2               PROJECT INFORMATION

Background

2.1         The Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs) are one of the important sources of land and housing supply in the medium and long term. The development of the KTN and FLN NDAs will be implemented in phase for full completion by 2031. The Phase 1 of the NDAs development, comprising the Advance Works and First Stage Works, is targeted to be implemented from the second half of 2019 progressively. The Advance and First Stage Works would include site formation, engineering infrastructure works (including roads, drainage, sewerage, waterworks, landscaping works, pumping stations, and fresh water and flushing water service reservoirs), soil remediation, reprovisioning of North District Temporary Wholesale Market, development of a nature park at Long Valley and implementation of environmental mitigation measures.

2.2         The scope of works under the Advance and First Stage Works comprises the following:

 

a)                   The Advance Works (PWP item No. 7747CL-2) consist of:

i)         site formation of land (including soil remediation) in KTN and FLN NDAs for housing, community facilities and engineering infrastructure;

ii)       construction of roads including the eastern section of Fanling Bypass (FLBP(E)) connecting the FLN NDA to Fanling Highway and other roads with footpaths and cycle tracks, and associated junction/ road improvements;

iii)     engineering infrastructure works including drainage. Sewerage (including two sewage pumping stations), waterworks (including a fresh water service reservoir and a flushing water service reservoir in the KTN NDA), landscape works and slopeworks;

iv)     part expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);

v)        reprovisioning works; and

vi)     implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i) to (v) above.

b)                  The First Stage Works (PWP item No. 7759CL) consist of:

i)         development of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River for connection between these two facilities;

ii)       reprovisioning of two egretry sites in the FLN NDA and enhancement works to an existing egretry site in the KTN NDA;

iii)     site formation of land for a village resite area and a district police station in the KTN NDA;

iv)     engineering infrastructure works including roads, drainage, sewerage, waterbirds, and landscape works; and 

v)        implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i) to (iv) above.

 

2.3         The Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule 3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October 2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs under the Project and the respective Work Contracts are summarized in Table 2.1.

 

Table 2.1 Summary of EPs under the Project and the Respective Work Contracts

EP No.

Designated Project

C1

C2

C3

C5A

C5B

C6

C7

EP-466/2013

Castle Peak Road Diversion

ü

 

 

 

 

 

 

EP-467/2013/A

Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement

ü

 

 

 

 

 

 

EP-468/2013/A

Kwu Tung North New Development Area Road D1 to D5

ü

 

ü

 

 

 

 

EP-469/2013

Sewage Pumping Stations in Kwu Tung North New Development Area

 

ü

 

 

 

 

 

EP-470/2013

Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works

ü

 

 

 

 

 

 

EP-473/2013/A

Fanling Bypass Eastern Section

 

 

ü

ü

ü

 

 

EP-475/2013/A

Reprovision of temporary Wholesale Market in Fanling North New Development Area

 

 

 

 

 

ü

 

EP-546/2017

Fanling North Temporary Sewage Pumping Station

 

 

 

ü

 

 

 

                Note: C1: ND/2019/01       C2: ND/2019/02  C3: ND/2019/03  C5A: ND/2019/04

                     C5B: ND/2019/05         C6: ND/2019/06  C7: ND/2019/07

 

2.4         The site boundary of the Project and all Works Contracts are shown in Drawing No. 1.

2.5         The required submissions and submission status under Environmental Permits are shown in Appendix U.

Project Organization

2.6         Different parties with different levels of involvement in the Project organization include:

Ÿ    Project Proponent – Civil Engineering and Development Department (CEDD)

Ÿ    Supervisor / Supervisor's Representative – AECOM

Ÿ    Environmental Team (ET) – Wellab Limited

Ÿ    Independent Environmental Checker (IEC) – Mott MacDonald Hong Kong Ltd (MottMac)

 

2.7         The key personnel contact names and numbers are summarised in Table 2.2.

 

Table 2.2     Key Contacts of the Project

Party

Role

Contact Person

Phone No.

Fax No.

Civil Engineering and Development Department, HKSAR (CEDD)

Project Proponent

Mr. Felix Fan

3152 3551

3547 1658

Supervisor / Supervisor's Representative

(AECOM)

Chief Resident Engineer

Mr. Alan Lee

6398 5982

2645 3900

Environmental Team

(Wellab Limited)

Environmental Team Leader

Dr. Priscilla Choy

2898 7388

2898 7076

Independent Environmental Checker (MottMac)

Independent Environmental Checker

Mr. Thomas Chan

2828 5967

2827 1823

Contract No. ND/2019/01

Contractor (Build King – Richwell Engineering Joint Venture)

Site Agent

Mr. Ivan Leung

9640 8340

--

Environmental Officer

Mr. Edward Tam

9287 8270

Contract No. ND/2019/02

Contractor (Chun Wo – Kwan Lee Joint Venture.)

