5               WATER QUALTY MONITORING

Monitoring Requirements

5.1         In accordance with the Updated EM&A Manual, impact water quality monitoring shall be carried out three days per week at all the designated monitoring stations during the construction period. The measurement periods are during the construction of channel specified in Table 4.1 of Updated EM&A Manual. The interval between two sets of monitoring shall not be less than 36 hours.

 

5.2         Replicate in-situ measurements of Dissolved Oxygen (DO), temperature, turbidity, pH, Suspended Solids (SS) and samples for Suspended Solids (SS), ammonia nitrogen, unionized ammonia, nitrate nitrogen and orthophosphate from each independent sampling event shall be collected to ensure a robust statistically interpretable database.

 

5.3         Appendix B shows the established Action and Limit Levels for the water quality monitoring work according to pre-construction ETs Updated EM&A Manual and Baseline Water Quality Monitoring Report (KTN & FLN NDA).

Monitoring Parameters, Frequency

5.4         Table 5.1 summarized the monitoring parameters, monitoring periods and frequencies of the water quality monitoring.

 

Table 5.1     Water Quality Monitoring Parameters and Frequency

Parameters, unit

Depth

Frequency

·         Temperature(°C)

·         pH(pH unit)

·         turbidity (NTU)

·         water depth (m)

·         salinity (ppt)

·         DO (mg/L and % of saturation)

·         SS (mg/L)

·         Ammonia Nitrogen (NH3-N) (mg NH3-N/L)

·         Unionized Ammonia (UIA) (mg/L)

·         Nitrate-nitrogen (NO3-N) (mg NO3--N/L)

·         Ortho-phosphate (PO4) (mg PO43--P/L)

·      3 water depths: 1m below water surface, mid-depth and 1m above river bed.

·      If the water depth was less than 3m, mid-depth sampling only.

·      If water depth was less than 6m, mid-depth may be omitted.

3 days per week during

construction of channel

Results and Observations

5.5         According to the Section 5.6.1.2 of approved EIA Report, the potential water quality impact during construction is due to the alternation of natural streams (i.e. channelization of Ma Tso Lung Stream and Siu Hang San Tsuen Stream) as these two streams are the ecological importance streams.

 

5.6         No construction of channel was carried out at Ma Tso Lung Stream and Siu Hang San Tsuen Stream during the reporting month. Therefore, no water quality monitoring was conducted.

 

Additional Water Quality Monitoring

Monitoring Requirements

5.7         Additional Water Quality Monitoring shall be carried out at River Beas, River Indus and near Siu Hang San Tsuen Stream three days per week at all designated monitoring stations during the construction period. The measurement period are during the construction site drainage along River Beas, construction of footbridge across River Beas and during construction of bridge across River Indus.

 

5.8         Replicate in-situ measurement and samples from each independent sampling event were collected to ensure a robust statistically interpretable database. DO, temperature, turbidity and pH were measured in-situ whereas SS and arsenic were determined by an accredited laboratory. Other relevant data were recorded, including monitoring location / position, time, water depth, weather conditions and any special phenomena or work underway at the construction site.

 

5.9         For all the monitoring stations, sampling were taken at 3 water depths, namely 1m below the water surface, mid depth and 1m above the river bed. For stations that are less than 3m in depth, only the mid depth sample was taken. Should the water depth is less than 6m, in which case the mid-depth station may be omitted. The interval between two sampling surveys was not less than 36 hours.

 

5.10     Appendix B shows the established Action and Limit Levels for the environmental monitoring works

Monitoring Locations

5.11     Additional impact water quality monitoring was conducted at 6 monitoring stations (SYR-CS1, SYR-IS1, NTR-CS1, NTR-IS1, SHST-IS2, MWR-IS3) which is summarised in Table 5.2. The location of monitoring stations are shown in Figure 5 and 6.

 


 

Table 5.2     Additional Water Quality Monitoring Stations

Station

Description

Locations

Measurement Periods

River Beas

SYR-CS1

Control Station

Upstream of river

During the construction site drainage along River Beas and construction of footbridge across River Beas

SYR-IS1

Impact Station

Downstream of river

River Indus and near Siu Hang San Tsuen Stream

NTR-CS1

Control Station

Upstream of river

During construction of bridge across River Indus

NTR-IS1

Impact Station

Downstream of river

SHST-IS2

Impact Station

Water sensitive receiver at near Siu Hang San Tsuen Stream

MWR-IS3

Impact Station

Water sensitive receiver at near Ma Wat River

Monitoring Equipment

Instrumentation

5.12     A multi-parameter meters (Model YSI EXO) was used to measure DO, turbidity, salinity, pH and temperature.

 

Dissolved Oxygen (DO) and Temperature Measuring Equipment

 

5.13     The instrument for measuring dissolved oxygen and temperature should be portable and weatherproof complete with cable, sensor, and use DC power source. The equipment was capable of measuring:

·         A dissolved oxygen level in the range of 0-20mg/L and 0-200% saturation; and

·         The temperature within 0-45 degree Celsius.

