Table 10.4 Specific Water Quality Mitigation Measures for Major
Construction Works in the Reporting Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Hydroseeding for slope
area |
ND/2019/02 |
Hard paved exposed
slope surface |
Temporary ditches to direct storm water to wastewater treatment
facilities |
ND/2019/03 |
Wastewater from wheel
washing was directed to wastewater treatment facility |
Regular clearance of
water for wheel washing facility |
ND/2019/04 |
Surface channels and earth bunds to direct
storm water to wastewater treatment facilities for works area near Siu Hang
San Tsuen Stream |
Deployment of silt curtain around works area in Ng Tung Rive |
ND/2019/05 |
Provision of sand
bags around works area |
Temporary ditches to direct
storm water to wastewater treatment facilities |
ND/2019/06 |
Grasscrete for slope protection |
Provision of concrete berm around site area |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
Temporary rainwater storage area for
rainstorm event |