Site Agent

Mr. Andy Chan

3485 9780

--

Environmental Officer

Mr. Ng Tao, Richard

9802 9577

Contract No. ND/2019/03

Contractor (Sang Hing Kuly Joint Venture)

Site Agent

Mr. Tang Wing Kai

9300 7037

--

Environmental Officer

Mr. Chow Ka Wing

9184 6351

Environmental Supervisor

Mr. Ken Kwok

9732 4360

Contract No. ND/2019/04

Contractor (Daewoo – Chun Wo – Kwan Lee Joint Venture)

Site Agent

Mr. Bear Ding

6483 6198

--

Environmental Officer

Ms. Donna Tso

9283 7167

Environmental Supervisor

Ms. Peggie Hon

9714 3308

Contract No. ND/2019/05

Contractor (CRCC – Paul Y. Joint Venture)

Site Agent

Mr. Darvin Lo

9467 5891

--

Environmental Manager

Mr. Pan Fong

9436 9435

Environmental Officer

Ms. Louise Poon

5272 5709

Contract No. ND/2019/06

Contractor (New Concepts Engineering Development Ltd.)

Site Agent

Mr. Anson Chan

 

9349 1320

2363 2162

Environmental Officer

Mr. Alex Choy

9409 9608

Environmental Coordinator

Ms. Mildred Hung

9460 2745

Contract No. ND/2019/07

Contractor (China Road and Bridge Corporation)

Site Agent

Mr. Daniel Wong

5335 9572

--

Environmental Officer

Mr. K. M. Lui

5113 8223

Environmental Supervisor

Mr. Attlee Chau

6386 9018

Summary of Construction Works Undertaken During Reporting Month

The major site activities undertaken in the reporting month are shown in Table 2.3.

 

Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (June 2021)

ND/2019/01

(a)          Site clearance, excavation in Portion 3

(b)         Site Clearance, stockpile of soil, construction of KW01 retaining wall, sheetpiling and excavation, pipes laying in Portion 5

(c)          Site Clearance, sheetpiling and excavation, pipes laying, construction of KW01 retaining wall in Portion 6a

(d)         Arsenic soil treatment works in Portion 6b

(e)          Site Clearance, Construction of temporary road for alternative Po Lau Road, Construction of site accommodation in Area T2 and T3, sheetpiling and excavation, pipes laying, footing of Noise Barriers in Portion 7

(f)          Construction of Retaining Wall, slope cutting, soil nailing, slope drainage and maintenance access construction, Excavation for Fresh Water Service Reservoir, RC construction of Flushing Water Service Reservoir in Portion 8a

(g)         Sheetpiling for jacking pit in Portion 8b

(h)         Sheetpiling and excavation and pipes laying in Portion 9b

(i)           Stockpile of soil and excavation in Portion 9c

(j)           Sheetpiling for ELS, excavation, pipes laying and noise barriers footing in Portion 10a

(k)         Sheetpiling and excavation in Portion 10b

(l)           Laying of rising mains, construction of MBR in Portion 11b

(m)       Sheetpiling and excavation , Construction of temporary sewage pumping station in Portion 14

(n)         Construction of CLC in Portion 16

ND/2019/02

(a)          Pre-bored Socketed H-pile

(b)         Tree felling

(c)          Hoarding erection

ND/2019/03

(a)          Underground Utilities Laying in Portion 1;

(b)         Portion 2 to Portion 20

-          Erection of Permanent Boundary Structure

-          Construction of Irrigation Channel

-          Geotechnical Works in Long Valley (Trail Pits)

-          Construction of Temporary Road in Long Valley

-          Asbestos Removal in Long Valley

-          Demolition of Existing Construction in Handed over Area

-          Construction of Storage Shed and Type 2 Storage House

-          Construction of Bird Hide

-          Construction of Outdoor Classroom

-          Wetland Creation & Restoration works

ND/2019/04

(a)           Site clearance

(b)           Tree felling

(c)           Predrill

(d)           Socket H-piling

(e)           Bored piling

(f)            Excavation

(g)           Sheet piling

ND/2019/05

(a)           Bridge Foundation Works

-          Ground investigation works at FLN3-DH016, ABH02, ABH04, ABH10, D39(P).