 

5.14     The equipment had a membrane electrode with automatic temperature compensation complete with a cable.

 

5.15     Sufficient stocks of spare electrodes and cables were available for replacement where necessary.

 

5.16     Salinity compensation was built-in in the DO equipment. In-situ salinity was measured to calibrate the DO equipment prior to each DO measurement.

 

Turbidity

 

5.17     Turbidity was measured in situ by using the nephelometric method. The instrument was portable and weatherproof using a DC power sources complete with cable, sensor and comprehensive operation manuals. The equipment was capable of measuring turbidity between 0-1000 NTU. The probe cable was not less than 25m in length. The meter was calibrated in order to establish the relationship between NTU units and the levels of suspended Solids.

Salinity

 

5.18     A portable salinometer capable of recording salinity within the range of 0-40 parts per thousand (ppt) was used for salinity measurement.

 

Water Depth Detector

 

5.19     A portable, battery-operated and hand held echo sounder was used for the determination of water depth at each designated monitoring station.

 

pH

 

5.20     The instrument was consisting of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device. It was readable to 0.1pH in a range of 0 to 14. Standard buffer solutions of at least pH 7 and pH 10 were used for calibration of the instrument before and after use.

 

Water Sampling for Laboratory Analysis

 

5.21     A water sampler, consisting of a transparent Polyvinyl Chloride (PVC) of a capacity of not less than two litres which can be effectively sealed with cups at both ends was used. The water sampler had a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler was at the selected water depth. In addition, a sampling cup attached to a fixed or extendable rod was also used for sampling at the monitoring stations with swallow water.

 

Sample Container and Storage

 

5.22     Following collection, water samples for laboratory analysis were stored in high density polyethylene bottles with appropriate preservatives added, packed in the ice (cooled to 4oC without being frozen). The sample were delivered to WELLAB Limited (HOKLAS Registration No.083) and analysed as soon as possible after collection of the water samples. Sufficient volume of samples was collected to achieve the detection limit.

 

Calibration of In Situ Instruments

 

5.23     The pH meter, DO meter and turbidimeter were checked and calibrated before use. DO meter and turbidimeter were certified by WELLAB Limited before use and subsequently re-calibrated at quarterly basis throughout all stage of water quality monitoring programme. Response of sensors and electrodes were checked with certified standard solutions before each use. Wet bulb calibration for a DO meter was carried out before measurement at each monitoring station.

 

5.24     For the on-site calibration of field equipment (Multi-parameter Water Quality System), the BS 1427:2009, “Guide to on-site test methods for analysis of waters” was observed.

 

Back-up Equipment

 

5.25     Sufficient stocks of spare parts were maintained for replacements when necessary. Backup monitoring equipment was also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

 

5.26     Table 5.3 summarizes the equipment used in the water quality monitoring program. The copies of the calibration certificates of multi-parameter water quality system are shown in the Appendix C.

 

Table 5.3     Water Quality Monitoring Equipment

Equipment

Model and Make

Qty.

Water sampler and sampling cup

A 2-Litre transparent PVC cylinder with latex cups at both ends and sampling cup for monitoring stations with swallow water

1

Sonar Water Depth Detector

Garmin Striker plus 4

1

Multi-parameter Water Quality System

YSI EXO 1

2

Monitoring Parameters and Frequency

5.27     Table 5.4 summarizes the monitoring parameters and frequencies of the additional water quality monitoring. The water quality monitoring schedule for the reporting month is shown in Appendix D.

 

Table 5.4     Additional Water Quality Monitoring Parameters and Frequency

Monitoring Station(s)

Parameters, unit

Depth

Frequency

River Beas

SYR-CS1

SYR-IS1

·         Temperature (oC)

·         pH (pH unit)

·         Turbidity (NTU)

·         Water depth (m)

·         Salinity (ppt)

·         Dissolved Oxygen (DO) (mg/L and % of saturation)

·         Suspended Solids (SS) (mg/L)

·         Arsenic (As) (µg/L)

·         3 water depths: 1m below water surface, mid-depth and 1m above river bed.

·         If the water depth was less than 3m, mid-depth sampling only.

·         If water depth was less than 6m, mid-depth might be omitted.

