Table IV       Summary Table for Site Activities in the coming Two Months

Contract No.

Site Activities (November 2021 and December 2021)

ND/2019/01

 

(a)          Site Clearance and remove of existing structure in Portion 1a

(b)         Site clearance, ground investigation in Portion 1b

(c)          Site Clearance and remove of existing structure in Portion 1e

(d)         Site clearance, ground investigation, tree felling and temporary road construction in Portion 2

(e)          Site clearance, backfilling, excavation and tree felling in Portion 3

(f)          Site clearance, stockpile of soil, construction of KW01 retaining wall, sheetpiling and excavation, drainage works, tree felling, backfilling and temporary road construction in Portion 5

(g)         Site Clearance, sheetpiling and excavation, pipes laying, backfilling, construction of KW01 retaining wall, construction of KB01 retaining wall, and haul road construction in Portion 6a

(h)         Operation of HAC treatment facility in Portion 6b

(i)           Site clearance, sheetpiling and excavation, pipes laying and construction of APLR in Portion 7

(j)           Construction of retaining wall, slope cutting, soil nailing, slope drainage and maintenance access construction, excavation for Fresh Water Service Reservoir, RC construction of Flushing Water Service Reservoir in Portion 8a

(k)         Sheetpiling for receiving pit, trenchless works, Sub soil drain, excavation, EGI, drill and grouting for jacking pit and site clearance in Portion 8b

(l)           Sheetpiling and excavation, pipes laying, GI works and demolition of existing structures in Portion 9b

(m)       Stockpile of soil and excavation in Portion 9c

(n)         Excavation, sheetpiling for ELS, drainage works and road construction in Portion 10a

(o)         Sheetpiling and excavation, pipes laying in Portion 10b

(p)         Construction of MBR at 11b

(q)         Construction of temporary sewage pumping station in Portion 14

ND/2019/02

(a)          Pre-bored Socketed H-pile

(b)         Tree felling

(c)          ELS

(d)         Pipe Jacking

(e)          Construction of Pile Cap

ND/2019/03

 

(a)        Portion 1

-            Demolition of concrete warehouse 巨賓

-            Road work and drainage work at Yin Kong Road

(b)       Portion 2 to Portion 20C

-          Erection of Permanent Boundary Structure

-          Construction of Irrigation Channel

-          Construction of Type 1 Storage House

-          Construction of Type 2 Storage House

-          Construction of Composting Facility

-          Construction of Bird Hide

-          Construction of Outdoor Classroom

-          Construction of Storage Sheds

-          Wetland Creation & Restoration works

ND/2019/04

 

(a)           Site clearance

(b)           Tree felling

(c)           Predrill

(d)           Bored piling

(e)           Excavation

(f)            Sheet piling

(g)           ELS

ND/2019/05

(a)           North Team Works

-          Pre-drilling for bored piles at B1-01(Portion I), B1 & B2 (Portion II), C1 (Portion II), C1-03

-          Bored piling at B1 (Portion 1), B1 & B2 (Portion II), C1 (Portion II), C1-03, C1-04, C2-01, C2-02, C2-03a, C2-03b, C3-02, C3-03a, C3-04a, D2-01, E2-01.

-          ELS and Pile cap construction at C3-03b, C3-04b, C4-03, C4-04a, C4-04b, D1-01, D1-02, D1-03, D1-04, E1-01, E1-02, E1-03 & E1-04

-          Footing construction at C4-02

-          Pier Construction at C4-03, C4-04a, C4-04b, D1-01, E1-01, E1-02, E1-03, E1-04

(b)          Viaduct Works

-          Abrication of the 2nd and 3rd typical segment mould

-          Fabrication of SOP segment mould

-          Fabrication of temporary support for SOP erection at Pier C4-04M and temporary falsework for1st pair segment erection

-          Fabrication of launching girder (LG) main truss and main support beams

-          Fabrication of 1st set Form Travel (FT)

-          Bearing test in Taiwan for the 1st batch (Bridge C4, C3 and C2)

-          E&M installation for the gantry crane in CTC yard

(c)           South Team Works

-          Venton Area – UU diversion, 11kv and 132kv cross road duct laying

-          Portion 13 – Construction of FW 52 bay 1 and 2. 132kv duct laying

-          Portion 17 and 18 – DN 1650 pipe and MH construction.

-          FLHY (NB) – Setback for lane shifting

-          HKY FB (West) – ELS for LT2

-          HKY FB (East) – construction of LT1, P02 and AB1

-          Portion 11 – DN1200 watermain laying work

-          E2-02 pier – pier construction.

-          E2-03 – ELS for pile cap. Pile cap construction.

-          E3-01 – Piling works

-          E3-03 – Pile cap and pier

-          D2-02 – ELS for pile cap

-          D2-03 – Pre-drilling and Piling works.

ND/2019/06

 

(a)          Finishing works and E&M installations for the Management Office Building (MOB) at Portion 4.

(b)         Erection of seam roof of steel canopy at Portion 3.

(c)          E&M installations for the steel canopy at Portion 3.

(d)         Construction of concrete carriageway at Portion 3.

(e)          Construction of underground utilities in the final stage market at Portion 3.

(f)          Installation of sheet piles for ELS for footings of additional carriageway steel cover at Portion 3.

(g)         Construction of footings of additional carriageway steel cover at Portion 3.

(h)         Construction of walls and columns of additional water tank and pump house at Portion 3.

ND/2019/07

(a)        Site clearance at Portion 1 and 2.

(b)        Erection of site hoarding at Portion 1.

(c)        C&D waste disposal at Portion 1 and 2.

(d)        G.I. works at Portion 1.

(e)        Construction of box culvert at Portion 2.

(f)         Filling works at Portion1 and 2.

(g)        Tree felling/ Disposal of yard waste at Portion 1, 2 and 3.

(h)        Construction of site haul road at Portion 1.

(i)         Trial pit at Ma Sik Road.

(j)         Demolition of villagers houses at Portion 1, 2 and 4.

(k)        Removal of asbestoses containing material at Portion 1, 2 and 4.

(l)         Drainage Works at Portion 1 and 3.