-          Pre-drilling for bored piles at B1(Portion I), C2-01, C2-02, E2-01, B1(Portion II), B2(Potion II), C1-01 & C1-02(Portion II), C3-02.

-          Bored piling at C3-03b, C3-04b, C2-04b, D1-03, E1-03, D1-04, E1-04, E2-03, C3-01b, C2-01, B1(Portion 1), C3-04b, E3-01, C3-01a, C2-03b, C3-03a, C3-04a, D1-02, E1-02, E2-01, D2-01.

-          Pile cap construction at E2-01, C4-03, C4-04, E3-03, D1-01, E1-01, HKY-P02 pile cap & HKYAB ELS.

-          Footing construction at C4-01a and C4-01b.

(b)          Viaduct Works

-          Segment Mould fabrication and installation.

-          Segment production line and segment storage yard establishment

-          First batch of precast segment production

-          Rebar cage jig fabrication

-          Segment shop drawing preparation for bridge C4

-          M.J. S.O.P. erection method statement submission

-          Typical pier column mould fabrication

-          Bearing fabrication for bridge C4 and C3

-          Falsework & formwork design for typical pier head

-          Pier column trial panel at CTC yard

-          First pair of segment erection method statement

-          PT material delivery (first batch) to HZ precast yard preparation

-          Bearing fabrication for bridge C2, C3 and C4

-          Ground beam construction for gantry crane

-          Containers site office setup

(c)           Jockey Club Road

-          Confirmation the retaining wall design and commence works

-          Tree fell and UU diversion

-          Completion of gas main diversion and commencement of cut slope work and soil nail at the 3SW-A/C149

-          Completion of gas main diversion and erection of temporary steel decking for site access at the 3SW-C/F63

(d)          Tai Wo Service Road West

-          Road widening for D2-03 (Jun-Aug)

-          Duct laying by telecoms and CLP in the Portion XI (joint bay)

-          Cross road duct laying to refuge island in the Portion XI

-          CLP and gas main duct laying in the Portion XIII

-          HKT draw pit construction in the Portion XIII

-          Completion of 1650 dia. drain and manhole and plate load test of         retaining wall FW52 in the Portion XIII

-          Commencement of FW52 construction

-          ELS and construction of 1650 dia. drain and manhole in the Portion XVIII

-          Erection of temporary barrier

-          Demolish of HKY staircase

(e)           Tai Wo Service Road East

-          Construction of drainage works at Portion XI and XII 

-          Water main laying works 

(f)           Fanling Highway

-          Road works for Diversion of Fanling Highway for Pier D2-03 Construction

ND/2019/06

(a)            Finishing works and E&M installations for the Management Office Building (MOB) at Portion 4

(b)           Off-site fabrication of steel column, steel truss and bracing of steel canopy in China

(c)            Erection of the steel members of steel canopy at Portion 3

(d)           Construction of retaining wall FW21 at Portion 6

(e)            Construction of ground slab of the market stall area and concrete carriageway at Portion 3

(f)            Construction of underground utilities in the final stage market at Portion 3

(g)           Installation of sheet piles for ELS for footings of additional carriageway steel cover at Portion 3

ND/2019/07

(h)           Site clearance at Portion 1 and 2.

(i)             Erection of site hoarding at Portion 1.

(j)             C&D waste disposal in Portion 1 and 2.

(k)           G.I. works at Portion 1.

(l)             Construction of box culvert in Portion 2.

(m)         Filling works in Portion 2.

(n)           Tree felling / Disposal of yard waste in Portion 1 and 2

(o)           Construction of site haul road in Portion 1.

(p)           Trial pit at Ma Sik Road.

(q)           Demolition of villagers houses in Portion 1 and 2.

(r)            Removal of asbestos containing materials in Portion 1 and 2.

 

Construction Programme

2.8         A copy of Contractors’ construction programme is provided in Appendix A.

Status of Environmental Licences, Notifications and Permits

2.9         A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.4.

 


 

Table 2.4       Status of Environmental Licenses, Notifications and Permits

Contract No.