3 days per week, for 2 weeks prior to the commencement of  construction works

River Indus and near Siu Hang San Tsuen Stream

NTR-CS1

NTR-IS1

SHST-IS2

MWR-IS3

·         Temperature (oC)

·         pH (pH unit)

·         Turbidity (NTU)

·         Water depth (m)

·         Salinity (ppt)

·         Dissolved Oxygen (DO) (mg/L and % of saturation)

·         Suspended Solids (SS) (mg/L)

 

5.28     Monitoring location and position, time, sampling depth, weather conditions and any special phenomena or work underway nearby was also be recorded.

Monitoring Methodology

Instrumentation

5.29     A multi-parameter meters (Model YSI EXO) was used to measure DO, turbidity, salinity, pH and temperature.

 

Operating/Analytical Procedures

5.30     At each measurement, two consecutive measurements of DO concentration, DO saturation, salinity, turbidity, pH and temperature were taken. The probes were retrieved out of the water after the first measurement and then re-deployed for the second measurement. Where the difference in the value between the first and second readings of each set was more than 25% of the value of the first reading, the reading was discarded and further readings were taken.

 

Laboratory Analytical Methods

5.31     Duplicate samples from each independent sampling event are required for all parameter. Analysis of suspended solids and arsenic were carried out by WELLAB Ltd. and comprehensive quality assurance and control procedures in place in order to ensure the quality and consistency in results. The reporting limit and detection limit are provided in Table 5.5.

 

Table 5.5     Method for Laboratory Analysis for Water Samples

Determinant

Proposed Method

Limit of Reporting

Total Suspend Solids (SS)

APHA 17ed 2540 D

2.5 mg/L

Arsenic (As)

In-house method SOP022 (ICP-AES) and SOP076 (ICP-MS)

1 µg/L

 


 

QA/QC Requirements

Decontamination Procedures

 

5.32     Water sampling equipment used during the course of the monitoring process was decontaminated by manual washing and rinsed with distilled water after each sampling event. All of the disposal equipment was discarded after the sampling.

 

Sampling Management and Supervision

 

5.33     All sampling bottles were labelled with the sample I.D (Including the sampling station), laboratory number and sampling date. Water samples were dispatched to the testing laboratory for analysis as soon as possible. All the collected samples were stored in a cool box to keep the temperature less than 4oC but without frozen. All water samples were handled under chain of custody protocols and relinquished to the laboratory representatives at locations specified by the laboratory.

 

Quality Control Measures for Sample Testing

 

5.34     The samples testing and following QC programme were performed by WELLAB Ltd. for every batch of 20 samples:

 

·                One method blank; and

·                One set of QC sample.

Results and Observations

5.35     All additional water quality monitoring was conducted as scheduled in the reporting month. The water quality monitoring schedule for this reporting month is shown in Appendix D.

 

5.36     The monitoring results and graphical presentation of additional water quality monitoring at the monitoring stations are shown in Appendix G.

 

5.37     During the reporting month, one (1) Action Level exceedance and fifteen (15) Limit Level exceedances for dissolved oxygen, eight (8) Limit level exceedances for turbidity, seven (7) Limit Level exceedances for suspended solids and three (3) Action Level exceedance for arsenic of impact water quality monitoring were recorded. The summary of exceedance records is shown in Table 5.6 and Table 5.7.

 

 

 

Table 5.6         Summary of Exceedance Records of Water Quality Monitoring in the Reporting Month

Date

Monitoring

Stations

Parameter (unit)

Depth-averaged Measured Value

Exceedances

Exceedances due to the Contract

AL

LL

2 June 2021

SYR-IS1

DO (mg/L)

4.8

 

ü

No

SHST-IS2

DO (mg/L)

6.8

ü

 

 No(ND/2019/04)

Turb. (NTU)

9.0

 

ü

MWR-IS3

DO (mg/L)

6.6

 

ü

No

4 June 2021

SYR-IS1

DO (mg/L)

5.6

 

ü

No

Arsenic (µg/L)

14.5

ü

 

NTR-IS1

DO (mg/L)

3.4

 

ü

No

SHST-IS2

DO (mg/L)

6.4

 

ü

Yes

(ND/2019/04)

Turb. (NTU)

20.9

 

ü

SS (mg/L)

33.5

 

ü

MWR-IS3

DO (mg/L)

6.8

 

ü

No

Turb. (NTU)

42.2

 

ü

SS (mg/L)

68.5

 

ü

7 June 2021

SYR-IS1

Arsenic (µg/L)

19.5

ü

 

No

NTR-IS1

DO (mg/L)

5.4

 

