemented by the
contractors were closely monitored to prevent water pollution, especially during
rainy season. An updated summary of the Environmental Mitigation Implementation
Schedule is provided in Appendix Q. Specific
water quality mitigation measures for major construction works in the reporting
month are presented in Table 10.4.
Table 10.4 Specific Water Quality Mitigation Measures for Major
Construction Works in the Reporting Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Hydroseeding for slope
area |
ND/2019/02 |
Hard paved exposed
slope surface |
Temporary ditches to direct storm water to wastewater treatment
facilities |
ND/2019/03 |
Wastewater from wheel
washing was directed to wastewater treatment facility |
Regular clearance of
water for wheel washing facility |
ND/2019/04 |
Surface channels and earth bunds to direct
storm water to wastewater treatment facilities for works area near Siu Hang
San Tsuen Stream |
Deployment of silt curtain around works area in Ng Tung Rive |
ND/2019/05 |
Provision of sand
bags around works area |
Temporary ditches to direct
storm water to wastewater treatment facilities |
ND/2019/06 |
Grasscrete for slope protection |
Provision of concrete berm around site area |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
Temporary rainwater storage area for
rainstorm event |
10.6
Waste generated
from Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06
and ND/2019/07 include inert construction and demolition (C&D) materials
and non-inert C&D wastes in the Reporting Month.
10.7
The amount of
wastes generated by the construction works of the Contract
No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and
ND/2019/07 during the
reporting month are shown in Appendix R.
10.8
The
Contractors are advised to minimize the wastes generated through recycling or
reusing. All mitigation measures stipulated in the Updated EM&A Manual and
waste management plans shall be fully implemented. The status of implementation
of waste management and reduction measures are summited in Appendix Q.
10.9
From
the findings of EIA Report, the area of Long Valley has been assessed as of
high to very high ecological value and is the largest contiguous area of
freshwater wetland habitats in Hong Kong. To safeguard the ecological value of
Long Valley, about 37 hectares of land in Long Valley has been proposed to
develop into Long Valley Nature Park (LVNP) for conserving and enhancing the
ecologically important environment as well as for compensation of the wetland
loss due to the NDA development.
10.10
LVNP is developed according to approved
Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. The
HCMP provides a framework and specifications for development and management of
the LVNP and guides the development to maintain and enhance the 37ha of low-lying
wetland habitats.
10.11
Regarding
to the design, the zoning of land use in the LVNP is intended to maintain the
existing mosaic pattern of wet and dry agriculture, while controlling the
activities that could potentially disturb target habitats and species. The LVNP
will divide into three broad zones of land use as below:
•
Biodiversity
Zone of about 21 hectares largely designated for biodiversity conservation
through cultivation of specified crops and habitat management.
•
Agricultural
Zone of about 11 hectares designated for commercially focuses crop production
and eco-friendly agricultural practice for farming.
•
Visitor
Zone of about 5 hectares designed to accommodate visitors as well as storage
and other facilities and for educational purposes.
10.12
The
construction of the LVNP started in late 2019 and is expected to be completed
in 2023. During construction period, the progress of construction and wetland
enhancement works are under observation by different stakeholders including
AFCD and green groups. Close communication between AFCD and CEDD are conducted
to exchange views on conservation, restoration and management of habitats as
well as on the planning and design of the park. Also, advices from green
groups, Hong Kong Bird Watching Society (HKBWS) and The Conservancy Association
(CA), are taken on habitat management of Long Valley and potential effects on
habitat and wildlife of each individual work conducted in Long Valley. Regular
meeting are held monthly on 29th October 2021 in the reporting month
to share the progress of LVNP with different stakeholders, including CEDD,
AFCD, CA, HKBWS, Contractor, ET, IEC and farmers.
10.13 Proposals on wetland creation and
restoration, dry agricultural land creation, pond creation, water treatment
wetland and design of irrigation channel are submitted by the Contractor to
achieve the objectives stated in HCMP and accepted by the Engineer with consent
from AFCD before implementation. The Contractor will consult with the
stakeholders for recommendations and suggestions on mitigation measures to minimise the environmental impacts arising from
construction works. The progress of works will be arranged to minimise impacts to avifauna and maintain the habitat for
avifauna. The photographic records of site activities in LVNP are presented in Table 10.5.
Table 10.5 Photographic
Records of Site Activities in LVNP
Agricultural practice are continued in
existing farmland to maintain habitats in Long Valley |
|||
Lotus
pond |
Open
water Habitat |
Chinese
arrowhead pond |
|
Creation of wetland with designated
habitat for biodiversity conservation |
|||
Planting of paddy rice to provide
foraging ground for Yellow-breasted Bunting |
|||
Retention of washing bay for amphibians
breeding |
Enhancement of irrigation channel
to provide reliable water source for farmland in Long Valley |
||
Provision of bird island (hidden area) |
Restoring of water flea pond to provide
food source to water birds |
||
Construction of storage sheds for farmers |
a Elanus caerileus was
recorded |
||
Provision of wastewater treatment
facilities |
Provision of noise barrier for noisy
works in Long Valley |
||