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

ND/2019/01

EP-466/2013

21/11/2013

N/A

Valid

EP-467/2013/A

27/01/2017

N/A

Valid

EP-468/2013/A

27/01/2017

N/A

Valid

EP-470/2013

21/11/2013

N/A

Valid

ND/2019/02

EP-469/2013

21/11/2013

N/A

Valid

ND/2019/03

EP-468/2013/A

27/01/2017

N/A

Valid

EP-473/2013/A

27/01/2017

N/A

Valid

ND/2019/04

EP/473/2013/A

27/01/2017

N/A

Valid

EP/546/2017

16/11/2017

N/A

Valid

ND/2019/05

EP-473/2013/A

27/01/2017

N/A

Valid

ND/2019/06

EP-475/2013/A

13/01/2017

N/A

Valid

Construction Noise Permit (CNP)

ND/2019/01

GW-RN0011-21

17/01/2021

16/07/2021

Valid

GW-RN0143-21

16/03/2021

15/09/2021

Valid

GW-RN0168-21

23/03/2021

22/06/2021

Expired in the reporting period

GW-RN0224-21

07/04/2021

06/10/2021

Valid

GW-RN0381-21

08/06/2021

07/09/2021

Valid

GW-RN0413-21

23/06/2021

17/12/2021

Valid

ND/2019/02

GW-RN0221-21

26/03/2021

25/06/2021

Expired in the reporting period

ND/2019/03

GW-RN0131-21

01/03/2021

31/08/2021

Valid

ND/2019/04

GW-RN0393-21

16/06/2021

15/07/2021

Valid

ND/2019/05

GW-RN0178-21

21/03/2021

20/06/2021

Expired in the reporting period

GW-RN0247-21

14/04/2021

13/07/2021

Valid

GW-RN0275-21

05/05/2021

02/11/2021

Valid

GW-RN0332-21

01/06/2021

30/07/2021

Valid

ND/2019/06

GW-RN0903-20

25/01/2021

24/07/2021

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

ND/2019/01

451792

11/12/2019

N/A

Valid

ND/2019/02

454012

05/03/2020

N/A

Valid

ND/2019/03

452216

24/12/2019

N/A

Valid

452332

31/12/2019

N/A

Valid

452333

31/12/2019

N/A

Valid

ND/2019/04

461184

23/10/2020

N/A

Valid

ND/2019/05

454323

13/03/2020

N/A

Valid

ND/2019/06

449369

24/09/2019

N/A

Valid

ND/2019/07

459393

28/08/2020

N/A

Valid

Billing Account for Disposal of Construction Waste

ND/2019/01

7036265

17/01/2020

N/A

Valid

ND/2019/02

7036898

01/04/2020

N/A

Valid

ND/2019/03

7036378

22/01/2020

N/A

Valid

ND/2019/04

7038391

22/09/2020

N/A

Valid

ND/2019/05

7036901

01/04/2020

N/A

Valid

ND/2019/06

7035473

17/10/2019

N/A

Valid

ND/2019/07

7038309

14/09/2020

N/A

Valid

Registration of Chemical Waste Producer

ND/2019/01

5213-545-B2578-01

10/01/2020

N/A

Valid

ND/2019/02

5213-548-C4439-01

06/05/2020

N/A

Valid

ND/2019/03

5213-623-S4231-01

14/04/2020

N/A

Valid

ND/2019/04

5211-624-D2709-01

26/11/2020

N/A

Valid

ND/2019/05

5213-625-C4464-01

 

20/05/2020

N/A

Valid

ND/2019/06

5213-625-N2716-01

02/10/2019

N/A

Valid

ND/2019/07

5213-625-C4498-01

21/09/2020

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

ND/2019/01

WT00036071-2020

22/06/2020

30/06/2025

Valid

WT00036073-2020

22/06/2020

30/06/2025

Valid

WT00036067-2020

22/06/2020

30/06/2025

Valid

WT00036075-2020

22/06/2020

30/06/2025

Valid

WT00036076-2020

22/06/2020

30/06/2025

Valid

WT00037191-2020

02/02/2021

28/02/2025

Valid

WT00037204-2020

02/02/2021

28/02/2025

Valid

WT00037412-2021

15/04/2021

30/04/2026

Valid

WT00037564-2021

19/04/2021

30/04/2026

Valid

ND/2019/02

WT00036584-2020

21/10/2020

31/10/2025

Valid

WT00036952-2020

17/12/2020

31/12/2025

Valid

ND/2019/03

WT00035847-2020

12/08/2020

31/08/2025

Valid

ND/2019/04

WT00037539-2021

16/04/2021

30/04/2026

Valid

ND/2019/05

WT00036996-2020

22/12/2020

31/12/2025

Valid

ND/2019/06

WT00035415-2019

20/03/2020

31/03/2025

Valid

ND/2019/07

WT00037526-2021

04/05/2021

31/05/2026

Valid