ü

No

SHST-IS2

DO (mg/L)

6.7

 

ü

No

Turb. (NTU)

12.1

 

ü

SS (mg/L)

10.0

 

ü

MWR-IS3

DO (mg/L)

8.4

 

ü

No

9 June 2021

SYR-IS1

Arsenic (µg/L)

18.5

ü

 

No

NTR-IS1

Turb. (NTU)

38.4

 

ü

No

SS (mg/L)

42.0

 

ü

SHST-IS2

DO (mg/L)

6.5

 

ü

No

Turb. (NTU)

12.8

 

ü

SS (mg/L)

18.0

 

ü

MWR-IS3

DO (mg/L)

6.7

 

ü

No

Turb. (NTU)

26.1

 

ü

SS (mg/L)

34.0

 

ü

11 June 2021

SYR-IS1

DO (mg/L)

4.9

 

ü

No

NTR-IS1

DO (mg/L)

5.1

 

ü

No

SHST-IS2

DO (mg/L)

6.3

 

ü

Yes

(ND/2019/04)

Turb. (NTU)

12.1

 

ü

SS (mg/L)

14.5

 

ü

MWR-IS3

DO (mg/L)

7.7

 

ü

No

Abbreviation: AL – Action Level, LL – Limit Level, DO – Dissolved Oxygen, Turb. – Turbidity, SS – Suspended Solids

 

Table 5.7         Summary of Exceedance Records of Water Quality Monitoring in the Reporting Month

Parameter

No. of non-project related Exceedances

Total No. of non-project related Exceedances

No. of Exceedance related to the Construction Works of the Contract

Total No. of Exceedance related to the Construction Works of the Contract

Action Level

Limit Level

Action Level

Limit Level

Dissolved Oxygen

1

12

13

0

3

3

Turbidity

0

5

5

0

3

3

Suspended Solids

0

4

4

0

3

3

Arsenic

3

0

3

0

0

0

 

5.38     Notifications of exceedance were issued to relevant parties upon confirmation of the monitoring results. Investigation for the exceedances recorded were conducted by ET accordingly. After investigation, three (3) Limit Level exceedances for dissolved oxygen, three (3) Limit level exceedances for turbidity and three (3) Limit Level exceedances for suspended solids at monitoring station, SHST-IS2, were found due to Contract No. ND/2019/04. Other exceedances were considered non-projected related. The investigation results and summary of exceedances are summarised in Table 5.8. The summary of exceedance recorded in the reporting month is shown in Appendix O.

 


 

 

Table 5.8         Summary of Investigation on Water Quality Monitoring Exceedance Records in the Reporting Month

Date

Monitoring Stations

Parameters

Investigation Summary

2, 4 and 11 June 2021

SYR-IS1

DO

The exceedances are considered not due to the Contract due to the following reasons:

1)    No pollution discharge from construction activity was observed;

2)    DO value at control station were measured lower than the water quality criteria at SYR-IS1 (4 June 2021);

3)    Water temperature recorded were relatively higher that that during baseline monitoring and led to low oxygen solubility in water.

4, 7 and 9 June 2021

SYR-IS1

Arsenic

No pollution discharge from construction activity was observed. The exceedances are considered due to the external factors rather than the contract works and non-project related.

4, 7 and 11 June 2021

NTR-IS1

DO

The exceedances are considered not due to the Contract due to the following reasons:

1)    No pollution discharge from construction activity was observed;

2)    DO value at control station were measured lower than the water quality criteria at NTR-IS1 (4 and 11 June 2021);

3)    Water temperature recorded were relatively higher that that during baseline monitoring and led to low oxygen solubility in water.

9 June 2021

NTR-IS1

Turbidity and SS

An influx of muddy water from a tributary (out of Project boundary) to Ma Wat River and then to River Indus was observed which affect the water quality of River Indus during the monitoring day. No pollution discharge from construction activity under the Project was observed. Rainfall was recorded before monitoring which led to increased surface runoff and hence adverse water quality. The exceedances are considered due to the external factors rather than the contract works and non-project related.

2 and 7 June 2021

SHST-IS2

DO, turbidity and SS

No pollution discharge from construction activity was observed. Rainfall was recorded before monitoring which led to increased surface runoff and erosion from natural habitat along the Siu Hang San Tsuen Stream, and also may cause the dispersion of riverbed sediment to the monitoring station. (2 June 2021).

DO value at control station were measured lower than the water quality criteria at SHST-IS2. The exceeded results were similar or within the ranges of baseline monitoring results. Water temperature recorded were relatively higher that that during baseline monitoring and led to low oxygen solubility in water. The exceedances are considered due to the external factors rather than the contract works and non-project related.

4, 9 and 11 June 2021

SHST-IS2

DO, turbidity and SS

Increased surface runoff from rainfall recorded before and during the water quality monitoring may lead to erosion from natural habitat along the stream, and also may cause the dispersion of riverbed sediment to the monitoring station. During monitoring, muddy surface runoff was observed between gaps of water barrier (under Contract No. ND/2019/04) near Station SHST-IS2 which was considered as a source of water pollution.

In addition, DO value at control station were measured lower than the water quality criteria at SHST-IS2. Water temperature recorded were relatively higher that that during baseline monitoring and led to low oxygen solubility in water.

Remedial works were observed in progress to clear the sediment trapped by desilting materials, provide concreting for exposed site area near Siu Hang San Tsuen Stream and provide surface channels for diverting storm water to wastewater treatment facilities. The following recommendations on remedial measures were given as below and shall be maintained to avoid further exceedances:

1)     To regularly clear the slurry and sediment trapped by desilting materials;

2)     To identify and minimise any source of surface runoff within site area near Siu Hang San Tsuen Stream;

3)     To provide spare pumps for emergency use to pump muddy surface runoff to wastewater treatment facilities after rainstorm;

4)     To minimise area of exposed soil surface by covering with impervious materials or clear loosen soil materials to reduce formation of muddy surface runoff;

5)     To frequently check and ensure desilting materials for protection of Siu Hang San Tsuen Stream are intact and in good condition;

6)     To provide channels, earth bunds or sand bag barriers to direct any muddy water to silt removal facilities and away from Siu Hang San Tsuen Stream;

7)     Regular supervision and close monitoring on sediment control measures should be conducted by designated foreman to ensure normal operation; and

8)     Proposal for mitigation measures on sediment control and contingency plan under Contract No. ND/2019/04 should be submitted to avoid further exceedances. The effectiveness of the remedial measures implemented should be closely reviewed

The effectiveness of remedial measures implemented by the Contractor would be continuously checked and reviewed during water quality monitoring and weekly site inspection.

2, 4, 7, 9 and 11 June 2021

MWR-IS3

DO, Turbidity and SS

Influx of muddy water from a tributary (out of Project boundary) to Ma Wat River and then to the monitoring stations was observed which affect the water quality of Ma Wat River during the monitoring days. No pollution discharge from construction activity under the Project was observed. DO value at control station were measured lower than the water quality criteria at MWR-IS3 (2, 4, 9 and 11 June 2021). Water temperature recorded were relatively higher that that during baseline monitoring and led to low oxygen solubility in water. The exceedances are considered due to the external factors rather than the contract works and non-project related.

 

5.39     Proposal for mitigation measures on sediment control and contingency plan under Contract No. ND/2019/04 were submitted to ET, IEC and engineer for review. Remedial measures on sediment control for Siu Hang San Tsuen Stream were proposed and implemented by the Contractor under Contract No. ND/2019/04 and are partially listed as below:

 

Construction Runoff

l  Excavated materials generated from bored piling works shall be removed off-site and disposed of immediately to prevent soil erosion;

l  2m-high solid barrier are erected for protection of Siu Hang San Tsuen Stream. Geotextile and sand bags are installed along the bottom of solid barrier to prevent muddy runoff to the stream;

l  Soil materials trapped within geotextile shall be regularly cleared;

l  Concrete or tarpaulin sheet are provided to cover the exposed soil surface to reduce muddy surface runoff;

l  Surface channels and earth bunds are provided for slope surface in site area near the stream to direct storm water to silt removal facilities or wastewater treatment facilities;

l  Deposited sand/silt shall be cleared regularly in silt removal facilities, channels and manholes, especially after rainstorm;

 

 

General Construction Activities and Measures

l  The exposure of soil on-site after excavation and backfilling shall be minimised where applicable to prevent washout of soil from the site;

l  Open stockpiles of construction materials on-site shall be covered with tarpaulin during rainstorms to prevent erosion;

l  Wastewater generated from site shall be collected and directed to the wastewater treatment facilities for treatment prior to discharging to the public drain as specified in the Effluent Discharge Licence;

l  Wastewater treatment facilities shall be inspected, maintained and cleaned as necessary by a designated person to ensure proper and efficient operations of the facilities, particularly after rainstorms; and

l   Spare water pumps shall be prepared.

 

5.40     The effectiveness of remedial measures implemented by the Contractor would be continuously checked and reviewed to ensure proper implementation.

Event and Action Plan

5.41     Should any project related non-compliance of the criteria occur, action in accordance with the Action Plan in Appendix N shall be carried out.